1 MONGOLIA’S CLIMATE TRANSITION: EMPOWERING CITIZENS FOR A JUST AND SUSTAINABLE FUTURE WWW.DEVDISCOURSE.COM PUBLISHED:2025/07/31      2 MONGOLIA RENEWABLE ENERGY TARGET: POWERFUL 2030 VISION WWW.PVKNOWHOW.COM  PUBLISHED:2025/07/31      3 MINISTER FOR FOREIGN AFFAIRS OF MONGOLIA BATMUNKH BATTSETSEG TO VISIT FINLAND WWW.VALTIONEUVOSTO.FI  PUBLISHED:2025/07/31      4 MIAT’S NEW “IRVES” AIRCRAFT ARRIVES IN MONGOLIA AFTER COVERING 12,265 KM WWW.MONTSAME.MN PUBLISHED:2025/07/31      5 5TH CHINA-MONGOLIA EXPO TO BOOST REGIONAL COOPERATION WWW.XINHUANET.COM PUBLISHED:2025/07/31      6 FIVE AIMAGS CLASSIFIED AS HIGH-RISK FOR DROUGHT WWW.MONTSAME.MN PUBLISHED:2025/07/31      7 SEACEN FORUM FOCUSES ON FUTURE-READY CENTRAL BANK WORKFORCE WWW.UBPOST.MN PUBLISHED:2025/07/31      8 39 MONGOLIAN STUDENTS TO STUDY IN GERMANY UNDER “PRESIDENT'S SCHOLAR - 2100” PROGRAM WWW.MONTSAME.MN PUBLISHED:2025/07/30      9 MONGOLIAN FLAG CARRIER TO START NON-STOP FLIGHTS BETWEEN SINGAPORE AND ULAANBAATAR FROM NOV 4 WWW.STRAITSTIMES.COM PUBLISHED:2025/07/30      10 WHEN CHINA SNEEZES, MONGOLIA CATCHES A COLD WWW.INTELLINEWS.COM PUBLISHED:2025/07/30      ЭРДЭМТДИЙН ЗӨВЛӨЛИЙН ШИЙДВЭРЭЭР ИРЭХ ӨВӨЛ ХАГАС КОКС БУЮУ ХӨХ НҮҮРСЭЭР ХИЙСЭН ШАХМАЛ ТҮЛШ ХЭРЭГЛЭНЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/07/31     ЗАСГИЙН ГАЗАР: УЛААНБААТАР ХОТЫН ДУЛААН ХАНГАМЖИД СХЕМИЙН ӨӨРЧЛӨЛТ ХИЙНЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/07/31     "АЛТ 3" АЯН ГАЦААНД ОРОВ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/07/31     ДЦСV-ЫГ БАРИХ КОМПАНИ ИРЭХ САРЫН 6-НД ТОДОРНО WWW.NEWS.MN НИЙТЭЛСЭН:2025/07/31     МИАТ КОМПАНИ КАНАД УЛСЫН BOMBARDIER ҮЙЛДВЭРИЙН CRJ-700 ШИНЭ АГААРЫН ХӨЛӨГ ОНГОЦОО ХҮЛЭЭН АВЛАА WWW.EGUUR.MN НИЙТЭЛСЭН:2025/07/31     BNE INTELLINEWS: БНХАУ НАЙТААХ ҮЕД МОНГОЛ ХАНИАД ХҮРДЭГ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/07/31     "БӨӨРӨЛЖҮҮТИЙН ЦС"-ЫН II БЛОКИЙГ 12-Р САРД АШИГЛАЛТАД ОРУУЛНА WWW.EGUUR.MN НИЙТЭЛСЭН:2025/07/31     ГАНГИЙН ЭРСДЛИЙН ҮНЭЛГЭЭГЭЭР ТАВАН АЙМАГ ЭРСДЭЛ ИХТЭЙ ГАРЧЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/07/30     МОНГОЛЫН КОКСЖИХ НҮҮРСНИЙ ҮНЭ ХЯТАДЫН БООМТУУДАД ДАХИН ӨСЛӨӨ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/07/30     НИЙСЛЭЛД ХЭРЭГЖҮҮЛЖ БУЙ МЕГА ТӨСЛҮҮДЭД ХАМТРАН АЖИЛЛАХААР САНАЛ СОЛИЛЦЛОО WWW.ITOIM.MN НИЙТЭЛСЭН:2025/07/30    

Rio Tinto Hits Cost Blowout at Mongolia Copper Expansion www.reuters.com

(Reuters) - Rio Tinto on Tuesday flagged a cost blowout of up to $1.9 billion and a delay of up to 30 months at its Oyu Tolgoi underground copper mine in Mongolia, the miner's key growth project.

Rio said the delay stemmed from the project's challenging geology. It expected to determine the preferred mine design, along with a final estimate of cost in the second half of 2020, and was also reviewing the value of its investment.

The cost blowout was bigger than analysts had expected after the company had earlier flagged issues with the original mine design.

Rio said first production could be achieved between May 2022 and June 2023, a delay of 16 to 30 months, while the capital cost of the project was estimated at $6.5 billion to $7.2 billion, up from an original estimate of $5.3 billion.

"It is a world class orebody in terms of the size, the grade etc. What we are trying to work out now, is can it be developed and mined economically to convert what is a world class orebody into world class mine," said Glyn Lawcock, analyst at UBS.

"Overall, it was below our expectations for the quarter."

The news of the blowout came as Rio reported a 3.5% drop in second-quarter iron ore shipments, as disruptions caused by tropical cyclone Veronica in late March squeezed output in the April-June period.

The company shipped 85.4 million tonnes of the steelmaking ingredient in the quarter ended June 30, down from 88.5 million tonnes a year earlier. Brokerage UBS had estimated quarterly shipments of 85.2 million tonnes.

Veronica ravaged the coast of Western Australia earlier this year, damaging several iron ore export hubs and prompting Australia's biggest listed miners to cut their 2019 forecast for iron ore output.

Rio on Tuesday maintained its annual iron ore exports forecast in the 320 million to 330 million tonnes range.

In Mongolia, the miner said it had made significant progress at Oyu Tolgoi during 2019.

"The ground conditions are more challenging than expected and we are having to review our mine plan and consider a number of options," said Stephen McIntosh, Group executive, Growth & Innovation.

"Delays are not unusual for such a large and complex project," he added.

Rio said it was reviewing the carrying value of its investment in Oyu Tolgoi and would announce if any changes were needed at its half-year results on Aug. 1.

Rio Tinto shares were flat in early trade in a steady broader market.

(Reporting by Aditya Soni and Aby Jose Koilparambil in Bengaluru; Additional reporting by Melanie Burton in Melbourne; Editing by Shounak Dasgupta and Richard Pullin)



Published Date:2019-07-16