1 14TH MBD MISSION FOR MBCC'S "DOING BUSINESS WITH MONGOLIA SEMINAR & CHRISTMAS RECEPTION" AND BUSINESS PROGRAM DEC 08- 14. 2025 LONDON, UK WWW.MONGOLIANBUSINESSDATABASE.COM PUBLISHED:2025/09/16      2 IMF WRAPS UP 2025 ARTICLE IV TALKS WITH MONGOLIA WWW.IMF.ORG PUBLISHED:2025/09/16      3 POSCO INTERNATIONAL TO LAUNCH WASTEWATER HEAT DISTRICT HEATING PROJECT IN MONGOLIA WWW.CM.ASIAE.CO.KR  PUBLISHED:2025/09/16      4 MONGOLIA'S EXTERNAL DEBT UP 12.7 PCT IN Q2 2025 WWW.NEWS.AZ PUBLISHED:2025/09/16      5 2025 AUTUMN SESSION OF THE STATE GREAT KHURAL COMMENCES WITH STRUCTURAL REFORMS WWW.MONTSAME.MN PUBLISHED:2025/09/16      6 MONGOLIA SURPASSES 617,000 TOURIST ARRIVALS BY MID-SEPTEMBER 2025 WWW.MONTSAME.MN PUBLISHED:2025/09/16      7 ODD-EVEN TRAFFIC RESTRICTION CONCLUDES WWW.UBPOST.MN PUBLISHED:2025/09/15      8 MMC ANNOUNCES FIRST GOLD POUR COMPLETED AT THE BAYAN KHUNDII MINE IN MONGOLIA WWW.SG.FINANCE.YAHOO.COM  PUBLISHED:2025/09/15      9 MKE LAUNCHES CARTRIDGE PRODUCTION LINE IN MONGOLIA WWW.RAILLYNEWS.COM  PUBLISHED:2025/09/15      10 MONGOLIA’S LARGEST MINING EVENT HIGHLIGHTS INVESTMENT AND RESPONSIBLE MINING WWW.MONTSAME.MN PUBLISHED:2025/09/14      14 ДЭХЬ УДААГИЙН MBCCI’S “ DOING BUSINESS WITH MONGOLIA SEMINAR & CHRISTMAS RECEPTION” B2B NETWORKING БОЛОН БИЗНЕС ХӨТӨЛБӨР 2025 ОНЫ 12 САРЫН 08 -13 ЛОНДОН ХОТ, ИХ БРИТАНИ WWW.MONGOLIANBUSINESSDATABASE.COM НИЙТЭЛСЭН:2025/09/16     ЭДИЙН ЗАСГИЙН ТӨРӨЛЖИЛТИЙН ИНДЕКСЭЭР МОНГОЛ УЛС 145 ОРНООС 139-Д БИЧИГДЖЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2025/09/16     ӨНӨӨДӨР: “СЭЛБЭ 20 МИНУТЫН ХОТ”-ЫН ДАРААГИЙН ЭЭЛЖИЙН ОРОН СУУЦНЫ ТӨСЛИЙН БҮТЭЭН БАЙГУУЛАЛТЫГ ЭХЛҮҮЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/09/16     ШЭНЬ МИНЬЖУАНЬ: БНХАУ МОНГОЛ УЛСЫГ ШХАБ-ЫН ГЭР БҮЛД НЭГДЭЖ, ХАМТЫН АЖИЛЛАГААГАА ӨРГӨЖҮҮЛЭХИЙГ УРЬСАН WWW.ITOIM.MN НИЙТЭЛСЭН:2025/09/15     Г.ЗАНДАШАТАР: ТӨРИЙН ДАНХАР БҮТЦИЙГ ХУМИХ АЖИЛ ИРЭХ ОНД Ч ҮРГЭЛЖИЛНЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/09/15     Ц.ТУВААН: НҮҮРСНИЙ ҮНЭ 3 САР ТУТАМ ШИНЭЧЛЭГДЭНЭ. ГЭРЭЭНД ЯМАР Ч НУУЦ БАЙХГҮЙ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/09/15     ХАНЫН МАТЕРИАЛД 1800 АЙЛЫН ОРОН СУУЦ БАРИХ ТӨСЛИЙН ГҮЙЦЭТГЭГЧ ШАЛГАРЛАА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/09/15     "ТАТВАРЫН ХЭТ ӨНДӨР ТООЦОО БИЗНЕС ЭРХЛЭГЧДИЙГ ХААЛГАА БАРИХАД ХҮРГЭНЭ" WWW.NEWS.MN НИЙТЭЛСЭН:2025/09/15     ГАДААД ХУДАЛДААНЫ НӨХЦӨЛИЙН ИНДЕКС ӨМНӨХ ОНООС 4.1 ХУВИАР БУУРЧЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2025/09/15     ЭХНИЙ НАЙМАН САРЫН БАЙДЛААР 600 МЯНГАН ЖУУЛЧИН ИРЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/09/15    

The world's largest gold project, just got a whole lot bigger www.mining.com

During the final days of 2014 Canada's minister of the environment gave the green light to Seabridge Gold's KSM project in northern British Columbia, the world's largest undeveloped gold-copper project by reserves.

The federal and provincial environmental assessment process took nearly seven-years and KSM was only the second metal mine in five years to receive approval.

A new preliminary economic impact study released by Toronto-based Seabridge on Thursday, the already ambitious project takes another leap forward.

According to a statement, Seabridge now envisages a much larger operation than the one outlined in the preliminary feasibility study released last month and in the process improves both the environmental impact and economics of KSM.

The PEA calls for mill throughput of 170,000 tonnes per day, 40,000 tonnes more than the earlier study which Seabridge says can be done without significant redesign of facilities. Initial capital costs have been increased by just less than 10% to $5.5 billion.

In the PEA the bulk of the operations are moved underground and using the block-cave method Seabridge says it can reduce waste rock by a whopping 81% or 2.4 billion tonnes over the 51 year life of the mine.

By vastly increasing the amount of copper mined life of mine operating costs are now a negative $179 an ounce while all-in costs fall to just $358 an ounce.

Measured and Indicated Mineral Resources at KSM are estimated at 2.9 billion tonnes grading 0.54 grams per tonne gold, 0.21% copper and 2.7 grams per tonne silver which translates into 49.8 million ounces of gold, 13.6 billion pounds of copper and 253 million ounces of silver.

During the first seven years of operation annual gold output would top 1 million ounces and life of mine annual production is estimated at 592,000 ounces of gold, 286,000 pounds of copper and 2.8 million ounces of silver.

Seabridge (TSX:SEA) (NYSE:SA) is worth just over $530 million on the New York Stock Exchange, up 21% in value year to date.



Published Date:2016-10-07