1 14TH MBD MISSION FOR MBCC'S "DOING BUSINESS WITH MONGOLIA SEMINAR & CHRISTMAS RECEPTION" AND BUSINESS PROGRAM DEC 08- 14. 2025 LONDON, UK WWW.MONGOLIANBUSINESSDATABASE.COM PUBLISHED:2025/09/16      2 IMF WRAPS UP 2025 ARTICLE IV TALKS WITH MONGOLIA WWW.IMF.ORG PUBLISHED:2025/09/16      3 POSCO INTERNATIONAL TO LAUNCH WASTEWATER HEAT DISTRICT HEATING PROJECT IN MONGOLIA WWW.CM.ASIAE.CO.KR  PUBLISHED:2025/09/16      4 MONGOLIA'S EXTERNAL DEBT UP 12.7 PCT IN Q2 2025 WWW.NEWS.AZ PUBLISHED:2025/09/16      5 2025 AUTUMN SESSION OF THE STATE GREAT KHURAL COMMENCES WITH STRUCTURAL REFORMS WWW.MONTSAME.MN PUBLISHED:2025/09/16      6 MONGOLIA SURPASSES 617,000 TOURIST ARRIVALS BY MID-SEPTEMBER 2025 WWW.MONTSAME.MN PUBLISHED:2025/09/16      7 ODD-EVEN TRAFFIC RESTRICTION CONCLUDES WWW.UBPOST.MN PUBLISHED:2025/09/15      8 MMC ANNOUNCES FIRST GOLD POUR COMPLETED AT THE BAYAN KHUNDII MINE IN MONGOLIA WWW.SG.FINANCE.YAHOO.COM  PUBLISHED:2025/09/15      9 MKE LAUNCHES CARTRIDGE PRODUCTION LINE IN MONGOLIA WWW.RAILLYNEWS.COM  PUBLISHED:2025/09/15      10 MONGOLIA’S LARGEST MINING EVENT HIGHLIGHTS INVESTMENT AND RESPONSIBLE MINING WWW.MONTSAME.MN PUBLISHED:2025/09/14      14 ДЭХЬ УДААГИЙН MBCCI’S “ DOING BUSINESS WITH MONGOLIA SEMINAR & CHRISTMAS RECEPTION” B2B NETWORKING БОЛОН БИЗНЕС ХӨТӨЛБӨР 2025 ОНЫ 12 САРЫН 08 -13 ЛОНДОН ХОТ, ИХ БРИТАНИ WWW.MONGOLIANBUSINESSDATABASE.COM НИЙТЭЛСЭН:2025/09/16     ЭДИЙН ЗАСГИЙН ТӨРӨЛЖИЛТИЙН ИНДЕКСЭЭР МОНГОЛ УЛС 145 ОРНООС 139-Д БИЧИГДЖЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2025/09/16     ӨНӨӨДӨР: “СЭЛБЭ 20 МИНУТЫН ХОТ”-ЫН ДАРААГИЙН ЭЭЛЖИЙН ОРОН СУУЦНЫ ТӨСЛИЙН БҮТЭЭН БАЙГУУЛАЛТЫГ ЭХЛҮҮЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/09/16     ШЭНЬ МИНЬЖУАНЬ: БНХАУ МОНГОЛ УЛСЫГ ШХАБ-ЫН ГЭР БҮЛД НЭГДЭЖ, ХАМТЫН АЖИЛЛАГААГАА ӨРГӨЖҮҮЛЭХИЙГ УРЬСАН WWW.ITOIM.MN НИЙТЭЛСЭН:2025/09/15     Г.ЗАНДАШАТАР: ТӨРИЙН ДАНХАР БҮТЦИЙГ ХУМИХ АЖИЛ ИРЭХ ОНД Ч ҮРГЭЛЖИЛНЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/09/15     Ц.ТУВААН: НҮҮРСНИЙ ҮНЭ 3 САР ТУТАМ ШИНЭЧЛЭГДЭНЭ. ГЭРЭЭНД ЯМАР Ч НУУЦ БАЙХГҮЙ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/09/15     ХАНЫН МАТЕРИАЛД 1800 АЙЛЫН ОРОН СУУЦ БАРИХ ТӨСЛИЙН ГҮЙЦЭТГЭГЧ ШАЛГАРЛАА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/09/15     "ТАТВАРЫН ХЭТ ӨНДӨР ТООЦОО БИЗНЕС ЭРХЛЭГЧДИЙГ ХААЛГАА БАРИХАД ХҮРГЭНЭ" WWW.NEWS.MN НИЙТЭЛСЭН:2025/09/15     ГАДААД ХУДАЛДААНЫ НӨХЦӨЛИЙН ИНДЕКС ӨМНӨХ ОНООС 4.1 ХУВИАР БУУРЧЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2025/09/15     ЭХНИЙ НАЙМАН САРЫН БАЙДЛААР 600 МЯНГАН ЖУУЛЧИН ИРЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/09/15    

