1 REGIONAL INITIATIVE ON DUST STORMS TO BE LAUNCHED DURING COP17 WWW.MONTSAME.MN PUBLISHED:2026/07/31      2 MONGOLIA TO IMPORT 6,000 TONS OF AI-92 AND AI-95 GASOLINE FROM CHINA WWW.GOGO.MN PUBLISHED:2026/07/31      3 MONGOLIA, JAPAN EXPAND ENERGY EDUCATION PARTNERSHIP WWW.MYANMARITV.COM PUBLISHED:2026/07/31      4 SEOUL’S INTEREST IN MONGOLIA’S RARE EARTHS WWW.ASIANEWS.IT PUBLISHED:2026/07/31      5 RUNIC INSCRIPTIONS 1300 YEARS OLD DISCOVERED IN MONGOLIA WWW.OPEN.KG PUBLISHED:2026/07/31      6 S. KOREA HELPS MONGOLIA BUILD CULTURAL HERITAGE CONSERVATION PROGRAM WWW.KOREAHERALD.COM PUBLISHED:2026/07/31      7 THERE ARE SOME REASONS TO SUGGEST THAT MONGOLIA ENERGY'S (HKG:276) EARNINGS ARE A POOR REFLECTION OF PROFITABILITY WWW.SIMPLYWALL.ST PUBLISHED:2026/07/31      8 PROTECTION ZONES TO BE ESTABLISHED FOR CEMETERY COMPLEXES OF THE HUNNU NOBILITY WWW.MONTSAME.MN PUBLISHED:2026/07/30      9 MINISTERS INSTRUCTED TO ADVANCE POWER PLANT PROJECTS AHEAD OF WINTER WWW.MONTSAME.MN PUBLISHED:2026/07/30      10 VEHICLE TRAFFIC TO BE REGULATED BY EVEN, ODD LICENSE PLATE NUMBERS FROM AUGUST 15 TO SEPTEMBER 12 WWW.MONTSAME.MN PUBLISHED:2026/07/30      Б.ДАШПҮРЭВ: МАРГААШААС ШАТАХУУНЫ ТҮГЭЭЛТ НЭМЭГДЭЖ, НӨХЦӨЛ БАЙДАЛ ЗӨӨЛӨРНӨ ГЭЖ ХАРЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/07/31     БҮСЧИЛСЭН ХӨГЖИЛ, ГАМШГИЙН ЭРСДЭЛИЙГ БУУРУУЛАХ ЧИГЛЭЛЭЭР НҮБ-ТАЙ ХАМТЫН АЖИЛЛАГААГАА ӨРГӨЖҮҮЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/07/31     Н.УЧРАЛ "РОСНЕФТЬ"-ИЙН ЗАХИРАЛ ИГОРЬ СЕЧИНД ШАТАХУУНТАЙ ХОЛБООТОЙ АСУУДЛААР ЗАХИДАЛ ИЛГЭЭЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/07/31     БАГА ОРЛОГОТОЙ ИРГЭДИЙН ОРЛОГОД ТАТВАР НОГДУУЛАХГҮЙ БАЙХ ЭРХ ЗҮЙН ОРЧНЫГ БҮРДҮҮЛЭВ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/07/31     ОЮУ ТОЛГОЙ КОМПАНИ 2026 ОНЫ II УЛИРАЛД УЛСАД 834 ТЭРБУМ ТӨГРӨГ ТӨВЛӨРҮҮЛЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/07/31     ГАЗРЫН ТОСНЫ ХАЙГУУЛЫН НЭЭЛТТЭЙ СОНГОН ШАЛГАРУУЛАЛТ ЗАРЛАЛАА WWW.GOGO.MN НИЙТЭЛСЭН:2026/07/31     ТАЛУУДЫН 16, 17 ДУГААР БАГА ХУРЛЫН ДАРГА НАР ХАМТЫН АЖИЛЛАГААГАА ҮРГЭЛЖЛҮҮЛЭХЭЭР САНАЛ НЭГДЛЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/07/31     ЕВРОПЫН ХОЛБООНЫ САНХҮҮЖИЛТТЭЙ “ДУЛААН ШИЙДЭЛ II” ТӨСӨЛ 2022-2026 ОНЫ ХООРОНД АМЖИЛТТАЙ ХЭРЭГЖИЖ ДУУСЛАА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/07/30     АМГТГ: УЛСЫН ХЭМЖЭЭНД АИ-92 БЕНЗИНИЙ 17, ДИЗЕЛЬ ТҮЛШНИЙ 23 ХОНОГИЙН НӨӨЦТЭЙ БАЙНА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/07/30     Б.ПҮРЭВДАГВА: НАЙМДУГААР САРЫН 15-НААС АВТОМАШИНЫГ ТЭГШ, СОНДГОЙ ДУГААРААР ХӨДӨЛГӨӨНД ОРОЛЦУУЛНА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/07/30    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Russia offers to Cooperate in Tavantolgoi TPP Construction Project www.montsame.mn

The government action plan includes building new energy sources to meet the growing electricity demand. From this perspective, it was decided to make new energy sources available in three main scopes:
To increase and expand the capacity of existing energy sources.
To build new sources with pulverized coal combustion technology.
To make renewable energy sources available.
The construction project of the Tavantolgoi Thermal Power Plant (TPP) with a capacity of 450 MW is one of the significant projects to build new energy sources that are operated with pulverized coal combustion technology. In April 2020, a resolution was issued by the Government that it will finance the project through its own resource. According to the resolution, Erdenes Tavantolgoi JSC will allocate 30 percent of the financing through owning shares of the plant and the remaining 70 percent will be financed by a loan through the government’s loan guarantee. In this framework, the government submitted its request for a debt guarantee to the State Great Khural. However, the State Great Khural refused to issue the debt guarantee due to the debt ceiling, stopping the project.
The Minister of Energy, B. Choijilsuren, stated that the Russian side has put forth a proposal to cooperate with Mongolia to continue the project.
Specifically, some Russian commercial banks have expressed their interest in financing the project. According to the Ministry, the tender for Tavantolgoi TPP will be announced before January, and the participants will be selected and contracted by the end of May 2023. It is planned to commence construction in the second half of next year and to be commissioned in the second half of 2026. Furthermore, Minister B. Choijilsuren highlighted that no offtake agreements will be established for this project.


Published Date:2022-12-07