1 N.UCHRAL: FINISH THE NAADAM FESTIVAL, PREPARE FOR WINTER WWW.GOGO.MN PUBLISHED:2026/07/27      2 OVER 2,800 DELEGATES EXPECTED FOR COP17 IN MONGOLIA WWW.GOGO.MN PUBLISHED:2026/07/27      3 VICTORIA DELMON ANNOUNCED AS WORLD BANK GROUP NEW COUNTRY MANAGER FOR MONGOLIA WWW.MONTSAME.MN PUBLISHED:2026/07/27      4 AI IN GOVERNMENT WWW.GOGO.MN PUBLISHED:2026/07/27      5 SA GAS COMPANY SIGNS BILLION-DOLLAR AGREEMENT WWW.INDAILYSA.COM.AU/ PUBLISHED:2026/07/27      6 MONGOLIA’S HUNNU NOBILITY CEMETERY COMPLEXES ADDED TO UNESCO WORLD HERITAGE LIST WWW.QAZINFORM.COM PUBLISHED:2026/07/27      7 MOM'S TOUCH OPENS 20TH STORE IN MONGOLIA, BECOMES NO. 2 QSR BRAND WWW.EN.SEDAILY.COM PUBLISHED:2026/07/27      8 GOVERNMENT DOMESTIC SECURITIES WORTH MNT 10 BILLION TRADED WWW.MONTSAME.MN PUBLISHED:2026/07/24      9 TMK ENERGY APPOINTS U.S. PRIVATE EQUITY VETERAN STEVE SKINNER AS COO TO DRIVE MONGOLIAN GAS PROJECT WWW.TIPRANKS.COM PUBLISHED:2026/07/24      10 ERDENE STOCK TRACKS LATEST RESOURCE UPDATE AS MONGOLIA GOLD PROJECT ADVANCES WWW.AD-HOC-NEWS.DE PUBLISHED:2026/07/24      Б.МӨНХТАМИР: COP17 ХУРАЛД УЛСЫН ТӨСВӨӨС 267 ТЭРБУМ ТӨГРӨГ ЗАРЦУУЛНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/07/27     МОНГОЛБАНК: ИНФЛЯЦ 2027 ОНООС ЗОРИЛТОТ ТҮВШИНД ТОГТВОРЖИХ ТӨЛӨВТЭЙ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/07/27     ДЭЛХИЙН БАНК ГРУППИЙН МОНГОЛ ДАХЬ СУУРИН ТӨЛӨӨЛӨГЧӨӨР ВИКТОРИА ДЕЛМОН ТОМИЛОГДЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/07/27     ЕРӨНХИЙ САЙД Н.УЧРАЛ: НАЙР НААДМАА ДУУСГА. ӨВӨЛДӨӨ БЭЛД WWW.GOGO.MN НИЙТЭЛСЭН:2026/07/27     ЗЭСИЙН ЭКСПОРТ НҮҮРСИЙГ ДАВЖ, ЭДИЙН ЗАСГИЙН ШИНЭ ТУЛГУУР БОЛЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/07/27     ДАМБАДАРЖАА ДУЛААНЫ СТАНЦЫГ ЭНЭ ОНД АШИГЛАЛТАД ОРУУЛНА WWW.NEWS.MN НИЙТЭЛСЭН:2026/07/27     ЖУУЛЧДЫН ТОО ӨМНӨХ ОНЫ МӨН ҮЕЭС 13.7 ХУВИАР НЭМЭГДЖЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/07/27     МОНГОЛ УЛСААС НҮБ-ЫН АНДЭЗНК-ЫН ДЭРГЭД СУУХ БАЙНГЫН ТӨЛӨӨЛӨГЧ В.ОЮУ ИТГЭМЖЛЭХ ЗАХИДЛАА ГАРДУУЛАВ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/07/24     “GLOBAL SILHOUETTE” ОЛОН УЛСЫН ҮЗЭСГЭЛЭН ХААН ГАЛЕРЕЙД НЭЭЛТЭЭ ХИЙЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/07/24     РИО ТИНТО-ТОЙ ХИЙХ ХЭЛЭЛЦЭЭРИЙН НОГДОЛ АШИГ АВАХ АЖЛЫН ХЭСГИЙГ САНГИЙН САЙД АХАЛНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/07/24    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Mongolia seeks Rio backing to terminate mine agreement www.ft.com

The government of Mongolia is seeking Rio Tinto’s agreement to terminate the deal that underpins the construction of a $6.75bn underground copper mine in the Gobi Desert, according to people with knowledge of the situation.
The ruling Mongolian People’s party and its new prime minister Luvsannamsrain Oyun-Erdene is facing pressure from parliament to replace the underground development plan for the Oyu Tolgoi mine.
But rather than act unilaterally and risk future foreign investment projects in the country, Ulan Bator has asked the Anglo-Australian miner whether it is prepared to mutually terminate the plan and replace it with an agreement that offers better terms, the people said.
The underground expansion of Oyu Tolgoi has been dogged by problems and disputes with the government. The project — Rio’s most important — is already $1.5bn over budget and almost two years behind schedule.
The government threatened last month to halt development, saying the delays had eroded the economic benefits the country had hoped for.
At peak production Oyu Tolgoi will be the fourth-biggest copper mine in the world, producing almost 500,000 tonnes a year from its existing open pit and underground mine. A decision on whether to start complex caving operations must be taken by June. First production is expected in October 2022.
Oyu Tolgoi, the country’s biggest source of foreign direct investment, has created thousands of well-paid jobs and generated almost $3bn of taxes and fee revenue over the past decade.
Signed in 2015, the UDP, also known as the Dubai agreement, put the underground project back on track after an earlier dispute between Rio and the government.
The agreement — and $4.4bn of project financing — was pulled together by Rio’s former chief executive Jean-Sébastien Jacques and the nation’s then-prime minister Chimediin Saikhanbileg.
It set out the fee Rio will receive for managing the project as well as the interest rates on the cash Ulan Bator has borrowed to finance its share of the construction costs.
However, the UDP was never approved by Mongolia’s parliament and has become a focal point for critics who say the country should receive a greater share of the financial benefits from mine.
A parliamentary resolution was passed in December 2019 ordering the government to improve the terms of the UDP.
“The government has to fix the legitimacy issue,” said one person with knowledge of the discussions. “Mutual termination of the UDP would achieve this.”
Rio has already told Ulan Bator it is prepared to “explore” a reduction of its project management fees and loan interest rates, according to documents seen by the Financial Times.
However, it is unlikely to agree a new development plan unless it also addresses some of the company’s concerns. These include a long-term power solution and Oyu Tolgoi’s budget for 2021.
Rio’s negotiations are now being led by Bold Baatar, a Mongolian national who was recently appointed to run Rio’s copper business.
“I acknowledge the government’s wish to improve the underground development plan and I am looking forward to discussing that with them, I hope in a way which promotes investor confidence in the country,” Baatar said in a statement.
The push to replace the UDP comes ahead of presidential elections in June, which the government hopes to win to complete a clean sweep of Mongolia’s hybrid parliamentary-presidential system. The government declined to comment.


Published Date:2021-02-08