1 ZANDANSHATAR GOMBOJAV APPOINTED AS PRIME MINISTER OF MONGOLIA WWW.MONTSAME.MN PUBLISHED:2025/06/13      2 WHAT MONGOLIA’S NEW PRIME MINISTER MEANS FOR ITS DEMOCRACY WWW.TIME.COM PUBLISHED:2025/06/13      3 ULAANBAATAR DIALOGUE SHOWS MONGOLIA’S FOREIGN POLICY CONTINUITY AMID POLITICAL UNREST WWW.THEDIPLOMAT.COM PUBLISHED:2025/06/13      4 THE UNITED NATIONS CHILDREN’S FUND (UNICEF) IN MONGOLIA, THE NATIONAL FOUNDATION FOR SUPPORTING THE BILLION TREES MOVEMENT, AND CREDITECH STM NBFI LLC HAVE JOINTLY LAUNCHED THE “ONE CHILD – ONE TREE” INITIATIVE WWW.BILLIONTREE.MN PUBLISHED:2025/06/13      5 NEW MONGOLIAN PM TAKES OFFICE AFTER CORRUPTION PROTESTS WWW.AFP.MN PUBLISHED:2025/06/13      6 GOLD, MINED BY ARTISANAL AND SMALL-SCALE MINERS OF MONGOLIA TO BE SUPPLIED TO INTERNATIONAL JEWELRY COMPANIES WWW.MONTSAME.MN PUBLISHED:2025/06/13      7 AUSTRIA PUBLISHES SYNTHESIZED TEXTS OF TAX TREATIES WITH ICELAND, KAZAKHSTAN AND MONGOLIA AS IMPACTED BY BEPS MLI WWW.ORBITAX.COM  PUBLISHED:2025/06/13      8 THE UNITED STATES AND MONGOLIA OPEN THE CENTER OF EXCELLENCE FOR ENGLISH LANGUAGE TEACHING IN ULAANBAATAR WWW.MN.USEMBASSY.GOV  PUBLISHED:2025/06/12      9 MONGOLIA'S 'DRAGON PRINCE' DINOSAUR WAS FORERUNNER OF T. REX WWW.REUTERS.COM PUBLISHED:2025/06/12      10 MONGOLIA’S PIVOT TO CENTRAL ASIA AND THE CAUCASUS: STRATEGIC REALIGNMENTS AND REGIONAL IMPLICATIONS WWW.CACIANALYST.ORG  PUBLISHED:2025/06/12      БӨӨРӨЛЖҮҮТИЙН ЦАХИЛГААН СТАНЦЫН II БЛОКИЙГ 12 ДУГААР САРД АШИГЛАЛТАД ОРУУЛНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/15     ОРОН СУУЦНЫ ҮНЭ 14.3 ХУВИАР ӨСЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/15     МОНГОЛ УЛСЫН 34 ДЭХ ЕРӨНХИЙ САЙДААР Г.ЗАНДАНШАТАРЫГ ТОМИЛЛОО WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/13     SXCOAL: МОНГОЛЫН НҮҮРСНИЙ ЭКСПОРТ ЗАХ ЗЭЭЛИЙН ХҮНДРЭЛИЙН СҮҮДЭРТ ХУМИГДАЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/06/13     МОНГОЛ БАНК: ТЭТГЭВРИЙН ЗЭЭЛД ТАВИХ ӨР ОРЛОГЫН ХАРЬЦААГ 50:50 БОЛГОЛОО WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/13     МОНГОЛ ДАХЬ НҮБ-ЫН ХҮҮХДИЙН САН, ТЭРБУМ МОД ҮНДЭСНИЙ ХӨДӨЛГӨӨНИЙГ ДЭМЖИХ САН, КРЕДИТЕХ СТМ ББСБ ХХК “ХҮҮХЭД БҮРД – НЭГ МОД” САНААЧИЛГЫГ ХАМТРАН ХЭРЭГЖҮҮЛНЭ WWW.BILLIONTREE.MN НИЙТЭЛСЭН:2025/06/13     ЕРӨНХИЙЛӨГЧИЙН ТАМГЫН ГАЗРЫН ДАРГААР А.ҮЙЛСТӨГӨЛДӨР АЖИЛЛАНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/06/13     34 ДЭХ ЕРӨНХИЙ САЙД Г.ЗАНДАНШАТАР ХЭРХЭН АЖИЛЛАНА ГЭЖ АМЛАВ? WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/13     “АНГЛИ ХЭЛНИЙ МЭРГЭШЛИЙН ТӨВ”-ИЙГ МУИС-Д НЭЭЛЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/13     Г.ЗАНДАНШАТАР БАЯЛГИЙН САНГИЙН БОДЛОГЫГ ҮРГЭЛЖЛҮҮЛНЭ ГЭЖ АМЛАЛАА WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/12    

Petro Matad spuds Red Deer-1 well in eastern Mongolia www.sharecast.com

Mongolian oil explorer Petro Matad announced on Monday that the Red Deer-1 exploration well in the Asgat Sag Basin of Block XX in eastern Mongolia was spudded on 4 August.

The AIM-traded firm said the well was being drilled with the Daton Petroleum Engineering and Oilfield Service rig, DXZ1.

It said the Red Deer-1 well was targeting a prospect with 48MMbo of mean prospective recoverable resource, and was planned to be drilled to a total depth of 2,100 metres.

The well was expected to take up to 35 days to complete.

In the event of a discovery, the company said would bring in a separate rig for testing.

A call-off testing contract had been signed, which ensured testing operations, if warranted, could commence soon after discovery.

Meanwhile, at Heron-1, Petro Matad said the first casing point at 551 metres was reached on schedule, and casing had been run and cemented.

The DQE rig 40105 was now ready to drill out cement, and then drill an eight-and-a-half inch hole to the prognosed total depth of 3,050 metres.

However, the provincial government had challenged Petro Matad's legal right to use the land at Heron-1 on the basis that a tripartite agreement between two central government agencies and the province had not been executed.

In all of Petro Matad's operations, the firm said it had followed the land permitting regulations as required under the production sharing contract, and in accordance with instructions from the Ministry of Mining and the industry regulator MRPAM.

The absence of a tripartite land use agreement between government agencies had never previously been an issue.

The board said it was working with the ministry, MRPAM and the provincial government to remedy that situation as soon as possible.

“The rig at Heron-1 has been put on standby whilst the situation is resolved,” the board said in its statement.

“All efforts are currently directed at fixing this interruption as quickly as possible in order to minimise rig standby costs.

“Daily standby costs are low by industry standards and are of the order of $12,000.”

Petro Matad said the Red Deer-1 well was located in a different province to that in which Heron-1 was located, and had not been affected.