1 BANGLADESH TO SEND FIRST BATCH OF 12 WORKERS TO MONGOLIA NOV 1 WWW.THEFINANCIALEXPRESS.COM.BD PUBLISHED:2026/10/26      2 MONGOLIAN AMBASSADOR PRESENTS CREDENTIALS TO KING CHARLES III WWW.MONTSAME.MN PUBLISHED:2026/10/26      3 JAPAN GOVT SAYS IT TAKES MONGOLIA WILDFIRE SERIOUSLY WWW.JEN.JIJI.COM PUBLISHED:2026/10/26      4 MONGOLIA TO CONSIDER SEEKING COMPENSATION OVER GRASSLAND FIRE WWW.NIPPON.COM PUBLISHED:2026/10/26      5 MONGOLIA’S TAX AND SOCIAL INSURANCE BURDEN TO BE REDUCED BY US$278.3 MILLION NEXT YEAR WWW.ASIANEWS.NETWORK PUBLISHED:2026/10/26      6 48 BROWN BEARS KILLED WWW.UBPOST.MN PUBLISHED:2026/10/26      7 PERSONNEL RECEIVE RESCUE TRAINING FOR CABLE CAR SYSTEM WWW.UBPOST.MN PUBLISHED:2026/10/26      8 WILL RIO TINTO ALSO RECEIVE DIVIDENDS IF GOVERNMENT RECEIVES THEM? WWW.UBPOST.MN PUBLISHED:2026/10/25      9 INDONESIA INTERCEPTS MONGOLIAN-FLAGGED TANKER CARRYING 1.16 TONNES OF KETAMINE WWW.MARINEINSIGHT.COM PUBLISHED:2026/10/25      10 EXPERT WARNS OF COMPLEX ECOLOGICAL FALLOUT FROM MONGOLIA GRASSLAND FIRE LINKED TO JAPANESE COMPANY WWW.XINHUANET.COM PUBLISHED:2026/10/25      ЕРӨНХИЙЛӨГЧ У.ХҮРЭЛСҮХИЙГ БҮГД НАЙРАМДАХ БЕЛАРУСЬ УЛСЫН ЕРӨНХИЙЛӨГЧ А.Г.ЛУКАШЕНКО АЛБАН ЁСООР УГТАН АВАВ WWW.IKON.MN НИЙТЭЛСЭН:2026/10/26     ХӨРӨНГИЙН БИРЖИЙН ГҮЙЦЭТГЭХ ЗАХИРЛЫН ҮҮРГИЙГ ТҮР ОРЛОН ГҮЙЦЭТГЭГЧЭЭР Б.АНАРЫГ ТОМИЛЖЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/10/26     NVIDIA КОМПАНИЙН ГҮЙЦЭТГЭХ ЗАХИРАЛ КАЗАХСТАН УЛСЫГ ФИЗИК ХИЙМЭЛ ОЮУН УХААНЫ ДЭЛХИЙН ТӨВ БОЛГОХ САНАЛ ТАВЬЖЭЭ WWW.IKON.MN НИЙТЭЛСЭН:2026/10/26     О.ӨМӨРБЕК: "МОБИКОМ КОРПОРАЦ" ХОХИРЛЫГ ТОГТООХОД ХЭРЭГТЭЙ БАЙГАА ЗАРДАЛ, ТУСЛАМЖ ДЭМЖЛЭГИЙГ БҮХ ТАЛААС НЬ ҮЗҮҮЛНЭ WWW.IKON.MN НИЙТЭЛСЭН:2026/10/26     АРВАННЭГДҮГЭЭР САРД ОЛОН ЖИЛИЙН ДУНДЖААС ХҮЙТЭН БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/10/26     ЯПОНЫ ЗАСГИЙН ГАЗАР НӨМРӨГИЙН ТҮЙМЭРТ ХАРАМСАЖ БУЙГАА ИЛЭРХИЙЛЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/10/26     СЭТГЭЦЭД НӨЛӨӨТ БОДИС ТЭЭВЭРЛЭСЭН ЭТГЭЭДҮҮДИЙГ СААТУУЛЖЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/10/26     Н.АЛТАНХУЯГ НАРЫН ХЭРГИЙГ ДАХИН ХЭЛЭЛЦЭНЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/10/25     ГАЗРЫН ТОС БОЛОВСРУУЛАХ ҮЙЛДВЭРИЙН ТҮҮХИЙ ЭДИЙН ЭРЛИЙГ 15 БАЙРШИЛД ХИЙЖ БАЙНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/10/25     Б.ПҮРЭВДАГВА: НИЙСЛЭЛЧҮҮДЭД 0.7 ГА ГАЗРЫГ ӨМЧЛҮҮЛЭХ АЖЛЫГ ЭРЧИМЖҮҮЛНЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/10/25    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Rio Tinto Hits Cost Blowout at Mongolia Copper Expansion www.reuters.com

(Reuters) - Rio Tinto on Tuesday flagged a cost blowout of up to $1.9 billion and a delay of up to 30 months at its Oyu Tolgoi underground copper mine in Mongolia, the miner's key growth project.

Rio said the delay stemmed from the project's challenging geology. It expected to determine the preferred mine design, along with a final estimate of cost in the second half of 2020, and was also reviewing the value of its investment.

The cost blowout was bigger than analysts had expected after the company had earlier flagged issues with the original mine design.

Rio said first production could be achieved between May 2022 and June 2023, a delay of 16 to 30 months, while the capital cost of the project was estimated at $6.5 billion to $7.2 billion, up from an original estimate of $5.3 billion.

"It is a world class orebody in terms of the size, the grade etc. What we are trying to work out now, is can it be developed and mined economically to convert what is a world class orebody into world class mine," said Glyn Lawcock, analyst at UBS.

"Overall, it was below our expectations for the quarter."

The news of the blowout came as Rio reported a 3.5% drop in second-quarter iron ore shipments, as disruptions caused by tropical cyclone Veronica in late March squeezed output in the April-June period.

The company shipped 85.4 million tonnes of the steelmaking ingredient in the quarter ended June 30, down from 88.5 million tonnes a year earlier. Brokerage UBS had estimated quarterly shipments of 85.2 million tonnes.

Veronica ravaged the coast of Western Australia earlier this year, damaging several iron ore export hubs and prompting Australia's biggest listed miners to cut their 2019 forecast for iron ore output.

Rio on Tuesday maintained its annual iron ore exports forecast in the 320 million to 330 million tonnes range.

In Mongolia, the miner said it had made significant progress at Oyu Tolgoi during 2019.

"The ground conditions are more challenging than expected and we are having to review our mine plan and consider a number of options," said Stephen McIntosh, Group executive, Growth & Innovation.

"Delays are not unusual for such a large and complex project," he added.

Rio said it was reviewing the carrying value of its investment in Oyu Tolgoi and would announce if any changes were needed at its half-year results on Aug. 1.

Rio Tinto shares were flat in early trade in a steady broader market.

(Reporting by Aditya Soni and Aby Jose Koilparambil in Bengaluru; Additional reporting by Melanie Burton in Melbourne; Editing by Shounak Dasgupta and Richard Pullin)