1 PRIME MINISTER OYUN-ERDENE VISITS EGIIN GOL HYDROPOWER PLANT PROJECT SITE WWW.MONTSAME.MN PUBLISHED:2025/04/30      2 ‘I FELT CAUGHT BETWEEN CULTURES’: MONGOLIAN MUSICIAN ENJI ON HER BEGUILING, BORDER-CROSSING MUSIC WWW.THEGUARDIAN.COM PUBLISHED:2025/04/30      3 POWER OF SIBERIA 2: ECONOMIC OPPORTUNITY OR GEOPOLITICAL RISK FOR MONGOLIA? WWW.THEDIPLOMAT.COM PUBLISHED:2025/04/29      4 UNITED AIRLINES TO LAUNCH FLIGHTS TO MONGOLIA IN MAY WWW.MONTSAME.MN PUBLISHED:2025/04/29      5 SIGNATURE OF OIL SALES AGREEMENT FOR BLOCK XX PRODUCTION WWW.RESEARCH-TREE.COM  PUBLISHED:2025/04/29      6 MONGOLIA ISSUES E-VISAS TO 11,575 FOREIGNERS IN Q1 WWW.XINHUANET.COM PUBLISHED:2025/04/29      7 KOREA AN IDEAL PARTNER TO HELP MONGOLIA GROW, SEOUL'S ENVOY SAYS WWW.KOREAJOONGANGDAILY.JOINS.COM  PUBLISHED:2025/04/29      8 MONGOLIA TO HOST THE 30TH ANNUAL GENERAL MEETING OF ASIA SECURITIES FORUM WWW.MONTSAME.MN PUBLISHED:2025/04/29      9 BAGAKHANGAI-KHUSHIG VALLEY RAILWAY PROJECT LAUNCHES WWW.UBPOST.MN PUBLISHED:2025/04/29      10 THE MONGOLIAN BUSINESS ENVIRONMENT AND FDI: CHALLENGES AND OPPORTUNITY WWW.MELVILLEDALAI.COM  PUBLISHED:2025/04/28      849 ТЭРБУМЫН ӨРТӨГТЭЙ "ГАШУУНСУХАЙТ-ГАНЦМОД" БООМТЫН ТЭЗҮ-Д ТУРШЛАГАГҮЙ, МОНГОЛ 2 КОМПАНИ ҮНИЙН САНАЛ ИРҮҮЛЭВ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/04/30     ХУУЛЬ БУСААР АШИГЛАЖ БАЙСАН "БОГД УУЛ" СУВИЛЛЫГ НИЙСЛЭЛ ӨМЧЛӨЛДӨӨ БУЦААВ WWW.NEWS.MN НИЙТЭЛСЭН:2025/04/30     МЕТРО БАРИХ ТӨСЛИЙГ ГҮЙЦЭТГЭХЭЭР САНАЛАА ӨГСӨН МОНГОЛЫН ГУРВАН КОМПАНИ WWW.EAGLE.MN НИЙТЭЛСЭН:2025/04/30     "UPC RENEWABLES" КОМПАНИТАЙ ХАМТРАН 2400 МВТ-ЫН ХҮЧИН ЧАДАЛТАЙ САЛХИН ЦАХИЛГААН СТАНЦ БАРИХААР БОЛОВ WWW.EAGLE.MN НИЙТЭЛСЭН:2025/04/30     ОРОСЫН МОНГОЛ УЛС ДАХЬ ТОМООХОН ТӨСЛҮҮД ДЭЭР “ГАР БАРИХ” СОНИРХОЛ БА АМБИЦ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/04/30     МОНГОЛ, АНУ-ЫН ХООРОНД ТАВДУГААР САРЫН 1-НЭЭС НИСЛЭГ ҮЙЛДЭНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/04/29     ЕРӨНХИЙ САЙД Л.ОЮУН-ЭРДЭНЭ ЭГИЙН ГОЛЫН УЦС-ЫН ТӨСЛИЙН ТАЛБАЙД АЖИЛЛАЖ БАЙНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/04/29     Ц.ТОД-ЭРДЭНЭ: БИЧИГТ БООМТЫН ЕРӨНХИЙ ТӨЛӨВЛӨГӨӨ БАТЛАГДВАЛ БУСАД БҮТЭЭН БАЙГУУЛАЛТЫН АЖЛУУД ЭХЛЭХ БОЛОМЖ БҮРДЭНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/04/29     MCS-ИЙН ХОЁР ДАХЬ “УХАА ХУДАГ”: БНХАУ, АВСТРАЛИТАЙ ХАМТРАН ЭЗЭМШДЭГ БАРУУН НАРАНГИЙН ХАЙГУУЛЫГ УЛСЫН ТӨСВӨӨР ХИЙЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/04/29     АМ.ДОЛЛАРЫН ХАНШ ТОГТВОРЖИЖ 3595 ТӨГРӨГ БАЙНА WWW.EGUUR.MN НИЙТЭЛСЭН:2025/04/29    

Turquoise Hill announces third quarter 2018 production and provides underground development update www.gogo.mn

Turquoise Hill Resources (Turquoise Hill or the Company) today announced third quarter 2018 production for Oyu Tolgoi and provided an update on underground development. Ulf Quellmann, Chief Executive Officer of Turquoise Hill, said, “We continued to see the impact of higher gold grades during the third quarter as Oyu Tolgoi processed increasing amounts of Phase 4 ore. We are well positioned to meet the upper-end of our 2018 production guidance.

“Rio Tinto has undertaken a second annual re-forecast of underground development schedule and costs and preliminary results have concluded that capital costs remain in line with the overall $5.3 billion budget and the project remains on schedule to complete in 2022. However, there are certain delays, most notably to the completion of Shaft 2, which includes schedule contingency, that are ultimately expected to result in a revised sustainable production start from the first quarter of 2021 to late in the third quarter 2021.

We are undertaking a review of the cause and the impact of these delays and will announce the results as soon as possible.” Third quarter mill throughput decreased 5.0% over Q2’18 due to increased processing of harder Phase 4 ore as well as a planned maintenance shutdown during the quarter. Copper production was flat over Q2’18 as higher grades and recoveries were partially offset by lower throughput. Gold production increased 54.0% over Q2’18 due to higher grades and recoveries.

Third quarter sales volumes were impacted by torrential rain in July and August, which consequently affected Chinese road and rail availability. Additionally, Q3’18 sales volumes were generally lower than Q2’18, which benefited from the sales of deferred volumes related to the Q1’18 force majeure. Turquoise Hill has updated Oyu Tolgoi’s expected copper production for 2018 from between 125,000 and 155,000 tonnes of copper to between 140,000 and 155,000 tonnes of copper in concentrates. The Company continues to expect production of gold in concentrates from between 240,000 and 280,000 ounces for 2018.



Published Date:2018-10-22