1 TRUMP’S SON WITH KAZAKH TUNGSTEN TIES LOST IN MONGOLIAN MOUNTAINS WWW.KZ.KURSIV.MEDIA PUBLISHED:2026/09/10      2 MONGOLIA TO HOLD PARLIAMENTARY HEARING ON EPSTEIN FILES IN OCTOBER WWW.AZERNEWS.AZ PUBLISHED:2026/09/10      3 MONGOLIA'S FOREIGN TRADE TURNOVER SURGES NEARLY 37 PCT IN FIRST 8 MONTHS WWW.XINHUANET.COM PUBLISHED:2026/09/10      4 MONGOLIA SIGNS MOU WITH BLACKROCK FMA WWW.MONTSAME.MN PUBLISHED:2026/09/10      5 MONGOLIA, UAE SIGN ENERGY COOPERATION MOU WWW.MONTSAME.MN PUBLISHED:2026/09/10      6 SPEAKERS OF MONGOLIA, VIETNAM HOLD OFFICIAL TALKS WWW.MONTSAME.MN PUBLISHED:2026/09/10      7 MONGOLIA AGREES TO PURCHASE 10,000 TONS OF GASOLINE AND 4,000 TONS OF JET FUEL FROM CHINA IN SEPTEMBER WWW.GOGO.MN PUBLISHED:2026/09/10      8 ADB SUPPORTS MONGOLIA'S FIRST GREEN-CERTIFIED RESIDENTIAL COMPLEX BUILT BY THE PRIVATE SECTOR WWW.ADB.ORG PUBLISHED:2026/09/09      9 MONGOLIA FINISHES FOURTH WITH 26 MEDALS AT WORLD NOMAD GAMES WWW.ASIANEWS.NETWORK PUBLISHED:2026/09/09      10 NEW FLIGHT ROUTES EXPLORED WITH HOKKAIDO AIRPORTS WWW.UBPOST.MN PUBLISHED:2026/09/09      ШАТАХУУНЫ НИЙЛҮҮЛЭЛТЭЭ УРТ ХУГАЦААНД ТОГТВОРЖУУЛЖ, ГАЗРЫН ТОС, НҮҮРС-ХИМИЙН ХАМТЫН АЖИЛЛАГААГ ӨРГӨЖҮҮЛНЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/10     ГОЛОМТ БАНК ХАРИЛЦАГЧДЫНХАА ХУДАЛДАА, ТӨЛБӨР ТООЦООГ ДЭМЖИХЭЭР BANK OF CHINA-ТАЙ СТРАТЕГИЙН ХАМТЫН АЖИЛЛАГААГ ЭХЛҮҮЛЛЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/10     АНЭУ-ТАЙ ЭРЧИМ ХҮЧНИЙ САЛБАРТ ХАМТРАН АЖИЛЛАНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/10     МАХ, БЕНЗИНИЙ ҮНИЙН НӨЛӨӨГӨӨР ИНФЛЯЦ 12.5 ХУВЬД ХҮРЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/10     МОНГОЛД ИРЖ БУЙ РИО ТИНТО ГРУППИЙН CEO САЙМОН ТРОТТ ГЭЖ ХЭН БЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/10     Ц.БАТБААТАР: ХАТУУ ЗОХИЦУУЛАЛТТАЙ 38 УЛСААС ОРЖ ИРЖ БАЙГАА ЭМҮҮДИЙГ ХӨНГӨЛӨЛТТЭЙ ЭМИЙН ЖАГСААЛТАД ХАМРУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/10     Н.УЧРАЛ: МИНИЙ ГЭР БҮЛ, АЖИЛ МЭРГЭЖЛИЙН НЭР ХҮНДЭД ХАЛДЛАА WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/10     СЭЛБЭ УХААЛАГ ХОТОД УНДНЫ УСНЫ ЗЭС ХООЛОЙ ШУГАМ УГСАРЧ БАЙНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/09     НАЙМДУГААР САРД ХҮНСНИЙ БҮЛГИЙН БҮТЭЭГДЭХҮҮНИЙ ҮНЭ 21.5 ХУВЬ НЭМЭГДЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/09     ЭРЧИМ ХҮЧНИЙ ҮНЭ НЭМЭХГҮЙН ТУЛД ТӨСӨВТ 200 ТЭРБУМ ТӨГРӨГИЙН ТАТААС ТУСГАЖЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/09    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Mongolia to 'carefully review' financing offer from Rio Tinto www.asia.nikkei.com

Mongolian officials said on Tuesday that they will "carefully review" a new plan from Rio Tinto for financing the costly expansion of the vast Oyu Tolgoi copper mine -- intimating that it could take years to reach agreement.
The rising cost of the new underground phase of the mine, now pegged at $6.8 billion, played a part in bringing down both Mongolia's previous prime minister and Rio's last chief executive.
While the government has not paid up front for any of the construction or operating costs of the mine, figures that emerged late last year projecting that it might never receive any dividends from its 34% ownership of one of the world's biggest copper deposits engulfed the project in fresh controversy.
In a proposal submitted to Prime Minister Oyun-Erdene Luvsannamsrai on Monday, Rio offered to waive interest on the loan extended to finance the government's capital share, an official told Nikkei Asia. Under the current arrangement, the rate is fixed at Libor plus 6.5%, or around 6.74% currently.
The company also offered to pay the government $350 million over the next three years to assist Mongolia with its pandemic difficulties, government officials said.
"We take the cash payment offer as a prepaid dividend and there will be much more further talks," Solongoo Bayarsaikhan, deputy cabinet secretariat chief and a leading negotiator in the talks with Rio, said at a news conference Tuesday.
"Negotiations may take 3 to 4 years," said Nyambaatar Khishgee, minister of justice and internal affairs, noting the government would hire consultants to carefully review terms, given perceived mistakes made in earlier rounds of talks.
Rio on Wednesday said it would decline to comment on "speculation" about its offer.
Under the current financing arrangement, Mongolia will only receive dividends once it has paid off the interest and principal on the loan from Rio, now about $2.2 billion. Until late 2020, the authorities had expected to start collect dividends in 2032 but a two-year delay in construction and $1.5 billion increase in the project's budget darkened the outlook.
Copper production from the underground section of the mine was originally scheduled to begin last year, and preparatory work will continue while negotiations proceed. Solongoo said the government will also continue to pursue an international arbitration claim against Rio for taxes found to be unpaid after auditing the mine's records.
Rio has said the mine project pays around $300 million in taxes annually to the government, including royalties. The company has collected $1.3 billion in management fees for operating the original open-pit section of the mine since 2013.
Earlier this month, a special board committee of the joint venture that owns the mine concluded that project management problems were key to the delays and cost overruns with the underground expansion.
Former Mongolian Prime Minister Saikhanbileg Chimed, who signed a 2015 deal with Rio, is under investigation over his handling of those talks but is in exile. Bayar Sanj, a predecessor, was sentenced in 2020 to five years' imprisonment for abuse of power in another case related to the mine.


Published Date:2021-09-01