1 ZANDANSHATAR GOMBOJAV APPOINTED AS PRIME MINISTER OF MONGOLIA WWW.MONTSAME.MN PUBLISHED:2025/06/13      2 WHAT MONGOLIA’S NEW PRIME MINISTER MEANS FOR ITS DEMOCRACY WWW.TIME.COM PUBLISHED:2025/06/13      3 ULAANBAATAR DIALOGUE SHOWS MONGOLIA’S FOREIGN POLICY CONTINUITY AMID POLITICAL UNREST WWW.THEDIPLOMAT.COM PUBLISHED:2025/06/13      4 THE UNITED NATIONS CHILDREN’S FUND (UNICEF) IN MONGOLIA, THE NATIONAL FOUNDATION FOR SUPPORTING THE BILLION TREES MOVEMENT, AND CREDITECH STM NBFI LLC HAVE JOINTLY LAUNCHED THE “ONE CHILD – ONE TREE” INITIATIVE WWW.BILLIONTREE.MN PUBLISHED:2025/06/13      5 NEW MONGOLIAN PM TAKES OFFICE AFTER CORRUPTION PROTESTS WWW.AFP.MN PUBLISHED:2025/06/13      6 GOLD, MINED BY ARTISANAL AND SMALL-SCALE MINERS OF MONGOLIA TO BE SUPPLIED TO INTERNATIONAL JEWELRY COMPANIES WWW.MONTSAME.MN PUBLISHED:2025/06/13      7 AUSTRIA PUBLISHES SYNTHESIZED TEXTS OF TAX TREATIES WITH ICELAND, KAZAKHSTAN AND MONGOLIA AS IMPACTED BY BEPS MLI WWW.ORBITAX.COM  PUBLISHED:2025/06/13      8 THE UNITED STATES AND MONGOLIA OPEN THE CENTER OF EXCELLENCE FOR ENGLISH LANGUAGE TEACHING IN ULAANBAATAR WWW.MN.USEMBASSY.GOV  PUBLISHED:2025/06/12      9 MONGOLIA'S 'DRAGON PRINCE' DINOSAUR WAS FORERUNNER OF T. REX WWW.REUTERS.COM PUBLISHED:2025/06/12      10 MONGOLIA’S PIVOT TO CENTRAL ASIA AND THE CAUCASUS: STRATEGIC REALIGNMENTS AND REGIONAL IMPLICATIONS WWW.CACIANALYST.ORG  PUBLISHED:2025/06/12      БӨӨРӨЛЖҮҮТИЙН ЦАХИЛГААН СТАНЦЫН II БЛОКИЙГ 12 ДУГААР САРД АШИГЛАЛТАД ОРУУЛНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/15     ОРОН СУУЦНЫ ҮНЭ 14.3 ХУВИАР ӨСЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/15     МОНГОЛ УЛСЫН 34 ДЭХ ЕРӨНХИЙ САЙДААР Г.ЗАНДАНШАТАРЫГ ТОМИЛЛОО WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/13     SXCOAL: МОНГОЛЫН НҮҮРСНИЙ ЭКСПОРТ ЗАХ ЗЭЭЛИЙН ХҮНДРЭЛИЙН СҮҮДЭРТ ХУМИГДАЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/06/13     МОНГОЛ БАНК: ТЭТГЭВРИЙН ЗЭЭЛД ТАВИХ ӨР ОРЛОГЫН ХАРЬЦААГ 50:50 БОЛГОЛОО WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/13     МОНГОЛ ДАХЬ НҮБ-ЫН ХҮҮХДИЙН САН, ТЭРБУМ МОД ҮНДЭСНИЙ ХӨДӨЛГӨӨНИЙГ ДЭМЖИХ САН, КРЕДИТЕХ СТМ ББСБ ХХК “ХҮҮХЭД БҮРД – НЭГ МОД” САНААЧИЛГЫГ ХАМТРАН ХЭРЭГЖҮҮЛНЭ WWW.BILLIONTREE.MN НИЙТЭЛСЭН:2025/06/13     ЕРӨНХИЙЛӨГЧИЙН ТАМГЫН ГАЗРЫН ДАРГААР А.ҮЙЛСТӨГӨЛДӨР АЖИЛЛАНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/06/13     34 ДЭХ ЕРӨНХИЙ САЙД Г.ЗАНДАНШАТАР ХЭРХЭН АЖИЛЛАНА ГЭЖ АМЛАВ? WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/13     “АНГЛИ ХЭЛНИЙ МЭРГЭШЛИЙН ТӨВ”-ИЙГ МУИС-Д НЭЭЛЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/06/13     Г.ЗАНДАНШАТАР БАЯЛГИЙН САНГИЙН БОДЛОГЫГ ҮРГЭЛЖЛҮҮЛНЭ ГЭЖ АМЛАЛАА WWW.EGUUR.MN НИЙТЭЛСЭН:2025/06/12    

L. Munkhbaatar: We Will Fully Support Commissioning of Oil Refinery on Time www.montsame.mn

Today the Vice-Chairman of the State Great Khural of Mongolia L. Munkhbaatar received the delegation headed by the Ambassador Extraordinary and Plenipotentiary of the Republic of India to Mongolia M.P. Singh.
At the beginning of the meeting, the Vice-Chairman of the State Great Khural L. Munkhbaatar noted that major projects and programs significantly contribute to the enrichment of the Strategic Partnership between Mongolia and India with new content, and development is taking place intensively, and congratulated the Indian partners on the occasion of the 76th Anniversary of the Independence of the Republic of India. At the meeting, the parties discussed the progress of the Oil Refinery Construction Project and exchanged opinions.
Considering the time to spend on the engineering work of each oil refinery facility, the construction work is divided into 4 parts: ЕРС-01, ЕРС-02, ЕРС-03, and ЕРС-04 (ЕРС: Engineering-Purchase-Construction). ЕРС-01 package work or construction of non-technological buildings started in 2021. They are working to hand it over within this year. The contractor for EPC-02 and 03 package works and construction of crude oil pipeline was selected in 2022 and the contract was signed. Currently, the design work is in the final stage, and the construction work at the factory site officially started in April of this year. H.E. Ambassador M.P. Singh presented the announcement of the tender for the selection of the EPC-04 package construction contractor. He noted that the Minister of Finance of Mongolia and Exim Bank of the Republic of India signed a new loan agreement on the ЕРС-01, ЕРС-02, ЕРС-03 projects for the construction of the oil refinery in Mongolia, and postponed the loan repayment period until 2030.
CEO of Engineers India Limited Vartika Shukla said that due to the pandemic and international geopolitical situation, increase of the price of materials, machinery and equipment on the world market affects the total investment expenses of the project. As it is necessary to solve the problem of additional funding for the implementation of the EPC-04 set of works, she asked the Parliament to support their endeavors.
With the completion of the oil refinery, Mongolia will get rid of dependence on fuel imports, and a new branch of the petrochemical industry will be created in the country reducing foreign trade deficit. The Vice-Chairman of the State Great Khural of Mongolia L. Munkhbaatar underscored that the Parliament will fully support and pay attention to the creation of a favorable legal environment and the coordination of relevant institutions in order to successfully implement the project, a symbol of cooperation between the two countries.
Executive Director of "Mongolian Oil Refinery" LLC D. Altantsetseg, Project Management Consultant for Oil Refinery, Chairman and Managing Director of Engineers India Limited Vartika Shukla, General Manager of EXIM Bank of India Nirmit Ved, and other officials took part in the meeting.