1 14TH MBD MISSION FOR MBCC'S "DOING BUSINESS WITH MONGOLIA SEMINAR & CHRISTMAS RECEPTION" AND BUSINESS PROGRAM DEC 08- 14. 2025 LONDON, UK WWW.MONGOLIANBUSINESSDATABASE.COM PUBLISHED:2025/09/16      2 IMF WRAPS UP 2025 ARTICLE IV TALKS WITH MONGOLIA WWW.IMF.ORG PUBLISHED:2025/09/16      3 POSCO INTERNATIONAL TO LAUNCH WASTEWATER HEAT DISTRICT HEATING PROJECT IN MONGOLIA WWW.CM.ASIAE.CO.KR  PUBLISHED:2025/09/16      4 MONGOLIA'S EXTERNAL DEBT UP 12.7 PCT IN Q2 2025 WWW.NEWS.AZ PUBLISHED:2025/09/16      5 2025 AUTUMN SESSION OF THE STATE GREAT KHURAL COMMENCES WITH STRUCTURAL REFORMS WWW.MONTSAME.MN PUBLISHED:2025/09/16      6 MONGOLIA SURPASSES 617,000 TOURIST ARRIVALS BY MID-SEPTEMBER 2025 WWW.MONTSAME.MN PUBLISHED:2025/09/16      7 ODD-EVEN TRAFFIC RESTRICTION CONCLUDES WWW.UBPOST.MN PUBLISHED:2025/09/15      8 MMC ANNOUNCES FIRST GOLD POUR COMPLETED AT THE BAYAN KHUNDII MINE IN MONGOLIA WWW.SG.FINANCE.YAHOO.COM  PUBLISHED:2025/09/15      9 MKE LAUNCHES CARTRIDGE PRODUCTION LINE IN MONGOLIA WWW.RAILLYNEWS.COM  PUBLISHED:2025/09/15      10 MONGOLIA’S LARGEST MINING EVENT HIGHLIGHTS INVESTMENT AND RESPONSIBLE MINING WWW.MONTSAME.MN PUBLISHED:2025/09/14      14 ДЭХЬ УДААГИЙН MBCCI’S “ DOING BUSINESS WITH MONGOLIA SEMINAR & CHRISTMAS RECEPTION” B2B NETWORKING БОЛОН БИЗНЕС ХӨТӨЛБӨР 2025 ОНЫ 12 САРЫН 08 -13 ЛОНДОН ХОТ, ИХ БРИТАНИ WWW.MONGOLIANBUSINESSDATABASE.COM НИЙТЭЛСЭН:2025/09/16     ЭДИЙН ЗАСГИЙН ТӨРӨЛЖИЛТИЙН ИНДЕКСЭЭР МОНГОЛ УЛС 145 ОРНООС 139-Д БИЧИГДЖЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2025/09/16     ӨНӨӨДӨР: “СЭЛБЭ 20 МИНУТЫН ХОТ”-ЫН ДАРААГИЙН ЭЭЛЖИЙН ОРОН СУУЦНЫ ТӨСЛИЙН БҮТЭЭН БАЙГУУЛАЛТЫГ ЭХЛҮҮЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/09/16     ШЭНЬ МИНЬЖУАНЬ: БНХАУ МОНГОЛ УЛСЫГ ШХАБ-ЫН ГЭР БҮЛД НЭГДЭЖ, ХАМТЫН АЖИЛЛАГААГАА ӨРГӨЖҮҮЛЭХИЙГ УРЬСАН WWW.ITOIM.MN НИЙТЭЛСЭН:2025/09/15     Г.ЗАНДАШАТАР: ТӨРИЙН ДАНХАР БҮТЦИЙГ ХУМИХ АЖИЛ ИРЭХ ОНД Ч ҮРГЭЛЖИЛНЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/09/15     Ц.ТУВААН: НҮҮРСНИЙ ҮНЭ 3 САР ТУТАМ ШИНЭЧЛЭГДЭНЭ. ГЭРЭЭНД ЯМАР Ч НУУЦ БАЙХГҮЙ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/09/15     ХАНЫН МАТЕРИАЛД 1800 АЙЛЫН ОРОН СУУЦ БАРИХ ТӨСЛИЙН ГҮЙЦЭТГЭГЧ ШАЛГАРЛАА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/09/15     "ТАТВАРЫН ХЭТ ӨНДӨР ТООЦОО БИЗНЕС ЭРХЛЭГЧДИЙГ ХААЛГАА БАРИХАД ХҮРГЭНЭ" WWW.NEWS.MN НИЙТЭЛСЭН:2025/09/15     ГАДААД ХУДАЛДААНЫ НӨХЦӨЛИЙН ИНДЕКС ӨМНӨХ ОНООС 4.1 ХУВИАР БУУРЧЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2025/09/15     ЭХНИЙ НАЙМАН САРЫН БАЙДЛААР 600 МЯНГАН ЖУУЛЧИН ИРЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/09/15    

Operational update - 3D seismic campaign www.petromatadgroup.com

Seismic Acquisition Campaign

· The Company has signed the contract with BGP Inc (a divisions of China National Petroleum Company) for 3D and 2D seismic work in Blocks IV and V

· Preliminary mobilization and camp construction is already underway, allowing for immediate preparatory and long lead work to begin

· The 218km2 3D survey in Blocks IV and V will be the first ever 3D seismic acquired in western Mongolia

Further to its announcement of 4 October 2017, the Company is pleased to provide the timelines and details regarding the planned seismic work programme following the signing of the BGP contract, as detailed further below. The 220km2 3D survey will be the first ever 3D seismic acquired in western Mongolia. It will be conducted over the Tugrug Basin of eastern Block V, a longstanding priority basin for Petro Matad with a proven working petroleum system including mature source rock, reservoir rocks with good porosity & permeability and live hydrocarbon staining found in previous stratigraphic coring operations. 

The survey in the Tugrug Basin of Block V is expected to begin 3D data recording operations by mid-November and to be completed by mid-December, 2017. The crew will then begin a 150 line km infill 2D survey in the same area, extending outward from the 3D, to cover surrounding prospects and leads. No camp move is required so the 2D acquisition can begin seamlessly after completion of the 3D. As such, the estimated completion date of the Tugrug Basin 2D program will be two weeks after the 3D. 

Following completion of the Tugrug Basin 2D, the crew and camp will move 350km NW into Block IV to acquire a new 205 line km 2D seismic grid over the Khangai Basin. The Khangai Basin is a deep and prospective basin in north-central Block IV. It has been high graded following the results of the airborne FTG/HRAM survey of 2015. Whilst only two regional 2D seismic lines currently cross the Khangai Basin, these lines show adequate basinal depths (3500M-4000M) and prospective structural and stratigraphic configurations. The Khangai Basin 2D survey is projected to start in late December, and complete before the end of January 2018. 

Processing of both the 3D and 2D data has been contracted to Western GeCo (a division of Schlumberger Limited). The data will be delivered to the processors in near real time to allow maximum efficiency and return of processed data to the Company. Both the 3D and 2D programs are focused on high grading specific leads and prospects to potential drilling targets for the 2018/19 operational seasons.



Published Date:2017-10-25