1 ZANDANSHATAR GOMBOJAV APPOINTED AS PRIME MINISTER OF MONGOLIA WWW.MONTSAME.MN PUBLISHED:2025/06/13      2 WHAT MONGOLIA’S NEW PRIME MINISTER MEANS FOR ITS DEMOCRACY WWW.TIME.COM PUBLISHED:2025/06/13      3 ULAANBAATAR DIALOGUE SHOWS MONGOLIA’S FOREIGN POLICY CONTINUITY AMID POLITICAL UNREST WWW.THEDIPLOMAT.COM PUBLISHED:2025/06/13      4 THE UNITED NATIONS CHILDREN’S FUND (UNICEF) IN MONGOLIA, THE NATIONAL FOUNDATION FOR SUPPORTING THE BILLION TREES MOVEMENT, AND CREDITECH STM NBFI LLC HAVE JOINTLY LAUNCHED THE “ONE CHILD – ONE TREE” INITIATIVE WWW.BILLIONTREE.MN PUBLISHED:2025/06/13      5 NEW MONGOLIAN PM TAKES OFFICE AFTER CORRUPTION PROTESTS WWW.AFP.MN PUBLISHED:2025/06/13      6 GOLD, MINED BY ARTISANAL AND SMALL-SCALE MINERS OF MONGOLIA TO BE SUPPLIED TO INTERNATIONAL JEWELRY COMPANIES WWW.MONTSAME.MN PUBLISHED:2025/06/13      7 AUSTRIA PUBLISHES SYNTHESIZED TEXTS OF TAX TREATIES WITH ICELAND, KAZAKHSTAN AND MONGOLIA AS IMPACTED BY BEPS MLI WWW.ORBITAX.COM  PUBLISHED:2025/06/13      8 THE UNITED STATES AND MONGOLIA OPEN THE CENTER OF EXCELLENCE FOR ENGLISH LANGUAGE TEACHING IN ULAANBAATAR WWW.MN.USEMBASSY.GOV  PUBLISHED:2025/06/12      9 MONGOLIA'S 'DRAGON PRINCE' DINOSAUR WAS FORERUNNER OF T. REX WWW.REUTERS.COM PUBLISHED:2025/06/12      10 MONGOLIA’S PIVOT TO CENTRAL ASIA AND THE CAUCASUS: STRATEGIC REALIGNMENTS AND REGIONAL IMPLICATIONS WWW.CACIANALYST.ORG  PUBLISHED:2025/06/12      БӨӨРӨЛЖҮҮТИЙН ЦАХИЛГААН СТАНЦЫН II БЛОКИЙГ 12 ДУГААР САРД АШИГЛАЛТАД ОРУУЛНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/15     ОРОН СУУЦНЫ ҮНЭ 14.3 ХУВИАР ӨСЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/15     МОНГОЛ УЛСЫН 34 ДЭХ ЕРӨНХИЙ САЙДААР Г.ЗАНДАНШАТАРЫГ ТОМИЛЛОО WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/13     SXCOAL: МОНГОЛЫН НҮҮРСНИЙ ЭКСПОРТ ЗАХ ЗЭЭЛИЙН ХҮНДРЭЛИЙН СҮҮДЭРТ ХУМИГДАЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/06/13     МОНГОЛ БАНК: ТЭТГЭВРИЙН ЗЭЭЛД ТАВИХ ӨР ОРЛОГЫН ХАРЬЦААГ 50:50 БОЛГОЛОО WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/13     МОНГОЛ ДАХЬ НҮБ-ЫН ХҮҮХДИЙН САН, ТЭРБУМ МОД ҮНДЭСНИЙ ХӨДӨЛГӨӨНИЙГ ДЭМЖИХ САН, КРЕДИТЕХ СТМ ББСБ ХХК “ХҮҮХЭД БҮРД – НЭГ МОД” САНААЧИЛГЫГ ХАМТРАН ХЭРЭГЖҮҮЛНЭ WWW.BILLIONTREE.MN НИЙТЭЛСЭН:2025/06/13     ЕРӨНХИЙЛӨГЧИЙН ТАМГЫН ГАЗРЫН ДАРГААР А.ҮЙЛСТӨГӨЛДӨР АЖИЛЛАНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/06/13     34 ДЭХ ЕРӨНХИЙ САЙД Г.ЗАНДАНШАТАР ХЭРХЭН АЖИЛЛАНА ГЭЖ АМЛАВ? WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/13     “АНГЛИ ХЭЛНИЙ МЭРГЭШЛИЙН ТӨВ”-ИЙГ МУИС-Д НЭЭЛЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/13     Г.ЗАНДАНШАТАР БАЯЛГИЙН САНГИЙН БОДЛОГЫГ ҮРГЭЛЖЛҮҮЛНЭ ГЭЖ АМЛАЛАА WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/12    

Rio Tinto slows expansion of Oyu Tolgoi copper mine in Mongolia www.ft.com

Rio Tinto has slowed work on the underground expansion of its giant copper mine in Mongolia’s Gobi desert, raising the prospect of further delays at its most important project.

The Anglo-Australian miner said the movement of goods and people, including overseas contractors and technical experts, had become more difficult in Mongolia and across the Chinese border after the first case of the coronavirus was recorded in the country and the government took action to limit its spread.

As a result, work on a multibillion underground expansion of the Oyu Tolgoi copper mine had been slowed, Rio said.

“This is slowing down construction activity at the underground project,” said Arnaud Soirat, the head of Rio’s copper and diamonds business. “It is too early to determine the impact of this and the team is doing all they can to minimise the disruption in a challenging environment.”

The company said it would update the market once more information was available and that operations in the open pit at Oyu Tolgoi and deliveries to customers in China were continuing as normal.

The underground expansion of Oyu Tolgoi is Rio’s most important growth project and will increase its production of copper at a time when the shift to renewable energy is driving growing demand for the metal for use in electric vehicles and wind turbines.

But the project, aimed at increasing output to more than 500,000 ounces a year, has been dogged by problems.

Last year Rio warned of a 16 to 30-month delay to first production — which is now expected between May 2022 and June 2023 — and a cost blowout of $1.2bn-$1.9bn. The company blamed difficult ground conditions.

Rio expects to complete a new mine design by the end of June and reveal new cost and timing estimates in the second half of the year.

Shares in Rio fell 5.8 per cent to 3,082p, close to a three-year low.

“This is likely to be the first of many changes to the underlying project path, production profile and capex spending across not just Rio Tinto but the entire mining industry,” said Tyler Broda, analyst at RBC Capital Markets.

“Balance sheets in the sector generally remain very strong, but like almost all other industries, the potential for operational stoppages is likely to create a material build of working capital. We see the miners generally being in a strong relative position to cope but clearly these are volatile times and estimates and forecasts are likely to be changing rapidly.”

Canadian group Lundin Mining has announced the suspension of construction at its Neves-Corvo zinc expansion project in Portugal because of travel restrictions related to the coronavirus.