1 RIO-GLENCORE DEAL CLOSER THAN EVER WITH PREMIUM AND CEO IN FOCUS WWW.BLOOMBERG.COM PUBLISHED:2026/01/10      2 MONGOLIA'S INFLATION DOWN TO 7.5 PCT IN DECEMBER 2025 WWW.XINHUANET.COM PUBLISHED:2026/01/10      3 MONGOLIA ENERGY FACES MNT 412.3 BILLION TAX LIABILITY AFTER LOSING MONGOLIAN COURT CASE WWW.TIPRANKS.COM  PUBLISHED:2026/01/10      4 NUMBER OF FOREIGN NATIONALS RESIDING FOR OFFICIAL AND PRIVATE PURPOSES UP 7.4% WWW.MONTSAME.MN PUBLISHED:2026/01/10      5 SUSTAINABILITY RELATED REPORTING: READINESS ASSESSMENT MONGOLIA REPORT WWW.UNDP.ORG PUBLISHED:2026/01/10      6 GOVERNMENT TO FORMALLY APPROACH RIO TINTO, OYU TOLGOI TO SAFEGUARD NATIONAL INTEREST WWW.MONTSAME.MN PUBLISHED:2026/01/09      7 NON-COMPLIANT ADVERTISING BILLBOARDS TO BE REMOVED WWW.MONTSAME.MN PUBLISHED:2026/01/09      8 FROM TORONTO, CANADA TO PHU QUOC, VIETNAM: MONGOLIA’S BOLD 2026 AVIATION EXPANSION INCLUDES NEW FLIGHTS, VISA-FREE TRAVEL, AND AIRPORT UPGRADES! WWW.TRAVELANDTOURWORLD.COM PUBLISHED:2026/01/09      9 MONGOLIA TO MARK 820TH ANNIVERSARY OF THE GREAT MONGOL EMPIRE WWW.MONTSAME.MN PUBLISHED:2026/01/09      10 PARLIAMENT SUPPORTS SOLAR GER INITIATIVE UNDER NEW REGULATORY REFORMS WWW.MONTSAME.MN PUBLISHED:2026/01/09      Б.ДЭЛГЭРСАЙХАН: ХӨШИГИЙН ХӨНДИЙН ТӨМӨР ЗАМ, НАВИГАЦЫН ТОНОГ ТӨХӨӨРӨМЖИЙН ШИНЭЧЛЭЛИЙГ ЭНЭ ОНД ДУУСГАНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/01/11     УРЬДЧИЛАН ЗАХИАЛГА ӨГСӨН 260 ИРГЭНИЙГ ХОЁР ТЭРБУМ ТӨГРӨГӨӨР ХОХИРООЖЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/01/11     GLENCORE, RIO TINTO КОМПАНИУД НЭГДЭХ ХЭЛЭЛЦЭЭ ХИЙЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/01/10     Н.НАРАНБААТАР: ЭНЭ ОНД НҮҮРСНИЙ ЭКСПОРТЫН ХЭМЖЭЭГ 90 САЯ ТОННД БАРИНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/01/10     УЛААНБААТАРТ ӨНДӨР ТЕХНОЛОГИЙН ХОЁР ҮЙЛДВЭР БАЙГУУЛЖ, УСАН ХАНГАМЖИЙГ 80 ХУВИАР НЭМЭГДҮҮЛЛЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/01/09     ХУУЛЬ БУС ЭЗЭМШИЛД БАЙСАН 15 БАРИЛГА БАЙГУУЛАМЖИЙГ НИЙСЛЭЛД БУЦААН АВЧЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/01/09     МОНГОЛ УЛСАД 37 097 ГАДААД ИРГЭН ОРШИН СУУХ БҮРТГЭЛТЭЙ БАЙНА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/01/09     ҮСХ: 12 ДУГААР САРЫН ИНФЛЯЦ 7.5 ХУВЬТАЙ ГАРЛАА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/01/09     2026 ОНД НИЙСЛЭЛД ХЭРЭГЖИХ ТОМООХОН БҮТЭЭН БАЙГУУЛАЛТУУД WWW.ITOIM.MN НИЙТЭЛСЭН:2026/01/09     ДУЛААНЫ ТАРИФ НЭМЭГДҮҮЛЭХ ШИЙДВЭРИЙГ ХОЙШЛУУЛЖ, 2027 ОНЫ НЭГДҮГЭЭР САРЫН 1-НЭЭС НЭМНЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/01/09    

Oyu Tolgoi review raises doubts over Rio Tinto stance on cost overruns www.reuters.com

Aug 9 (Reuters) - Turquoise Hill Resources (TRQ.TO) said an independent review of$1.4 billion in cost overruns at the Oyu Tolgoi mine in Mongolia suggested that the project's troubles were not caused by the geology issues that mine operator Rio Tinto blamed in 2019.
The review "raises certain questions in relation to the project management process" around the cost blowout and delay, Turquoise Hill said.
"Rio Tinto will engage with the OT (Oyu Tolgoi) Board as soon as we have had the opportunity to review the report in detail," Australia's Rio Tinto (RIO.AX), (RIO.L) said in an emailed statement.
Rio owns 51% of Turquoise Hill, which owns 66% of the Oyu Tolgoi mine. The rest of the mine is owned by the government of Mongolia.
Costs to expand the Oyu Tolgoi mine, Rio's biggest copper growth project, have ballooned up to $6.75 billion from its original budget of $5.3 billion in 2016, raising friction over funding with Turquoise Hill.
The Wall Street Journal was first to report the news.


Published Date:2021-08-10