1 CENTRAL BANK INTRODUCES NEW RESERVE RULE FOR FOREIGN BORROWING WWW.MONTSAME.MN PUBLISHED:2026/05/27      2 CONSUMER LOAN DEFAULTS STABILIZE IN RECENT MONTHS WWW.MONTSAME.MN PUBLISHED:2026/05/27      3 GOVERNMENT APPROVES MAJOR RESTRUCTURING OF ERDENES MONGOL WWW.MONTSAME.MN PUBLISHED:2026/05/27      4 CAPITAL MARKETS MONGOLIA SUCCESSFULLY HOSTS INAUGURAL MONGOLIA INVESTMENT FORUM IN SHANGHAI WWW.CAPITALMARKETS.MN PUBLISHED:2026/05/27      5 NATIONAL GREEN LAB SHORTLISTS TOP PROJECTS FOR COP17 WWW.MONTSAME.MN PUBLISHED:2026/05/27      6 MONGOLIA INTRODUCES IDENTIFICATION SIGNS FOR PREGNANT WOMEN WWW.XINHUANET.COM PUBLISHED:2026/05/27      7 ROAD CONSTRUCTION FOR COP-17 TO BE COMPLETED BY JULY 1 WWW.GOGO.MN PUBLISHED:2026/05/27      8 B.PUREVDAGVA APPOINTED GOVERNOR OF THE CAPITAL CITY AND MAYOR OF ULAANBAATAR WWW.GOGO.MN PUBLISHED:2026/05/27      9 INTERIM TRADE AGREEMENT TO DIVERSIFY EXPORT STRUCTURE, MARKETS WWW.MONTSAME.MN PUBLISHED:2026/05/27      10 TOWARD A US-MONGOLIA CRITICAL MINERALS PARTNERSHIP WWW.NATIONALINTEREST.ORG PUBLISHED:2026/05/26      "РИО ТИНТО"-ТОЙ ХЭЛЭЛЦЭЭ ХИЙХТЭЙ ЗЭРЭГЦЭН Г.ДАМДИННЯМ ЗЭСИЙН АМНАТ-ИЙГ БУУРУУЛАХ ХУУЛЬ ЗҮТГҮҮЛЛЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/05/27     “ЭРДЭНЭТ ҮЙЛДВЭР” ТӨҮГ-Т АЖИЛЛАЖ БАЙХДАА ИХ ХЭМЖЭЭНИЙ ХАХУУЛЬ АВСАН ХЭРГИЙГ ШҮҮХЭЭР ШИЙДВЭРЛЭЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/05/27     "ЭРДЭНЭС ОЮУ ТОЛГОЙ" КОМПАНИЙГ Б.ТЭЛМҮҮН УДИРДАНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/05/27     Б.ДАВААДАЛАЙ: "ЭРДЭНЭС МОНГОЛ НЭГДЭЛ" НЭРЭЭ ӨӨРЧИЛЖ, ХӨРӨНГӨ УДИРДАХ ЧИГЛЭЛД ТӨВЛӨРНӨ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/05/27     УС, ДУЛААНЫ ТӨЛБӨРӨӨ ТӨЛДӨГГҮЙ ӨРХИЙН МЭДЭЭЛЛИЙГ ЗЭЭЛИЙН МЭДЭЭЛЛИЙН САНД БҮРТГЭНЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/05/27     ЗҮТГҮҮРИЙН ЦАХИЛГААН ХӨДӨЛГҮҮРИЙГ МОНГОЛДОО ЗАСДАГ БОЛЛОО WWW.GOGO.MN НИЙТЭЛСЭН:2026/05/27     БАНКНЫ САЛБАР ГАДААД ЗАХ ЗЭЭЛЭЭС УРТ ХУГАЦААТ ЭХ ҮҮСВЭР ТАТАХЫГ ДЭМЖИХ ШИЙДВЭР ГАРГАВ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/05/27     МАНАЙ УЛС АМИА ХОРЛОЛТЫН ТООГООР ДЭЛХИЙД ХОЁРТ ЭРЭМБЭЛЭГДЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/05/27     ЗӨВЛӨМЖ: НАС БАРСАН ИРГЭНИЙ 1072 ХУВЬЦААГ ӨВЛҮҮЛЖ, НОГДОЛ АШИГ АВАХ 5 АЛХАМ, БУСАД ЗААВАРЧИЛГАА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/05/27     БАНКНЫ САЛБАР 2.5 ИХ НАЯД ТӨГРӨГИЙН НОГООН ЗЭЭЛ ОЛГООД БАЙНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/05/27    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Former coal-fired power plant in Ontario becomes solar facility www.mining.com

The former Nanticoke Generating Station site, located on the northern shore of Lake Erie, has been transformed into a 44-megawatt clean energy facility that hosts 192,431 solar panels across 260 acres.

The project has just been completed by PCL Construction, a company that was commissioned to design, engineer and build it, as well as supply the photovoltaic solar panels and racking system. Behind the idea and funding are Ontario Power Generation, the Six Nations of the Grand River Development Corporation and the Mississaugas of the Credit First Nation.

The opening of the solar facility coincides with the one-year anniversary of the demolition of the Nanticoke 650-feet smokestacks. It has also been almost five years since the station burned its last piece of coal.

In its heyday, the Nanticoke Generating Station was the largest coal-fired plant in North America, providing 15% of Ontario’s electricity. After serving the province for more than 40 years, it stopped using coal as fuel in 2013. Two years later, the site was safely closed while the switchyards, operated by Hydro One Networks, remain in operation as a significant hub for the electricity grid in the southwestern part of the region.

Official information indicates that some parts of the former facility, such as the powerhouse, still need to be torn down. Following the last demolition scheduled for September 2019, the site will undergo a restoration process in 2020.

Since 2014, Ontario Power Generation stopped using coal to generate electricity in Canada's most populous province, a move that resulted in the equivalent of taking 7 million cars off the road.