1 MONGOLIA RECEIVES NATIONAL PRODUCTIVITY MASTER PLAN (2026–35) TO DRIVE PRODUCTIVITY-LED GROWTH, RESILIENCE, AND SHARED PROSPERITY WWW.GLOBALNEWSWIRE.COM PUBLISHED:2026/01/29      2 78 FOREIGN NATIONALS FROM 12 COUNTRIES DEPORTED FROM MONGOLIA WWW.GOGO.MN PUBLISHED:2026/01/29      3 JAPANESE MILITARY MAPS REVEAL FIRST LOOK AT THE HIDDEN GREAT MONGOLIAN ROAD WWW.INDIANDEFENCEREVIEW.COM PUBLISHED:2026/01/29      4 SILVER ELEPHANT ANNOUNCES FAVORABLE TAX TRIBUNAL RULING IN MONGOLIA WWW.INVESTINGNEWS.COM PUBLISHED:2026/01/29      5 MELTING RESERVES OF POWER: MONGOLIA’S GLACIERS AND THE FUTURE OF ENERGY AND FOOD SECURITY WWW.RELIEFWEB.INT PUBLISHED:2026/01/28      6 MONGOLIA CONSTRUCTION INDUSTRY REPORT 2025: OUTPUT TO GROW AT AN AAGR OF 4.3% BETWEEN 2026-2029, SUPPORTED BY INVESTMENTS IN TRANSPORTATION, ELECTRICITY, AND INFRASTRUCTURE - RESEARCHANDMARKETS.COM WWW.BUSINESSWIRE.COM PUBLISHED:2026/01/28      7 EMERGING CHANGES IN THE METHODS AND TACTICS OF HUMAN TRAFFICKING WWW.GOV.MN PUBLISHED:2026/01/28      8 MONGOLIA PLANS TO PRODUCE 90 MILLION TONS OF COAL THIS YEAR WWW.MONTSAME.MN PUBLISHED:2026/01/27      9 MINING SECTOR WEEK OPENS, PLANNED LEGAL REFORMS OUTLINED WWW.MONTSAME.MN PUBLISHED:2026/01/27      10 13 PEOPLE FREEZE TO DEATH IN MONGOLIA IN JANUARY WWW.XINHUANET.COM PUBLISHED:2026/01/27      МОНГОЛ УЛСЫН ГАДААД ПАСПОРТ ХҮЧИРХЭГ БАЙДЛААРАА 73-Т ЖАГСЖЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/01/29     АНУ-ЫН ХУДАЛДАА, ХӨГЖЛИЙН АГЕНТЛАГ МОНГОЛД 2.2 САЯ ДОЛЛАРЫН БУЦАЛТГҮЙ ТУСЛАМЖ ҮЗҮҮЛНЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/01/29     ЗЭСИЙН БАЯЖМАЛЫН ҮЙЛДВЭРИЙН ТӨСЛИЙН ХАМТРАГЧИЙГ ЭНЭ ОНЫ I УЛИРАЛД ШАЛГАРУУЛНА WWW.NEWS.MN НИЙТЭЛСЭН:2026/01/29     АЖ ҮЙЛДВЭРИЙН САЛБАРЫН НИЙТ ҮЙЛДВЭРЛЭЛ ӨМНӨХ ОНЫ МӨН ҮЕЭС 4.8 ХУВИАР ӨСӨВ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/01/28     ЗГ: ЗЭС ХАЙЛУУЛАХ ҮЙЛДВЭРИЙН СОНГОН ШАЛГАРУУЛАЛТЫН ТАЛААР МЭДЭЭЛНЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/01/28     12 УЛСЫН 78 ИРГЭНИЙГ АЛБАДАН ГАРГАВ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/01/28     “ХОГ ШАТААЖ, ЭРЧИМ ХҮЧ ҮЙЛДВЭРЛЭХ” ТӨСЛИЙН ГАЗАР ЧӨЛӨӨЛӨЛТ 71 ХУВЬТАЙ БАЙНА WWW.NEWS.MN НИЙТЭЛСЭН:2026/01/27     ОНЫ ЭХНИЙ ХАГАС ГЭХЭД АЛТ ТУШААЛТЫГ 20-30 ХУВИАР НЭМЭГДҮҮЛНЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/01/27     ХАВРЫН ЧУУЛГАНААР АМНАТ ТООЦОХ АРГАЧЛАЛЫГ ШИНЭЧИЛНЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/01/27     БАГАНУУРЫГ ТҮШИГЛЭН БАРИХ ШИНЭ ҮЙЛДВЭРТ 40МВТ-ИЙН ЭРЧИМ ХҮЧ ҮЙЛДВЭРЛЭНЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/01/27    

Steppe Gold plans production of 150,000oz gold per year www.news.mn

Steppe Gold is very pleased to provide an update on the Bankable Feasibility Study (“BFS”) underway for the expansion of the ATO Gold Mine into fresh rock ores with a planned production profile of approximately 150,000oz gold equivalent per year and an estimated ten year mine life.

In parallel with the company’s aggressive exploration program currently underway at the ATO Gold Mine, the Company has retained technical and project management advisers and is now working towards the completion of a BFS with a target date of March 2021. The BFS is built on a previously completed Centerra Gold 2012 Internal Feasibility study and on further internal studies undertaken by Steppe Gold from 2017 to present.

The Company is currently working on updating all resources and reserves for the ATO1, ATO2 and ATO4 deposits in addition to a maiden resource and reserve for the Mungu Discovery. Steppe Gold has completed a substantial amount of drilling at the ATO Gold Mine since resources and reserves were last calculated. The Company has drilled 1,840 metres at ATO1, 1,662 metres at ATO2, 14,760 metres at ATO4 and over 26,573 metres have been drilled at the Mungu Discovery.

Financing strategies for the ATO Gold Mine Expansion are advancing in parallel with the BFS process with construction targeted for commencement in mid-2021. The Company has commenced discussions with project finance and lending groups and it expects to fund its equity contribution from operating cash flows and cash on hand. Post the recent placement of shares to Eric Sprott the Company has approximately USD 22M cash on hand with regular gold sales from the ATO Gold Mine continuing.

The Company expects a smooth transition from open cut oxide ores being heap leached to the processing of open cut fresh rock ores through a new flotation and CIL circuit. The Company is targeting first production from the ATO Gold Mine Expansion in mid to late 2022.

Steppe Gold CEO Mr Bataa Tumur-Ochir commented: “With our Phase 1 production now well underway and generating strong cash flows, we are excited to be accelerating the expansion of the ATO Gold Mine into fresh rock ores. Previous studies by Centerra and our own in-house work provide us with a high level of confidence in the economic potential of the fresh rock expansion.”

He continued:

“This larger second phase will clearly demonstrate that the ATO Gold Mine is a robust, long life, low cost operation with considerable exploration growth through aggressive drilling programs.” (Yahoo Finance)



Published Date:2020-07-30