1 DRAFT TAX REFORM PACKAGE UP FOR PARLIAMENT SUBMISSION WWW.UBPOST.MN PUBLISHED:2025/12/26      2 MONGOLIA LAUNCHES WORLD'S FIRST 24/5 BLOCKCHAIN-BASED SECURITIES TRADING WWW.KIPOST.NET  PUBLISHED:2025/12/26      3 CONSTRUCTION OF OIL REFINERY AT 50 PERCENT COMPLETE WWW.MONTSAME.MN PUBLISHED:2025/12/26      4 FLS DRIVING INNOVATION AND SUSTAINABILITY IN MONGOLIA'S MINING INDUSTRY WWW.MONGOLIANMININGJOURNAL.COM  PUBLISHED:2025/12/26      5 MORE THAN 3,000 LAND PARCELS CLEARED IN ULAANBAATAR IN 2025 WWW.MONTSAME.MN PUBLISHED:2025/12/26      6 LAND ALLOCATION REQUESTS TO BE PROCESSED STARTING DECEMBER WWW.MONTSAME.MN PUBLISHED:2025/12/26      7 SCHOOL NO.49 BECOMES 100% SOLAR-POWERED WWW.GOGO.MN PUBLISHED:2025/12/26      8 CONSTRUCTION OF WASTE-TO-ENERGY PLANT TO BEGIN IN 2026 WWW.GOGO.MN PUBLISHED:2025/12/25      9 SECURITIES TRADING REACHES MNT 879.5 BILLION WWW.MONTSAME.MN PUBLISHED:2025/12/25      10 PROPOSAL, CONCLUSION ON DETERMINING THE STATE OWNERSHIP STAKES IN 'ACHIT IKHT', 'ERDENET MINING', AND 'ZES ERDENIIN KHUVI' LLCS TO BE DISCUSSED WWW.MONTSAME.MN PUBLISHED:2025/12/25      Ж.ЧИНБҮРЭН: ХДХВ/ДОХ-ЫН ХАЛДВАРТАЙ 12 ИРГЭН ХЯНАЛТАД ОРОХГҮЙ АЛДАГДСАН НЬ ҮНЭН WWW.GOGO.MN НИЙТЭЛСЭН:2025/12/26     БАТ-ӨЛЗИЙ, ХУЖИРТ СУМЫГ ХОЛБОСОН АВТО ЗАМЫГ УЛСЫН КОМИСС ХҮЛЭЭН АВЛАА WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/12/26     "ОЮУТОЛГОЙ"-Н ТОГТООЛЫН ТӨСӨЛ БАТЛАГДАЖ, ТҮР ХОРОО ТАТАН БУУГДЛАА WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/26     ГОВЬ-АЛТАЙ АЙМГИЙН АЛТАЙ СУМ ЦАХИЛГААНД БҮРЭН ХОЛБОГДЛОО WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/26     ЭНЭ ОНД НИЙСЛЭЛД 16.3 КМ БОРООНЫ УС ЗАЙЛУУЛАХ ШУГАМ УГСАРЧЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/26     ТӨРИЙН ӨМЧИТ КОМПАНИУД ДНБ-ИЙ 74 ХУВЬТАЙ ТЭНЦЭХ ХӨРӨНГӨТЭЙ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/26     УЛААНБААТАР ХОТОД БЕНЗИН, ДИЗЕЛИЙН ТҮЛШНИЙ НИЙЛҮҮЛЭЛТ ТОГТВОРЖСОН WWW.EAGLE.MN НИЙТЭЛСЭН:2025/12/26     ГАЗАР ЭЗЭМШИХ ГЭРЧИЛГЭЭГ ОЛГОЖ ЭХЭЛНЭ WWW.NEWS.MN НИЙТЭЛСЭН:2025/12/25     ИРЭХ ОНЫ ЭХНИЙ УЛИРАЛД “АЧИТ ИХТ”, “ЭРДМИН”, “ЗЭС ЭРДЭНИЙН ХУВЬ” ХХК-Д ТӨРИЙН ЭЗЭМШЛИЙН ХУВЬ ХЭМЖЭЭГ ТОГТООХЫГ ҮҮРЭГДЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2025/12/25     2026 ОНД ЮУНД ХӨРӨНГӨ ОРУУЛБАЛ АШИГТАЙ БАЙХ ВЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/25    

Rio Tinto avoids footing $1bn bill for new power plant in Mongolia www.ft.com

Rio Tinto has been spared from footing the bill for a $1bn coal-fired power station in Mongolia, where the miner is developing a huge underground copper deposit in the Gobi Desert.

The Anglo-Australian group said on Monday that a government-built plant at the Tavan Tolgoi coalfield would provide the long-awaited domestic power source for its $6.8bn Oyu Tolgoi project.

The deal comes days after the ruling Mongolian People’s party scored a landslide general election victory and will give the government greater influence over the project, the country's biggest source of foreign direct investment.

Analysts at Canaccord Genuity said the deal handed Mongolia a “valuable bargaining chip” should there be further disputes over the investment agreement that underpins development of the underground mine and that Ulaanbaatar wants to improve.

“While the elimination of a funding requirement on the order of $1bn is positive, in a world awash with historically cheap capital we view this as a limited benefit relative to the negative strategic and operational implications,” said analysts at Canaccord.

Twice weekly newsletter

Energy is the world’s indispensable business and Energy Source is its newsletter. Every Tuesday and Thursday, direct to your inbox, Energy Source brings you essential news, forward-thinking analysis and insider intelligence. Sign up here.

“In addition, we are unclear as to what the impact on the mine’s operating costs will be as the government seeks to recoup a meaningful return on its investment.

Mongolia owns 34 per cent of OT, with the remainder owned by Turquoise Hill Resources, a Canadian-listed company. In turn, Rio owns 50.8 per cent of Turquoise and manages the mining operations.

The existing surface mine at OT is powered by coal-fired electricity that is imported from neighbouring China via overhead cables, but Mongolia has demanded that Rio find a domestic power source.

In February, Rio said a 300 megawatt coal-fired power station costing almost $1bn was the most likely domestic solution, a proposal that was subsequently knocked back by the government.

Under the new agreement, the parties will work towards finalising the commercial terms of a power purchase agreement by March 2021.

Subject to negotiations, Rio will continue to buy power from China for the surface mine at OT until the plant is commissioned and can supply reliable and continuous power from 2025.

The underground expansion of OT is one of Rio’s most important growth projects. When finished it will make the mine one of the world’s largest sources of copper, producing more than 500,000 tonnes a year of the metal used in everything from cars to air conditioning units.

However, the project has suffered setbacks. In July 2019 Rio said the expansion was running 16 to 30 months behind schedule and would cost $1.2bn to $1.9bn more than forecast, although it has since said the delay and cost overrun will be near the middle of that range.

“This was always a Catch-22 for Rio,” said Henry Steel, of Odey Asset Management. “Either Rio build the power plant and have to source the coal from Tavan Tolgoi, allowing the Mongolians to squeeze them on the coal price. Or the Mongolians build the power plant and squeeze Rio on the power price. Both are as bad as each other.”



Published Date:2020-07-01