1 MAJOR GENERAL ERDENEBAT PRAISED FOR STRENGTHENING MONGOLIA’S GLOBAL REPUTATION WWW.MONTSAME.MN PUBLISHED:2026/03/11      2 RIO TINTO SHARES HOLD SUPPORT: RENEGOTIATING COPPER MINE DEAL WWW.THEBULL.COM.AU PUBLISHED:2026/03/11      3 OVER 5,000 HOUSEHOLDS AT RISK FROM SNOWMELT FLOODS WWW.MONTSAME.MN PUBLISHED:2026/03/11      4 PRIME MINISTER RAISES DEMANDS ON OYU TOLGOI PROJECT IN MEETING WITH RIO TINTO WWW.MONTSAME.MN PUBLISHED:2026/03/10      5 DISCUSSION ON FORESTS, WATER AND RANGELANDS TO BE HELD AHEAD OF COP17 IN MONGOLIA WWW.MONTSAME.MN PUBLISHED:2026/03/10      6 RIO TINTO HELPED REMAKE THE MONGOLIAN ECONOMY. NOW, THE COUNTRY IS PUTTING ITS HAND OUT FOR MORE (OPINION) WWW.THENIGHTLY.COM.AU PUBLISHED:2026/03/10      7 PM CRITICISES RIO TINTO OVER OYU TOLGOI TERMS, CALLS FOR FAIRER BENEFITS FOR MONGOLIA WWW.GOGO.MN PUBLISHED:2026/03/10      8 MONGOLIA PRESSES RIO TINTO TO REWRITE ‘UNFAIR’ TERMS OF $18BN OYU TOLGOI MINE WWW.FT.COM PUBLISHED:2026/03/10      9 CHINA HIGHLIGHTS MAJOR GAS PIPELINE WORK WITH RUSSIA TO BOOST ENERGY SUPPLY AMID IRAN TENSIONS WWW.MSN.COM PUBLISHED:2026/03/10      10 MONGOLIA'S #1 ROCKERS THE HU RETURN TO THE UK AND EUROPE PUBLISHED:2026/03/10      ХЭРГИЙН МӨРӨӨР: Д.АМАРБАЯСГАЛАН "ҮНДЭСЛЭЛГҮЙГЭЭР ХӨРӨНГӨЖИХ" ЗҮЙЛ АНГИА ХАСУУЛЖ, ЭЦА, АТГ-Т 4 ХЭРГЭЭР ШАЛГУУЛЖ БАЙНА WWW.EGUUR.MN НИЙТЭЛСЭН:2026/03/11     МОНГОЛЫН 91 ИРГЭНИЙГ ДАЙНЫ ЭРСДЭЛТЭЙ БҮСЭЭС ТАТАН АВЧИРЛАА WWW.NEWS.MN НИЙТЭЛСЭН:2026/03/11     ХОЁРДУГААР САРД ГАДААДЫН 776 ИРГЭНД МОНГОЛД ОРШИН СУУХ ЗӨВШӨӨРӨЛ ОЛГОЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/03/10     ГАДААД ХУДАЛДААНЫ БАЛАНС ЭЕРЭГ ГАРЛАА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/03/10     ХЭРГИЙН МӨРӨӨР: Б.БААТАРЫГ ТЕГ, ЭЦА, АТГ-ААС 12 ХҮРТЭЛХ ЖИЛИЙН ХОРИХ ЯЛТАЙ ДОЛООН ЗҮЙЛ АНГИАР ШАЛГАЖ БАЙНА WWW.EGUUR.MN НИЙТЭЛСЭН:2026/03/10     ЭНЭ ОНД НИЙСЛЭЛИЙН ХЭМЖЭЭНД ДАРААХ 13 БАЙРШИЛД 52 КМ АВТО ЗАМ ШИНЭЭР БАРИНА WWW.EGUUR.MN НИЙТЭЛСЭН:2026/03/10     Н.АЛТАНХУЯГИЙГ ГУРВАН УДАА ЦАГААТГАСАН ШИЙДВЭРИЙГ ДАВЖ ЗААЛДАХ ШАТНЫ ШҮҮХЭЭС ХҮЧИНГҮЙ БОЛГОЛОО WWW.EGUUR.MN НИЙТЭЛСЭН:2026/03/10     “ОЮУ ТОЛГОЙ” ТӨСЛИЙН МОНГОЛД НОГДОХ ӨГӨӨЖИЙГ 60 ХУВИАС НЭМЭГДҮҮЛЭХ, 2026 ОНД БАГТААН НОГДОЛ АШИГ ОЛГОХ ШААРДЛАГА ТАВИЛАА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/03/10     “ГУРВАНТЭС-XXXV” ТӨСЛИЙН ХИЙН ГАРЦ 33 ХУВИАР ӨСӨЖ, ШИНЭ ДЭЭД ҮЗҮҮЛЭЛТЭД ХҮРЧЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/03/09     ИЗНН-ЫН ДАРГААР УИХ-ЫН ГИШҮҮН Р.БАТБОЛД СОНГОЛОО WWW.EGUUR.MN НИЙТЭЛСЭН:2026/03/09    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

New airport expected to be operational in July, 2019 www.montsame.mn

Together with his cabinet members, Prime Minister U.Khurelsukh yesterday got acquainted with construction progress of the New Ulaanbaatar International Airport being built in Khushig Valley of Tuv aimag. Ambassador of Japan to Mongolia M.Takaoka and representatives of Japanese investor companies and entities were invited to the event.

While expressing the Government’s interest to commission the New Ulaanbaatar International Airport in July, 2019 on the occasion of the National Naadam Festival, PM U.Khurelsukh claimed that the Government will render support on fulfilling works for which the Government of Mongolia is responsible at high level of quality, resolving necessary investment promptly and establishing concession agreements within schedule.

“In any business participant parties working under joint management should follow win-win approach. Our government has already introduced its decision to operate the new airport under 51:49 management agreement. Therefore, I assign the two parties to establish the agreement within January, 2019, showing mutual trust to each other, “ PM U.Khurelsukh added.

Furthermore, Minister of Finance Ch.Khurelbaatar informed that the funding to be financed from state budget will be allocated without any in 2019 as it has been fully reflected in the Law on 2019 State Budget.

According to the agreement, total sum of the construction works is JPY 49.5 billion and additional works cost JPY 5.9 billion. The contractor undertook duty to hand over a total of 32 works including 23 buildings and 9 facilities and equipment and approval works by the state commission is running at 98.9 percent.

Construction of the highway to the airport is running with 86 percent performance and it is expected to be completed in April, 2019.

When the New Ulaanbaatar International Airport puts into operation, in July 2019 according to the talks held by Prime Ministers of Mongolia and Japan, Mongolia will have world-standard international airport, covering 54.000 square meter of area and having capacity to receive 3 million passengers a year as well as connected with Ulaanbaatar city with 6-lane highway.



Published Date:2018-12-20