1 MONGOLIA’S FIRST LARGE-SCALE WASTEWATER RECYCLING PLANT OPENS WWW.MONTSAME.MN PUBLISHED:2026/03/17      2 ULAANBAATAR READY TO ACCEPT PRIVATE INITIATIVES TO REDUCE AIR POLLUTION AND TRAFFIC CONGESTION WWW.GOGO.MN PUBLISHED:2026/03/17      3 ‘WE ARE BEING SILENCED’: MONGOLIAN POLITICIANS FACE JAIL AFTER VOTE CALLING FOR PM TO RESIGN WWW.THEGUARDIAN.COM PUBLISHED:2026/03/17      4 KOREA COMPLETES PRE-FEASIBILITY STUDY FOR MONGOLIA RAIL PROJECT WWW.EN.SEDAILY.COM PUBLISHED:2026/03/17      5 ULAANBAATAR TO EXPAND COOPERATION WITH FRANCE IN URBAN DEVELOPMENT WWW.MONTSAME.MN PUBLISHED:2026/03/17      6 SPRING SESSION TO TACKLE ECONOMIC CHALLENGES, TAX REFORM, GOVERNANCE ISSUES WWW.MONTSAME.MN PUBLISHED:2026/03/17      7 MONGOLIAN MINING CORPORATION ANNOUNCES 2025 ANNUAL RESULTS WWW.STOCKTITAN.NET PUBLISHED:2026/03/17      8 SOLAR POWER PLANT TO BE BUILT IN THE WESTERN REGION WWW.MONTSAME.MN PUBLISHED:2026/03/17      9 ECONOMIC GROWTH REMAINS STRONG AS FOREIGN INVESTMENT DECLINES WWW.MONTSAME.MN PUBLISHED:2026/03/17      10 HILTON ENTERS MONGOLIA WITH THE SIGNING OF CONRAD ULAANBAATAR, MARKING A NEW CHAPTER FOR LUXURY HOSPITALITY IN THE CAPITAL WWW.MARKETSCREENER.COM PUBLISHED:2026/03/17      “ОЮУТОЛГОЙН ШИНЭ ХЭЛЭЛЦЭЭ: МОНГОЛЫН ТАЛ ЭНЭ УДАА БУЦАХГҮЙ” WWW.EAGLE.MN НИЙТЭЛСЭН:2026/03/17     Х.ГАНХУЯГ: "ШИНЭ ХОРШОО"-ГООР 894 ТЭРБУМЫН ЗЭЭЛ ОЛГОСОН. ЦААШИД ЗЭЭЛИЙГ ТҮР ЗОГСООНО WWW.EGUUR.MN НИЙТЭЛСЭН:2026/03/17     САРЫН ДУНДАЖ ЦАЛИН ₮2.8 САЯ, ГОЛЧ ЦАЛИН 2.4 САЯ ТӨГРӨГ БАЙНА WWW.EGUUR.MN НИЙТЭЛСЭН:2026/03/17     МОНГОЛ, АНУ-ЫН ХАРИЛЦАА, ХАМТЫН АЖИЛЛАГААГ БҮХИЙ Л САЛБАРТ ӨРГӨЖҮҮЛЭХЭД ОНЦГОЙ АНХААРЧ АЖИЛЛАХАА ИЛЭРХИЙЛЭВ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/03/17     АНУ-ЫН МЯНГАНЫ СОРИЛТЫН КОРПОРАЦ МОНГОЛД ДАХИН БУЦАЛТГҮЙ ТУСЛАМЖ ҮЗҮҮЛЭХ ҮҮ? WWW.EAGLE.MN НИЙТЭЛСЭН:2026/03/17     БАРУУН БҮСЭД СЭРГЭЭГДЭХ ЭРЧИМ ХҮЧНИЙ НАРНЫ ЦАХИЛГААН СТАНЦ БАРИНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/03/17     ТРАССТ ӨРТӨЖ БУЙ ГАЗАР АШИГЛАГЧДЫН ГАЗАР АШИГЛАХ ЭРХИЙГ ХЭСЭГЧЛЭН ЦУЦАЛНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/03/16     "УЛААНБААТАР МЕТРО"-НЫ БАРИЛГА УГСРАЛТЫН ГҮЙЦЭТГЭГЧИЙГ ШАЛГАРУУЛАХ ТЕНДЕРИЙГ 07.03-НД НЭЭНЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/03/16     ЖУУЛЧДЫН ТОО ӨНГӨРСӨН ЖИЛЭЭС 38,6 ХУВИАР ӨСЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/03/16     ХАЯГДАЛ УС ДАХИН БОЛОВСРУУЛАХ ҮЙЛДВЭР АШИГЛАЛТАД ОРЛОО WWW.EAGLE.MN НИЙТЭЛСЭН:2026/03/16    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Denison Mines awarded $10m plus interest in Mongolia sale arbitration www.miningweekly.com

The London Court of International Arbitration (LCIA) has this week rendered a final award in favour of Canada-based Denison Mines for the arbitration proceedings between the company and Uranium Industry (UI), relating to the 2015 sale of Denison’s assets in Mongolia.

The arbitration panel declared that UI violated its obligations to Denison under the related agreements, and ordered UI to pay the company $10-million, plus interest at a rate of 5% a year from November 16, 2016, as well as certain legal and arbitration costs.

The arbitration panel also dismissed all other claims and counterclaims.

In November 2015, Denison completed the sale of its mining assets and operations located in Mongolia to UI pursuant to an amended and restated share purchase. The primary assets, at that time, were the exploration licences for the Hairhan, Haraat, Gurvan Saihan and Ulzit projects.

In September 2016, the Mineral Resources Authority of Mongolia formally issued mining licence certificates for all four projects, triggering Denison's right to receive additional post-closing contingent consideration of $10-million.

Denison has extended the payment due date of the mining licence receivable from November 16, 2016 to July 16, 2017, and agreed to a 5% a year interest rate.

The uranium exploration company turned to arbitration after the required payments were not made.