1 ZANDANSHATAR GOMBOJAV APPOINTED AS PRIME MINISTER OF MONGOLIA WWW.MONTSAME.MN PUBLISHED:2025/06/13      2 WHAT MONGOLIA’S NEW PRIME MINISTER MEANS FOR ITS DEMOCRACY WWW.TIME.COM PUBLISHED:2025/06/13      3 ULAANBAATAR DIALOGUE SHOWS MONGOLIA’S FOREIGN POLICY CONTINUITY AMID POLITICAL UNREST WWW.THEDIPLOMAT.COM PUBLISHED:2025/06/13      4 THE UNITED NATIONS CHILDREN’S FUND (UNICEF) IN MONGOLIA, THE NATIONAL FOUNDATION FOR SUPPORTING THE BILLION TREES MOVEMENT, AND CREDITECH STM NBFI LLC HAVE JOINTLY LAUNCHED THE “ONE CHILD – ONE TREE” INITIATIVE WWW.BILLIONTREE.MN PUBLISHED:2025/06/13      5 NEW MONGOLIAN PM TAKES OFFICE AFTER CORRUPTION PROTESTS WWW.AFP.MN PUBLISHED:2025/06/13      6 GOLD, MINED BY ARTISANAL AND SMALL-SCALE MINERS OF MONGOLIA TO BE SUPPLIED TO INTERNATIONAL JEWELRY COMPANIES WWW.MONTSAME.MN PUBLISHED:2025/06/13      7 AUSTRIA PUBLISHES SYNTHESIZED TEXTS OF TAX TREATIES WITH ICELAND, KAZAKHSTAN AND MONGOLIA AS IMPACTED BY BEPS MLI WWW.ORBITAX.COM  PUBLISHED:2025/06/13      8 THE UNITED STATES AND MONGOLIA OPEN THE CENTER OF EXCELLENCE FOR ENGLISH LANGUAGE TEACHING IN ULAANBAATAR WWW.MN.USEMBASSY.GOV  PUBLISHED:2025/06/12      9 MONGOLIA'S 'DRAGON PRINCE' DINOSAUR WAS FORERUNNER OF T. REX WWW.REUTERS.COM PUBLISHED:2025/06/12      10 MONGOLIA’S PIVOT TO CENTRAL ASIA AND THE CAUCASUS: STRATEGIC REALIGNMENTS AND REGIONAL IMPLICATIONS WWW.CACIANALYST.ORG  PUBLISHED:2025/06/12      БӨӨРӨЛЖҮҮТИЙН ЦАХИЛГААН СТАНЦЫН II БЛОКИЙГ 12 ДУГААР САРД АШИГЛАЛТАД ОРУУЛНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/15     ОРОН СУУЦНЫ ҮНЭ 14.3 ХУВИАР ӨСЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/15     МОНГОЛ УЛСЫН 34 ДЭХ ЕРӨНХИЙ САЙДААР Г.ЗАНДАНШАТАРЫГ ТОМИЛЛОО WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/13     SXCOAL: МОНГОЛЫН НҮҮРСНИЙ ЭКСПОРТ ЗАХ ЗЭЭЛИЙН ХҮНДРЭЛИЙН СҮҮДЭРТ ХУМИГДАЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/06/13     МОНГОЛ БАНК: ТЭТГЭВРИЙН ЗЭЭЛД ТАВИХ ӨР ОРЛОГЫН ХАРЬЦААГ 50:50 БОЛГОЛОО WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/13     МОНГОЛ ДАХЬ НҮБ-ЫН ХҮҮХДИЙН САН, ТЭРБУМ МОД ҮНДЭСНИЙ ХӨДӨЛГӨӨНИЙГ ДЭМЖИХ САН, КРЕДИТЕХ СТМ ББСБ ХХК “ХҮҮХЭД БҮРД – НЭГ МОД” САНААЧИЛГЫГ ХАМТРАН ХЭРЭГЖҮҮЛНЭ WWW.BILLIONTREE.MN НИЙТЭЛСЭН:2025/06/13     ЕРӨНХИЙЛӨГЧИЙН ТАМГЫН ГАЗРЫН ДАРГААР А.ҮЙЛСТӨГӨЛДӨР АЖИЛЛАНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/06/13     34 ДЭХ ЕРӨНХИЙ САЙД Г.ЗАНДАНШАТАР ХЭРХЭН АЖИЛЛАНА ГЭЖ АМЛАВ? WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/13     “АНГЛИ ХЭЛНИЙ МЭРГЭШЛИЙН ТӨВ”-ИЙГ МУИС-Д НЭЭЛЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/13     Г.ЗАНДАНШАТАР БАЯЛГИЙН САНГИЙН БОДЛОГЫГ ҮРГЭЛЖЛҮҮЛНЭ ГЭЖ АМЛАЛАА WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/12    

EPC-1 project of Oil Refinery progressing at 63 percent www.montsame.mn

Construction work for oil refinery consists of four engineering-procurement – construction (EPC-1,2,3 and 4) phase projects, and India’s state-owned company, ‘Engineers India Limited’ is monitoring the performance of the EPC-1, which is a complex project of industrial non-technological facilities, construction site infrastructure, and road and water supply system, in accordance with international norms and standards, reported the Ministry of Mining and Heavy Industry.
‘JMC Projects’ LLC of India as a general contractor of the project and engineers and technical experts of 21 subcontracting companies of Mongolia or a total of 641 people with 250 pieces of equipment are working according to a plan to hand over the project on November 29, 2022.
The EPC-1 project has four main stages: preparatory work, blueprint development, procurement, and construction, and the overall project is progressing at 63 percent. In detail, the construction of water storage tank is running at 85 percent, first aid and hospital building -80 percent, office and training center – 45 percent, cafeteria -84 percent, laboratory -85 percent, warehouse -45 percent, firefighting unit’s facility – 52 percent, repair facility -35 percent, drainage pipe-30 percent, floodwater harvesting area -82.5 percent, electric power transmission line-90 percent as well as others.
A tender for the selection of the general contractor for the EPC-2 unpatented technology facility works was announced on June 6, 2022 on an expedited basis and proposals will be received on August 16, 2022.
Moreover, a tender for the selection of the general contractor for the EPC-3 –construction of power plant of the Oil Refinery was announced on May 04, 2022 and proposals were received on July 04, 2022.
In addition, license holders for patented technology works of EPC-4 have been selected. Relevant contracts have been established with leading corporations of the petrochemical industry, such as KT - Kinetics Technology, UOP Honeywell, and Axens Solutions.