1 RIO-GLENCORE DEAL CLOSER THAN EVER WITH PREMIUM AND CEO IN FOCUS WWW.BLOOMBERG.COM PUBLISHED:2026/01/10      2 MONGOLIA'S INFLATION DOWN TO 7.5 PCT IN DECEMBER 2025 WWW.XINHUANET.COM PUBLISHED:2026/01/10      3 MONGOLIA ENERGY FACES MNT 412.3 BILLION TAX LIABILITY AFTER LOSING MONGOLIAN COURT CASE WWW.TIPRANKS.COM  PUBLISHED:2026/01/10      4 NUMBER OF FOREIGN NATIONALS RESIDING FOR OFFICIAL AND PRIVATE PURPOSES UP 7.4% WWW.MONTSAME.MN PUBLISHED:2026/01/10      5 SUSTAINABILITY RELATED REPORTING: READINESS ASSESSMENT MONGOLIA REPORT WWW.UNDP.ORG PUBLISHED:2026/01/10      6 GOVERNMENT TO FORMALLY APPROACH RIO TINTO, OYU TOLGOI TO SAFEGUARD NATIONAL INTEREST WWW.MONTSAME.MN PUBLISHED:2026/01/09      7 NON-COMPLIANT ADVERTISING BILLBOARDS TO BE REMOVED WWW.MONTSAME.MN PUBLISHED:2026/01/09      8 FROM TORONTO, CANADA TO PHU QUOC, VIETNAM: MONGOLIA’S BOLD 2026 AVIATION EXPANSION INCLUDES NEW FLIGHTS, VISA-FREE TRAVEL, AND AIRPORT UPGRADES! WWW.TRAVELANDTOURWORLD.COM PUBLISHED:2026/01/09      9 MONGOLIA TO MARK 820TH ANNIVERSARY OF THE GREAT MONGOL EMPIRE WWW.MONTSAME.MN PUBLISHED:2026/01/09      10 PARLIAMENT SUPPORTS SOLAR GER INITIATIVE UNDER NEW REGULATORY REFORMS WWW.MONTSAME.MN PUBLISHED:2026/01/09      Б.ДЭЛГЭРСАЙХАН: ХӨШИГИЙН ХӨНДИЙН ТӨМӨР ЗАМ, НАВИГАЦЫН ТОНОГ ТӨХӨӨРӨМЖИЙН ШИНЭЧЛЭЛИЙГ ЭНЭ ОНД ДУУСГАНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/01/11     УРЬДЧИЛАН ЗАХИАЛГА ӨГСӨН 260 ИРГЭНИЙГ ХОЁР ТЭРБУМ ТӨГРӨГӨӨР ХОХИРООЖЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/01/11     GLENCORE, RIO TINTO КОМПАНИУД НЭГДЭХ ХЭЛЭЛЦЭЭ ХИЙЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/01/10     Н.НАРАНБААТАР: ЭНЭ ОНД НҮҮРСНИЙ ЭКСПОРТЫН ХЭМЖЭЭГ 90 САЯ ТОННД БАРИНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/01/10     УЛААНБААТАРТ ӨНДӨР ТЕХНОЛОГИЙН ХОЁР ҮЙЛДВЭР БАЙГУУЛЖ, УСАН ХАНГАМЖИЙГ 80 ХУВИАР НЭМЭГДҮҮЛЛЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/01/09     ХУУЛЬ БУС ЭЗЭМШИЛД БАЙСАН 15 БАРИЛГА БАЙГУУЛАМЖИЙГ НИЙСЛЭЛД БУЦААН АВЧЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/01/09     МОНГОЛ УЛСАД 37 097 ГАДААД ИРГЭН ОРШИН СУУХ БҮРТГЭЛТЭЙ БАЙНА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/01/09     ҮСХ: 12 ДУГААР САРЫН ИНФЛЯЦ 7.5 ХУВЬТАЙ ГАРЛАА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/01/09     2026 ОНД НИЙСЛЭЛД ХЭРЭГЖИХ ТОМООХОН БҮТЭЭН БАЙГУУЛАЛТУУД WWW.ITOIM.MN НИЙТЭЛСЭН:2026/01/09     ДУЛААНЫ ТАРИФ НЭМЭГДҮҮЛЭХ ШИЙДВЭРИЙГ ХОЙШЛУУЛЖ, 2027 ОНЫ НЭГДҮГЭЭР САРЫН 1-НЭЭС НЭМНЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/01/09    

Rio submits feasibility study for Tavan Tolgoi power plant www.reuters.com

Rio Tinto (NYSE, ASX:RIO) on Tuesday said its Mongolian copper mine project has submitted a feasibility study to the local government in its bid to secure domestically sourced power for the East Asian’s country’s biggest foreign investment project.

Oyu Tolgoi LLC submitted a feasibility study for the Tavan Tolgoi Power Plant (TTPP) Project, which involves building a 300 MW coal power plant at an estimated cost of about $924 million, the Anglo-Australian miner said in a statement.

The global miner said it is also working on alternative options to source domestic power, including a renewable power component.

Rio Tinto-owned Turquoise Hill Resources has a 66% stake in the multi-billion-dollar project and the Mongolian state owns 34%, with investment terms agreed in 2015 in a deal known as the Dubai Agreement.

Mongolia has been exerting pressure on Rio Tinto to revise the Oyu Tolgoi agreement terms to make it more beneficial to the country and its citizens.