1 TRUMP’S SON WITH KAZAKH TUNGSTEN TIES LOST IN MONGOLIAN MOUNTAINS WWW.KZ.KURSIV.MEDIA PUBLISHED:2026/09/10      2 MONGOLIA TO HOLD PARLIAMENTARY HEARING ON EPSTEIN FILES IN OCTOBER WWW.AZERNEWS.AZ PUBLISHED:2026/09/10      3 MONGOLIA'S FOREIGN TRADE TURNOVER SURGES NEARLY 37 PCT IN FIRST 8 MONTHS WWW.XINHUANET.COM PUBLISHED:2026/09/10      4 MONGOLIA SIGNS MOU WITH BLACKROCK FMA WWW.MONTSAME.MN PUBLISHED:2026/09/10      5 MONGOLIA, UAE SIGN ENERGY COOPERATION MOU WWW.MONTSAME.MN PUBLISHED:2026/09/10      6 SPEAKERS OF MONGOLIA, VIETNAM HOLD OFFICIAL TALKS WWW.MONTSAME.MN PUBLISHED:2026/09/10      7 MONGOLIA AGREES TO PURCHASE 10,000 TONS OF GASOLINE AND 4,000 TONS OF JET FUEL FROM CHINA IN SEPTEMBER WWW.GOGO.MN PUBLISHED:2026/09/10      8 ADB SUPPORTS MONGOLIA'S FIRST GREEN-CERTIFIED RESIDENTIAL COMPLEX BUILT BY THE PRIVATE SECTOR WWW.ADB.ORG PUBLISHED:2026/09/09      9 MONGOLIA FINISHES FOURTH WITH 26 MEDALS AT WORLD NOMAD GAMES WWW.ASIANEWS.NETWORK PUBLISHED:2026/09/09      10 NEW FLIGHT ROUTES EXPLORED WITH HOKKAIDO AIRPORTS WWW.UBPOST.MN PUBLISHED:2026/09/09      ШАТАХУУНЫ НИЙЛҮҮЛЭЛТЭЭ УРТ ХУГАЦААНД ТОГТВОРЖУУЛЖ, ГАЗРЫН ТОС, НҮҮРС-ХИМИЙН ХАМТЫН АЖИЛЛАГААГ ӨРГӨЖҮҮЛНЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/10     ГОЛОМТ БАНК ХАРИЛЦАГЧДЫНХАА ХУДАЛДАА, ТӨЛБӨР ТООЦООГ ДЭМЖИХЭЭР BANK OF CHINA-ТАЙ СТРАТЕГИЙН ХАМТЫН АЖИЛЛАГААГ ЭХЛҮҮЛЛЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/10     АНЭУ-ТАЙ ЭРЧИМ ХҮЧНИЙ САЛБАРТ ХАМТРАН АЖИЛЛАНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/10     МАХ, БЕНЗИНИЙ ҮНИЙН НӨЛӨӨГӨӨР ИНФЛЯЦ 12.5 ХУВЬД ХҮРЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/10     МОНГОЛД ИРЖ БУЙ РИО ТИНТО ГРУППИЙН CEO САЙМОН ТРОТТ ГЭЖ ХЭН БЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/10     Ц.БАТБААТАР: ХАТУУ ЗОХИЦУУЛАЛТТАЙ 38 УЛСААС ОРЖ ИРЖ БАЙГАА ЭМҮҮДИЙГ ХӨНГӨЛӨЛТТЭЙ ЭМИЙН ЖАГСААЛТАД ХАМРУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/10     Н.УЧРАЛ: МИНИЙ ГЭР БҮЛ, АЖИЛ МЭРГЭЖЛИЙН НЭР ХҮНДЭД ХАЛДЛАА WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/10     СЭЛБЭ УХААЛАГ ХОТОД УНДНЫ УСНЫ ЗЭС ХООЛОЙ ШУГАМ УГСАРЧ БАЙНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/09     НАЙМДУГААР САРД ХҮНСНИЙ БҮЛГИЙН БҮТЭЭГДЭХҮҮНИЙ ҮНЭ 21.5 ХУВЬ НЭМЭГДЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/09     ЭРЧИМ ХҮЧНИЙ ҮНЭ НЭМЭХГҮЙН ТУЛД ТӨСӨВТ 200 ТЭРБУМ ТӨГРӨГИЙН ТАТААС ТУСГАЖЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/09    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Prime Minister Tasks to Start PC-04 Package Work of Oil Refinery www.montsame.mn

The Prime Minister of Mongolia Oyun-Erdene Luvsannamsrai tasked to start the EPC-04 Package Work of the Oil Refinery and commission the plant in 2027. The Government of Mongolia pursues the policy of intensifying the construction of the Oil Refinery. The Premier instructed to make up for the 13 months of work lost during the Covid-19, start the EPC-04 Package Work of the Oil Refinery, and intensify the work to put the plant into operation in 2027.
In 2016, the General Loan Agreement of USD 1 Billion was signed between the Government of Mongolia and the Export-Import (EXIM) Bank of the Republic of India. According to the Feasibility Study released at that time, it was concluded that the "Oil Refinery Construction Project" requires funding equivalent to USD 1 billion 236 million. Therefore, a loan agreement was signed in October 2019 to settle additional funding of USD 236 million from the Government of Mongolia.
The principal repayment of the loan was scheduled to be paid annually in the amount of USD 64.5 million starting from February 2023. However, as of February 2023, USD 112 million was taken out of the USD 1 billion loan. Therefore, a proposal to change the repayment schedule of the loan, which had been used to a minor extent, was made to the Indian side, sub-loan agreements have been signed on August 17, 2023, and the repayment has been postponed. The sub-loan agreement reduces the principal repayment of the loan from USD 64.5 million to USD 13.1 million. In addition, the period of exemption from the principal payment of 789.0 million US dollars, which is the financing of EPC-02 and EPC-03 Package Works, has been extended for another seven years.
With this agreement, the implementation of the four Package Works of "Oil Refinery Construction Project" that were regulated by one contract, which were dependent on each other and delayed, can be separated, thus enabling to intensify implementation of the Package Works.
Currently, EPC-04 Package Works, namely the construction and equipment works of the main plant, are pending. "Mongolian Oil Refinery" has announced that the budgeted cost of EPC-04 Package of USD 236 million will be increased by USD 422.0 million during the bidding process, making it a total of USD 648 million.
The Government of Mongolia confirmed the loan agreement for the initial cost of USD 236 million, and submitted a request for financing to the Export-Import Bank of the Republic of India in order to quickly start the work on the three facilities that will require the longest period of work in the EPC-04 Package: hydrocracking, sulfur separation facility, and hydrogen plant.


Published Date:2023-09-15