1 14TH MBD MISSION FOR MBCC'S "DOING BUSINESS WITH MONGOLIA SEMINAR & CHRISTMAS RECEPTION" AND BUSINESS PROGRAM DEC 08- 14. 2025 LONDON, UK WWW.MONGOLIANBUSINESSDATABASE.COM PUBLISHED:2025/09/16      2 IMF WRAPS UP 2025 ARTICLE IV TALKS WITH MONGOLIA WWW.IMF.ORG PUBLISHED:2025/09/16      3 POSCO INTERNATIONAL TO LAUNCH WASTEWATER HEAT DISTRICT HEATING PROJECT IN MONGOLIA WWW.CM.ASIAE.CO.KR  PUBLISHED:2025/09/16      4 MONGOLIA'S EXTERNAL DEBT UP 12.7 PCT IN Q2 2025 WWW.NEWS.AZ PUBLISHED:2025/09/16      5 2025 AUTUMN SESSION OF THE STATE GREAT KHURAL COMMENCES WITH STRUCTURAL REFORMS WWW.MONTSAME.MN PUBLISHED:2025/09/16      6 MONGOLIA SURPASSES 617,000 TOURIST ARRIVALS BY MID-SEPTEMBER 2025 WWW.MONTSAME.MN PUBLISHED:2025/09/16      7 ODD-EVEN TRAFFIC RESTRICTION CONCLUDES WWW.UBPOST.MN PUBLISHED:2025/09/15      8 MMC ANNOUNCES FIRST GOLD POUR COMPLETED AT THE BAYAN KHUNDII MINE IN MONGOLIA WWW.SG.FINANCE.YAHOO.COM  PUBLISHED:2025/09/15      9 MKE LAUNCHES CARTRIDGE PRODUCTION LINE IN MONGOLIA WWW.RAILLYNEWS.COM  PUBLISHED:2025/09/15      10 MONGOLIA’S LARGEST MINING EVENT HIGHLIGHTS INVESTMENT AND RESPONSIBLE MINING WWW.MONTSAME.MN PUBLISHED:2025/09/14      14 ДЭХЬ УДААГИЙН MBCCI’S “ DOING BUSINESS WITH MONGOLIA SEMINAR & CHRISTMAS RECEPTION” B2B NETWORKING БОЛОН БИЗНЕС ХӨТӨЛБӨР 2025 ОНЫ 12 САРЫН 08 -13 ЛОНДОН ХОТ, ИХ БРИТАНИ WWW.MONGOLIANBUSINESSDATABASE.COM НИЙТЭЛСЭН:2025/09/16     ЭДИЙН ЗАСГИЙН ТӨРӨЛЖИЛТИЙН ИНДЕКСЭЭР МОНГОЛ УЛС 145 ОРНООС 139-Д БИЧИГДЖЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2025/09/16     ӨНӨӨДӨР: “СЭЛБЭ 20 МИНУТЫН ХОТ”-ЫН ДАРААГИЙН ЭЭЛЖИЙН ОРОН СУУЦНЫ ТӨСЛИЙН БҮТЭЭН БАЙГУУЛАЛТЫГ ЭХЛҮҮЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/09/16     ШЭНЬ МИНЬЖУАНЬ: БНХАУ МОНГОЛ УЛСЫГ ШХАБ-ЫН ГЭР БҮЛД НЭГДЭЖ, ХАМТЫН АЖИЛЛАГААГАА ӨРГӨЖҮҮЛЭХИЙГ УРЬСАН WWW.ITOIM.MN НИЙТЭЛСЭН:2025/09/15     Г.ЗАНДАШАТАР: ТӨРИЙН ДАНХАР БҮТЦИЙГ ХУМИХ АЖИЛ ИРЭХ ОНД Ч ҮРГЭЛЖИЛНЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/09/15     Ц.ТУВААН: НҮҮРСНИЙ ҮНЭ 3 САР ТУТАМ ШИНЭЧЛЭГДЭНЭ. ГЭРЭЭНД ЯМАР Ч НУУЦ БАЙХГҮЙ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/09/15     ХАНЫН МАТЕРИАЛД 1800 АЙЛЫН ОРОН СУУЦ БАРИХ ТӨСЛИЙН ГҮЙЦЭТГЭГЧ ШАЛГАРЛАА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/09/15     "ТАТВАРЫН ХЭТ ӨНДӨР ТООЦОО БИЗНЕС ЭРХЛЭГЧДИЙГ ХААЛГАА БАРИХАД ХҮРГЭНЭ" WWW.NEWS.MN НИЙТЭЛСЭН:2025/09/15     ГАДААД ХУДАЛДААНЫ НӨХЦӨЛИЙН ИНДЕКС ӨМНӨХ ОНООС 4.1 ХУВИАР БУУРЧЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2025/09/15     ЭХНИЙ НАЙМАН САРЫН БАЙДЛААР 600 МЯНГАН ЖУУЛЧИН ИРЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/09/15    

Oyu Tolgoi funded 35.1 km road opens in Khanbogd www.gogo.mn

The Khanbogd-Oyu Tolgoi paved road has been opened ceremoniously today. The 35.1 km road enables safe and comfortable travel for locals and Oyu Tolgoi employees.

Oyu Tolgoi LLC fully funded the MNT46 billion project, which was recognized as the “Best Construction and Infrastructure Project 2018” by Umnugovi province. It is the latest of many projects Oyu Tolgoi LLC has funded for the development of Umnugovi and Khanbogd. Recently, Oyu Tolgoi-funded school and kindergarten complex for 840 students opened in Khanbogd. The school introduces Cambridge education system to the community, making it the only soum level educational institution with international curriculum.

Before its commission on December 24, 2019, The Ministry of Road and Transportation Development representatives praised the quality of construction, pavement markings and road safety signs during a visit to the construction site.

The construction was concluded by the joint efforts of 26 different national contractors, led by Arj Road, Anand Road, Zag Engineering and KACMS LLC. In 2018, the surrounding area registered high rainfall level, complicating work conditions at the site. To deliver the quality work within timeframe, the construction team took immediate measures to increase the technical capabilities and manpower and managed to complete the project on time. At the height of construction, 550 workers and 171 vehicles were employed at the site, paving up to 2800 meters of asphalt concrete a day, significantly above the national average.

Extensive research and tests were conducted to address material shortages in of the local market, successfully planning the logistics of procurement from distant areas. Material quality was assured by an on-site laboratory, which conducted more than 1200 tests.

Prior to land disturbance, extensive archeological and paleontological researches were undertaken in accordance to the Environmental, Social, Cultural Impact Assessment. In addition, 10 thousand rare plants of six species were relocated to Oyu Tolgoi tree nursery in Khanbogd.



Published Date:2019-02-21