1 MONGOLIA INVESTMENT FORUM TAKES PLACE IN NEW YORK CITY WWW.MONTSAME.MN PUBLISHED:2025/04/30      2 MONGOLIA’S LENDMN SECURES $20M DEBT FINANCING FROM LENDABLE WWW.FINTECHFUTURES.COM  PUBLISHED:2025/04/30      3 JADE GAS CONFIRMS SIGNIFICANT GAS POTENTIAL IN MONGOLIA WWW.TIPRANKS.COM  PUBLISHED:2025/04/30      4 TRANSFORMING REMOTE MINING: HOW IPCC TECHNOLOGY CAN REDEFINE OPEN-PIT OPERATIONS IN MONGOLIA’S GOBI DESERT WWW.UBPOST.MN PUBLISHED:2025/04/30      5 MONGOLIA REMAINS UNDEFEATED AT THE ICE HOCKEY WORLD CHAMPIONSHIP 2025 DIVISION III WWW.MONTSAME.MN PUBLISHED:2025/04/30      6 PRIME MINISTER OYUN-ERDENE VISITS EGIIN GOL HYDROPOWER PLANT PROJECT SITE WWW.MONTSAME.MN PUBLISHED:2025/04/30      7 ‘I FELT CAUGHT BETWEEN CULTURES’: MONGOLIAN MUSICIAN ENJI ON HER BEGUILING, BORDER-CROSSING MUSIC WWW.THEGUARDIAN.COM PUBLISHED:2025/04/30      8 POWER OF SIBERIA 2: ECONOMIC OPPORTUNITY OR GEOPOLITICAL RISK FOR MONGOLIA? WWW.THEDIPLOMAT.COM PUBLISHED:2025/04/29      9 UNITED AIRLINES TO LAUNCH FLIGHTS TO MONGOLIA IN MAY WWW.MONTSAME.MN PUBLISHED:2025/04/29      10 SIGNATURE OF OIL SALES AGREEMENT FOR BLOCK XX PRODUCTION WWW.RESEARCH-TREE.COM  PUBLISHED:2025/04/29      ДӨРВӨН УЛИРЛЫН АЯЛАЛ ЖУУЛЧЛАЛЫН ҮЙЛ АЖИЛЛАГАА ЭРХЛЭГЧДЭД ХӨНГӨЛӨЛТТЭЙ ЗЭЭЛ ОЛГОНО WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/04/30     Н.УЧРАЛ: НЭЭЛТТЭЙ СОНГОН ШАЛГАРУУЛАЛТ ЗАРЛАЖ ҮҮСМЭЛ ОРДУУДЫГ АШИГЛУУЛДАГ БОЛНО WWW.EAGLE.MN НИЙТЭЛСЭН:2025/04/30     849 ТЭРБУМЫН ӨРТӨГТЭЙ "ГАШУУНСУХАЙТ-ГАНЦМОД" БООМТЫН ТЭЗҮ-Д ТУРШЛАГАГҮЙ, МОНГОЛ 2 КОМПАНИ ҮНИЙН САНАЛ ИРҮҮЛЭВ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/04/30     ХУУЛЬ БУСААР АШИГЛАЖ БАЙСАН "БОГД УУЛ" СУВИЛЛЫГ НИЙСЛЭЛ ӨМЧЛӨЛДӨӨ БУЦААВ WWW.NEWS.MN НИЙТЭЛСЭН:2025/04/30     МЕТРО БАРИХ ТӨСЛИЙГ ГҮЙЦЭТГЭХЭЭР САНАЛАА ӨГСӨН МОНГОЛЫН ГУРВАН КОМПАНИ WWW.EAGLE.MN НИЙТЭЛСЭН:2025/04/30     "UPC RENEWABLES" КОМПАНИТАЙ ХАМТРАН 2400 МВТ-ЫН ХҮЧИН ЧАДАЛТАЙ САЛХИН ЦАХИЛГААН СТАНЦ БАРИХААР БОЛОВ WWW.EAGLE.MN НИЙТЭЛСЭН:2025/04/30     ОРОСЫН МОНГОЛ УЛС ДАХЬ ТОМООХОН ТӨСЛҮҮД ДЭЭР “ГАР БАРИХ” СОНИРХОЛ БА АМБИЦ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/04/30     МОНГОЛ, АНУ-ЫН ХООРОНД ТАВДУГААР САРЫН 1-НЭЭС НИСЛЭГ ҮЙЛДЭНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/04/29     ЕРӨНХИЙ САЙД Л.ОЮУН-ЭРДЭНЭ ЭГИЙН ГОЛЫН УЦС-ЫН ТӨСЛИЙН ТАЛБАЙД АЖИЛЛАЖ БАЙНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/04/29     Ц.ТОД-ЭРДЭНЭ: БИЧИГТ БООМТЫН ЕРӨНХИЙ ТӨЛӨВЛӨГӨӨ БАТЛАГДВАЛ БУСАД БҮТЭЭН БАЙГУУЛАЛТЫН АЖЛУУД ЭХЛЭХ БОЛОМЖ БҮРДЭНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/04/29    