Turquoise Hill expects Oyu Tolgoi blowout to top $1.8bn www.mining.com

Canada’s Turquoise Hill Resources (TSX, NYSE: TRQ) said this week that an ongoing expansion of the giant Oyu Tolgoi copper-gold-silver mine in Mongolia is expected to cost as much as an additional $1.8 billion.

The Rio Tinto-controlled company and mine operator had expected the underground expansion to cost $5.3 billion when it was approved in 2015. Last year, however, Turquoise Hill flagged stability risks associated with the original project design, adding that amendments to it could increase costs by as much as an additional $1.9 billion.

The Vancouver-based miner also warned at the time of further delays of up to two and a half years, noting it wouldn’t know the exact scale of schedule and costs blowouts until mid-2020.

Oyu Tolgoi’s operator now says the expansion will need an estimated $1.5 billion, in a range of $1.3 billion to $1.8 billion. This may change due to any additional scheduling delays or increases in capital costs arising from the impacts of the covid-19 pandemic, it said.

In terms of project completion, Turquoise anticipates it would take two extra years than originally planned for the project to begin production, with a 21 to 29 months range.

“It is still a range. It is still fairly broad, but it is narrower (than the 2019 estimates), and importantly, it stayed within the range we have given,” chief executive officer Ulf Quellmann said.

Block caving
Turquoise Hill’s boss noted the company had selected block caving for the mine design, as it considers it a “more resilient mine plan that provides the best opportunity for success.”

Quellmann also said that the decision was based on an extensive trade-off analysis taking into account the reserve recovery, geotechnical, constructability, operability, schedule, as well as cost and value risks.

Turquoise Hill has $1.8 billion, which Quellmann says is sufficient to fund operations, underground and power development into the third quarter of 2021.

He also said that a definitive estimate will be published in the second half of the year.

Turquoise Hill is currently in discussions with Oyu Tolgoi’s 50.8%-owner, Rio Tinto (ASX, LON, NYSE: RIO), regarding a proposal for an interim $4 billion funding over and above the liquidity currently available.

The massive deposit was discovered in Mongolia’s south Gobi Desert in 2001. Rio Tinto gained control of it in 2012, with the government of Mongolia retaining one-third ownership of the asset.

The ongoing expansion is expected to lift production from 125,000–150,000 tonnes in 2019 to 560,000 tonnes at peak output, targeted for 2025. This would make it the biggest new copper mine to come on stream in several years.

Oyu Tolgoi produced 35,203 tonnes of copper and 26,154 ounces of gold in the first three months of this year, which puts it on track to achieve 2020 production guidance.

One of Rio Tinto’s top investors, US hedge fund Pentwater Capital, said in April it would push for a management shakeup at the operation, due to what it calls “a massive devaluation” of the asset.



Published Date:2020-05-17