1 MONGOLIA INVESTMENT FORUM TAKES PLACE IN NEW YORK CITY WWW.MONTSAME.MN PUBLISHED:2025/04/30      2 MONGOLIA’S LENDMN SECURES $20M DEBT FINANCING FROM LENDABLE WWW.FINTECHFUTURES.COM  PUBLISHED:2025/04/30      3 JADE GAS CONFIRMS SIGNIFICANT GAS POTENTIAL IN MONGOLIA WWW.TIPRANKS.COM  PUBLISHED:2025/04/30      4 TRANSFORMING REMOTE MINING: HOW IPCC TECHNOLOGY CAN REDEFINE OPEN-PIT OPERATIONS IN MONGOLIA’S GOBI DESERT WWW.UBPOST.MN PUBLISHED:2025/04/30      5 MONGOLIA REMAINS UNDEFEATED AT THE ICE HOCKEY WORLD CHAMPIONSHIP 2025 DIVISION III WWW.MONTSAME.MN PUBLISHED:2025/04/30      6 PRIME MINISTER OYUN-ERDENE VISITS EGIIN GOL HYDROPOWER PLANT PROJECT SITE WWW.MONTSAME.MN PUBLISHED:2025/04/30      7 ‘I FELT CAUGHT BETWEEN CULTURES’: MONGOLIAN MUSICIAN ENJI ON HER BEGUILING, BORDER-CROSSING MUSIC WWW.THEGUARDIAN.COM PUBLISHED:2025/04/30      8 POWER OF SIBERIA 2: ECONOMIC OPPORTUNITY OR GEOPOLITICAL RISK FOR MONGOLIA? WWW.THEDIPLOMAT.COM PUBLISHED:2025/04/29      9 UNITED AIRLINES TO LAUNCH FLIGHTS TO MONGOLIA IN MAY WWW.MONTSAME.MN PUBLISHED:2025/04/29      10 SIGNATURE OF OIL SALES AGREEMENT FOR BLOCK XX PRODUCTION WWW.RESEARCH-TREE.COM  PUBLISHED:2025/04/29      ДӨРВӨН УЛИРЛЫН АЯЛАЛ ЖУУЛЧЛАЛЫН ҮЙЛ АЖИЛЛАГАА ЭРХЛЭГЧДЭД ХӨНГӨЛӨЛТТЭЙ ЗЭЭЛ ОЛГОНО WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/04/30     Н.УЧРАЛ: НЭЭЛТТЭЙ СОНГОН ШАЛГАРУУЛАЛТ ЗАРЛАЖ ҮҮСМЭЛ ОРДУУДЫГ АШИГЛУУЛДАГ БОЛНО WWW.EAGLE.MN НИЙТЭЛСЭН:2025/04/30     849 ТЭРБУМЫН ӨРТӨГТЭЙ "ГАШУУНСУХАЙТ-ГАНЦМОД" БООМТЫН ТЭЗҮ-Д ТУРШЛАГАГҮЙ, МОНГОЛ 2 КОМПАНИ ҮНИЙН САНАЛ ИРҮҮЛЭВ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/04/30     ХУУЛЬ БУСААР АШИГЛАЖ БАЙСАН "БОГД УУЛ" СУВИЛЛЫГ НИЙСЛЭЛ ӨМЧЛӨЛДӨӨ БУЦААВ WWW.NEWS.MN НИЙТЭЛСЭН:2025/04/30     МЕТРО БАРИХ ТӨСЛИЙГ ГҮЙЦЭТГЭХЭЭР САНАЛАА ӨГСӨН МОНГОЛЫН ГУРВАН КОМПАНИ WWW.EAGLE.MN НИЙТЭЛСЭН:2025/04/30     "UPC RENEWABLES" КОМПАНИТАЙ ХАМТРАН 2400 МВТ-ЫН ХҮЧИН ЧАДАЛТАЙ САЛХИН ЦАХИЛГААН СТАНЦ БАРИХААР БОЛОВ WWW.EAGLE.MN НИЙТЭЛСЭН:2025/04/30     ОРОСЫН МОНГОЛ УЛС ДАХЬ ТОМООХОН ТӨСЛҮҮД ДЭЭР “ГАР БАРИХ” СОНИРХОЛ БА АМБИЦ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/04/30     МОНГОЛ, АНУ-ЫН ХООРОНД ТАВДУГААР САРЫН 1-НЭЭС НИСЛЭГ ҮЙЛДЭНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/04/29     ЕРӨНХИЙ САЙД Л.ОЮУН-ЭРДЭНЭ ЭГИЙН ГОЛЫН УЦС-ЫН ТӨСЛИЙН ТАЛБАЙД АЖИЛЛАЖ БАЙНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/04/29     Ц.ТОД-ЭРДЭНЭ: БИЧИГТ БООМТЫН ЕРӨНХИЙ ТӨЛӨВЛӨГӨӨ БАТЛАГДВАЛ БУСАД БҮТЭЭН БАЙГУУЛАЛТЫН АЖЛУУД ЭХЛЭХ БОЛОМЖ БҮРДЭНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/04/29    

Rio Tinto slows expansion of Oyu Tolgoi copper mine in Mongolia www.ft.com

Rio Tinto has slowed work on the underground expansion of its giant copper mine in Mongolia’s Gobi desert, raising the prospect of further delays at its most important project.

The Anglo-Australian miner said the movement of goods and people, including overseas contractors and technical experts, had become more difficult in Mongolia and across the Chinese border after the first case of the coronavirus was recorded in the country and the government took action to limit its spread.

As a result, work on a multibillion underground expansion of the Oyu Tolgoi copper mine had been slowed, Rio said.

“This is slowing down construction activity at the underground project,” said Arnaud Soirat, the head of Rio’s copper and diamonds business. “It is too early to determine the impact of this and the team is doing all they can to minimise the disruption in a challenging environment.”

The company said it would update the market once more information was available and that operations in the open pit at Oyu Tolgoi and deliveries to customers in China were continuing as normal.

The underground expansion of Oyu Tolgoi is Rio’s most important growth project and will increase its production of copper at a time when the shift to renewable energy is driving growing demand for the metal for use in electric vehicles and wind turbines.

But the project, aimed at increasing output to more than 500,000 ounces a year, has been dogged by problems.

Last year Rio warned of a 16 to 30-month delay to first production — which is now expected between May 2022 and June 2023 — and a cost blowout of $1.2bn-$1.9bn. The company blamed difficult ground conditions.

Rio expects to complete a new mine design by the end of June and reveal new cost and timing estimates in the second half of the year.

Shares in Rio fell 5.8 per cent to 3,082p, close to a three-year low.

“This is likely to be the first of many changes to the underlying project path, production profile and capex spending across not just Rio Tinto but the entire mining industry,” said Tyler Broda, analyst at RBC Capital Markets.

“Balance sheets in the sector generally remain very strong, but like almost all other industries, the potential for operational stoppages is likely to create a material build of working capital. We see the miners generally being in a strong relative position to cope but clearly these are volatile times and estimates and forecasts are likely to be changing rapidly.”

Canadian group Lundin Mining has announced the suspension of construction at its Neves-Corvo zinc expansion project in Portugal because of travel restrictions related to the coronavirus.