Ivanhoe’s Kakula mine advances ahead of schedule www.mining.com

Ivanhoe (TSX: IVN) announced on Monday that underground development at the Kakula copper mine in the Democratic Republic of Congo continues to advance ahead of schedule and said it will bring the deposit into production on time and budget by the third quarter of 2021. .

The company reported that more than 13.5 kilometres (8 miles) of underground development is now completed, 4.2 kilometres (3 miles) ahead of schedule.

“The mining team is on pace to set a new monthly development record of 1.7 kilometres of advancement ─ 562 metres ahead of plan for the month,” the company said in a release.

Ivanhoe said each blast in Kakula’s high-grade mining zone produces approximately 550 tonnes of ore.

Kakula’s high-grade ore stockpile is expected to total approximately 1.5 million tonnes prior to the start of initial production.

According to the pre-feasibility study (PFS) released last year, if all phases are completed the Kamoa-Kakula project is expected to reach peak annual production of more than 700,000 tonnes of copper.

The mining company also announced cost-saving measures that should cut costs by about $75 million, including lower expenditures this year at its Platreef palladium-platinum-nickel-copper-gold-rhodium project in South Africa and at its Kipushi zinc-copper-lead-germanium mine in the DRC.

Work on Platreef’s first shaft will continue, but the company has reduced the project’s 2020 budget to $41.7 million, down from $60 million, and trimmed its budget for Kipushi to $28.7 million, down from $40 million.

The company also announced voluntary salary reductions by senior management of up to 35% for a six-month period, and the suspension of all short-term incentive award payments for 2020.

In addition, Ivanhoe has trimmed its corporate and senior management headcount and reduced its footprint of global offices.

The company’s head office will remain in South Africa and be supported by satellite offices in Beijing and London.

In terms of management changes, Egizio Bianchini, Ivanhoe’s executive vice chairman, will relinquish his executive role but remain as vice chairman and a director.

The initiatives “are designed to further build on our robust cash and cash equivalents of approximately $600 million and essentially no debt,” Marna Cloete, the company’s CEO said.

Andrew Mikitchook of BMO Capital Markets has an outperform rating on the stock and a price target of $9.00 per share, according to The Northern Miner.

At presstime in Toronto the company’s shares were trading at $2.69 apiece within a 52-week trading range of $1.80 and $4.54.

“The company is in a strong financial position with $603 million at the end of March with today’s press release highlighting ~$75 million in cost savings through 2021 including the reduction of activities at Platreef and Kipushi, deferral of exploration activities, and voluntary management salary reductions,” Mikitchook wrote in a research note.

“The company continues to prioritize focus towards developing Kakula on time and on budget.”