1 CHINA’S MONGOLIAN COAL IMPORTS UP 20% IN OCT, RUSSIAN IMPORTS SLIP 18% WWW.BRECORDER.COM  PUBLISHED:2025/11/21      2 S.KOREA-MONGOLIA JOINT COMMITTEE MEETING REAFFIRMS MINERAL COOPERATION WWW.KOREAPOST.COM PUBLISHED:2025/11/21      3 TEAM MONGOLIA FROM PHYSICAL ASIA: WHERE ARE THEY NOW? WWW.MOVIEDELIC.COM PUBLISHED:2025/11/21      4 N.UCHRAL: I’LL BE LENIENT WITH THE RIGHT, STRICT WITH THE WRONG WWW.GOGO.MN PUBLISHED:2025/11/20      5 MONGOLIAN BANKING SECTOR'S NET FOREIGN ASSETS DECLINE 16.1 PCT IN OCTOBER WWW.XINHUANET.COM PUBLISHED:2025/11/20      6 ON THE TALKS OF SECRETARY-GENERAL WITH THE MINISTER OF FOREIGN AFFAIRS OF MONGOLIA WWW.ENG.SECTSCO.ORG PUBLISHED:2025/11/20      7 MONGOLIA UNIFIES TO COMBAT NEW THREATS TO SNOW LEOPARDS WWW.SNOWLEOPARD.ORG PUBLISHED:2025/11/20      8 AMERICAN-CANADIAN BILLIONAIRE OPENS $2-BILLION PLATINUM MINE IN SOUTH AFRICA WWW.AFRICA.BUSINESSINSIDER.COM PUBLISHED:2025/11/20      9 EDUCATION INFRASTRUCTURE: 12 SCHOOLS, 24 KINDERGARTENS SET FOR 2025 LAUNCH WWW.MONTSAME.MN PUBLISHED:2025/11/20      10 MONGOLIA JAPAN HOSPITAL INTRODUCES SELECTIVE LASER TRABECULOPLASTY SYSTEM WWW.AKIPRESS.COM PUBLISHED:2025/11/20      Н.УЧРАЛ: ХУУЛЬ ТОТООХ ДЭЭД БАЙГУУЛЛАГААС ХУЛГАЙН СЭЖИГТНҮҮД БИШ ХУУЛЬ ТӨРЖ БАЙХ ЁСТОЙ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/11/21     ТЭРБУМ МОД САНГИЙН ТӨСЛИЙН СОНГОН ШАЛГАРУУЛАЛТ ЗАРЛАГДЛАА WWW.BILLIONTREE.MN НИЙТЭЛСЭН:2025/11/20     ОЙЖУУЛАЛТАД ХАМГИЙН ИХ ХӨРӨНГӨ ОРУУЛАЛТ ХИЙЖ БАЙГАА ХУВИЙН ХЭВШЛИЙН САНГААР ТЭРБУМ МОД САНГ НЭРЛЭЛЭЭ WWW.BILLIONTREE.MN НИЙТЭЛСЭН:2025/11/20     МОНГОЛД ГАДНЫ БАНК НЭЭХ НЬ ХЭРЭГЛЭГЧДЭД ӨГӨӨЖТЭЙ Ч ДОТООДЫН БАНК САНХҮҮГИЙН САЛБАРТ ЭРСДЭЛТЭЙ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/11/20     ӨНГӨРСӨН САРД 11 УЛСЫН 240 ИРГЭНИЙГ АЛБАДАН ГАРГАЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/11/20     Х.НЯМБААТАР: ГАНДАН ОРЧМЫГ НОГООН БАЙГУУЛАМЖ БҮХИЙ ЖИШИГ ГУДАМЖ БОЛГОН ТОХИЖУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/11/20     ОЮУ ТОЛГОЙ ТӨСЛИЙН ХУВЬ НИЙЛҮҮЛЭГЧДИЙН ЗЭЭЛИЙН ХҮҮГ БУУРУУЛАХ ХЭЛЭЛЦЭЭ ҮРГЭЛЖИЛЖ БАЙНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/11/20     УИХ-ЫН ДАРГААР Н.УЧРАЛ СОНГОГДЛОО WWW.ITOIM.MN НИЙТЭЛСЭН:2025/11/20     "ЧИНГИС ХААН" ОДОН ХҮРТЭЖ БУЙ С.НАРАНГЭРЭЛ ГЭЖ ХЭН БЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/11/20     ОХУ-ЫН БАНК САЛБАРАА МОНГОЛД НЭЭХ ҮҮ? WWW.NEWS.MN НИЙТЭЛСЭН:2025/11/20    

Speaker of Lok Sabha Visits “Mongol Refinery” LLC www.montsame.mn

The Speaker of the Lok Sabha, Lower House of the Parliament of India Om Birla, who is on an Official Visit to Mongolia visited the state-owned company “Mongol Refinery” LLC on July 7.
Dr. D. Altantsetseg, the Executive Director of the “Mongol Refinery” LLC, Mongolia's Consulting Engineer expressed gratitude to the government and parliament of India for all-round support to the establishment of the first oil refinery, which has specifically important to the economic development and energy independence of Mongolia and informed on the progress of the project.
The Government of Mongolia is implementing the Project to establish a grass root Oil Refinery Plant based on domestic crude in Dornogobi aimag, located in Southeastern part of the country, within the framework of the soft loan extended by the Government of India to ensure energy independency and expand the industry diversification.
Upon approving the Detailed Feasibility Study and selecting "Engineers India Limited" as Project Management Consultant in 2019, the design and engineering works have completed, and from this year on, the mechanical erection of the main technological facilities has started at full capacity.
Out of four main EPC packages planned for the project, the first package, which comprises of non-technological facilities, such as civil buildings (office-training center, first aid center, fire station, warehouse, laboratory, workshop, canteen, 30 thousand cubic meter underground water storage tank) is at the final stage, noted Executive Director Dr. D. Altantsetseg.
EPC 02 package consists of initial processing units, such as Atmospheric and Vacuum Distillation Units, Saturated Gas Plant, and utilities, including tank farms, product dispatching facilities, and the different types of auxiliary and supporting units, whereas a 35 MW Thermal Power Plant would be built as part of the EPC 03 package. The site works of these packages have commenced, informed the project implementers.