1 N.UCHRAL: FINISH THE NAADAM FESTIVAL, PREPARE FOR WINTER WWW.GOGO.MN PUBLISHED:2026/07/27      2 OVER 2,800 DELEGATES EXPECTED FOR COP17 IN MONGOLIA WWW.GOGO.MN PUBLISHED:2026/07/27      3 VICTORIA DELMON ANNOUNCED AS WORLD BANK GROUP NEW COUNTRY MANAGER FOR MONGOLIA WWW.MONTSAME.MN PUBLISHED:2026/07/27      4 AI IN GOVERNMENT WWW.GOGO.MN PUBLISHED:2026/07/27      5 SA GAS COMPANY SIGNS BILLION-DOLLAR AGREEMENT WWW.INDAILYSA.COM.AU/ PUBLISHED:2026/07/27      6 MONGOLIA’S HUNNU NOBILITY CEMETERY COMPLEXES ADDED TO UNESCO WORLD HERITAGE LIST WWW.QAZINFORM.COM PUBLISHED:2026/07/27      7 MOM'S TOUCH OPENS 20TH STORE IN MONGOLIA, BECOMES NO. 2 QSR BRAND WWW.EN.SEDAILY.COM PUBLISHED:2026/07/27      8 GOVERNMENT DOMESTIC SECURITIES WORTH MNT 10 BILLION TRADED WWW.MONTSAME.MN PUBLISHED:2026/07/24      9 TMK ENERGY APPOINTS U.S. PRIVATE EQUITY VETERAN STEVE SKINNER AS COO TO DRIVE MONGOLIAN GAS PROJECT WWW.TIPRANKS.COM PUBLISHED:2026/07/24      10 ERDENE STOCK TRACKS LATEST RESOURCE UPDATE AS MONGOLIA GOLD PROJECT ADVANCES WWW.AD-HOC-NEWS.DE PUBLISHED:2026/07/24      Б.МӨНХТАМИР: COP17 ХУРАЛД УЛСЫН ТӨСВӨӨС 267 ТЭРБУМ ТӨГРӨГ ЗАРЦУУЛНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/07/27     МОНГОЛБАНК: ИНФЛЯЦ 2027 ОНООС ЗОРИЛТОТ ТҮВШИНД ТОГТВОРЖИХ ТӨЛӨВТЭЙ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/07/27     ДЭЛХИЙН БАНК ГРУППИЙН МОНГОЛ ДАХЬ СУУРИН ТӨЛӨӨЛӨГЧӨӨР ВИКТОРИА ДЕЛМОН ТОМИЛОГДЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/07/27     ЕРӨНХИЙ САЙД Н.УЧРАЛ: НАЙР НААДМАА ДУУСГА. ӨВӨЛДӨӨ БЭЛД WWW.GOGO.MN НИЙТЭЛСЭН:2026/07/27     ЗЭСИЙН ЭКСПОРТ НҮҮРСИЙГ ДАВЖ, ЭДИЙН ЗАСГИЙН ШИНЭ ТУЛГУУР БОЛЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/07/27     ДАМБАДАРЖАА ДУЛААНЫ СТАНЦЫГ ЭНЭ ОНД АШИГЛАЛТАД ОРУУЛНА WWW.NEWS.MN НИЙТЭЛСЭН:2026/07/27     ЖУУЛЧДЫН ТОО ӨМНӨХ ОНЫ МӨН ҮЕЭС 13.7 ХУВИАР НЭМЭГДЖЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/07/27     МОНГОЛ УЛСААС НҮБ-ЫН АНДЭЗНК-ЫН ДЭРГЭД СУУХ БАЙНГЫН ТӨЛӨӨЛӨГЧ В.ОЮУ ИТГЭМЖЛЭХ ЗАХИДЛАА ГАРДУУЛАВ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/07/24     “GLOBAL SILHOUETTE” ОЛОН УЛСЫН ҮЗЭСГЭЛЭН ХААН ГАЛЕРЕЙД НЭЭЛТЭЭ ХИЙЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/07/24     РИО ТИНТО-ТОЙ ХИЙХ ХЭЛЭЛЦЭЭРИЙН НОГДОЛ АШИГ АВАХ АЖЛЫН ХЭСГИЙГ САНГИЙН САЙД АХАЛНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/07/24    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Operational update - 3D seismic campaign www.petromatadgroup.com

Seismic Acquisition Campaign

· The Company has signed the contract with BGP Inc (a divisions of China National Petroleum Company) for 3D and 2D seismic work in Blocks IV and V

· Preliminary mobilization and camp construction is already underway, allowing for immediate preparatory and long lead work to begin

· The 218km2 3D survey in Blocks IV and V will be the first ever 3D seismic acquired in western Mongolia

Further to its announcement of 4 October 2017, the Company is pleased to provide the timelines and details regarding the planned seismic work programme following the signing of the BGP contract, as detailed further below. The 220km2 3D survey will be the first ever 3D seismic acquired in western Mongolia. It will be conducted over the Tugrug Basin of eastern Block V, a longstanding priority basin for Petro Matad with a proven working petroleum system including mature source rock, reservoir rocks with good porosity & permeability and live hydrocarbon staining found in previous stratigraphic coring operations. 

The survey in the Tugrug Basin of Block V is expected to begin 3D data recording operations by mid-November and to be completed by mid-December, 2017. The crew will then begin a 150 line km infill 2D survey in the same area, extending outward from the 3D, to cover surrounding prospects and leads. No camp move is required so the 2D acquisition can begin seamlessly after completion of the 3D. As such, the estimated completion date of the Tugrug Basin 2D program will be two weeks after the 3D. 

Following completion of the Tugrug Basin 2D, the crew and camp will move 350km NW into Block IV to acquire a new 205 line km 2D seismic grid over the Khangai Basin. The Khangai Basin is a deep and prospective basin in north-central Block IV. It has been high graded following the results of the airborne FTG/HRAM survey of 2015. Whilst only two regional 2D seismic lines currently cross the Khangai Basin, these lines show adequate basinal depths (3500M-4000M) and prospective structural and stratigraphic configurations. The Khangai Basin 2D survey is projected to start in late December, and complete before the end of January 2018. 

Processing of both the 3D and 2D data has been contracted to Western GeCo (a division of Schlumberger Limited). The data will be delivered to the processors in near real time to allow maximum efficiency and return of processed data to the Company. Both the 3D and 2D programs are focused on high grading specific leads and prospects to potential drilling targets for the 2018/19 operational seasons.



Published Date:2017-10-25