1 MONGOLIA’S CLIMATE TRANSITION: EMPOWERING CITIZENS FOR A JUST AND SUSTAINABLE FUTURE WWW.DEVDISCOURSE.COM PUBLISHED:2025/07/31      2 MONGOLIA RENEWABLE ENERGY TARGET: POWERFUL 2030 VISION WWW.PVKNOWHOW.COM  PUBLISHED:2025/07/31      3 MINISTER FOR FOREIGN AFFAIRS OF MONGOLIA BATMUNKH BATTSETSEG TO VISIT FINLAND WWW.VALTIONEUVOSTO.FI  PUBLISHED:2025/07/31      4 MIAT’S NEW “IRVES” AIRCRAFT ARRIVES IN MONGOLIA AFTER COVERING 12,265 KM WWW.MONTSAME.MN PUBLISHED:2025/07/31      5 5TH CHINA-MONGOLIA EXPO TO BOOST REGIONAL COOPERATION WWW.XINHUANET.COM PUBLISHED:2025/07/31      6 FIVE AIMAGS CLASSIFIED AS HIGH-RISK FOR DROUGHT WWW.MONTSAME.MN PUBLISHED:2025/07/31      7 SEACEN FORUM FOCUSES ON FUTURE-READY CENTRAL BANK WORKFORCE WWW.UBPOST.MN PUBLISHED:2025/07/31      8 39 MONGOLIAN STUDENTS TO STUDY IN GERMANY UNDER “PRESIDENT'S SCHOLAR - 2100” PROGRAM WWW.MONTSAME.MN PUBLISHED:2025/07/30      9 MONGOLIAN FLAG CARRIER TO START NON-STOP FLIGHTS BETWEEN SINGAPORE AND ULAANBAATAR FROM NOV 4 WWW.STRAITSTIMES.COM PUBLISHED:2025/07/30      10 WHEN CHINA SNEEZES, MONGOLIA CATCHES A COLD WWW.INTELLINEWS.COM PUBLISHED:2025/07/30      ЭРДЭМТДИЙН ЗӨВЛӨЛИЙН ШИЙДВЭРЭЭР ИРЭХ ӨВӨЛ ХАГАС КОКС БУЮУ ХӨХ НҮҮРСЭЭР ХИЙСЭН ШАХМАЛ ТҮЛШ ХЭРЭГЛЭНЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/07/31     ЗАСГИЙН ГАЗАР: УЛААНБААТАР ХОТЫН ДУЛААН ХАНГАМЖИД СХЕМИЙН ӨӨРЧЛӨЛТ ХИЙНЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/07/31     "АЛТ 3" АЯН ГАЦААНД ОРОВ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/07/31     ДЦСV-ЫГ БАРИХ КОМПАНИ ИРЭХ САРЫН 6-НД ТОДОРНО WWW.NEWS.MN НИЙТЭЛСЭН:2025/07/31     МИАТ КОМПАНИ КАНАД УЛСЫН BOMBARDIER ҮЙЛДВЭРИЙН CRJ-700 ШИНЭ АГААРЫН ХӨЛӨГ ОНГОЦОО ХҮЛЭЭН АВЛАА WWW.EGUUR.MN НИЙТЭЛСЭН:2025/07/31     BNE INTELLINEWS: БНХАУ НАЙТААХ ҮЕД МОНГОЛ ХАНИАД ХҮРДЭГ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/07/31     "БӨӨРӨЛЖҮҮТИЙН ЦС"-ЫН II БЛОКИЙГ 12-Р САРД АШИГЛАЛТАД ОРУУЛНА WWW.EGUUR.MN НИЙТЭЛСЭН:2025/07/31     ГАНГИЙН ЭРСДЛИЙН ҮНЭЛГЭЭГЭЭР ТАВАН АЙМАГ ЭРСДЭЛ ИХТЭЙ ГАРЧЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/07/30     МОНГОЛЫН КОКСЖИХ НҮҮРСНИЙ ҮНЭ ХЯТАДЫН БООМТУУДАД ДАХИН ӨСЛӨӨ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/07/30     НИЙСЛЭЛД ХЭРЭГЖҮҮЛЖ БУЙ МЕГА ТӨСЛҮҮДЭД ХАМТРАН АЖИЛЛАХААР САНАЛ СОЛИЛЦЛОО WWW.ITOIM.MN НИЙТЭЛСЭН:2025/07/30    

Final Stage Contract of Oil Refinery Plant Signed www.montsame.mn

The construction of the first Oil Refinery Plant of Mongolia with a capacity to process 1.5 million tons of crude oil per year is progressing in Altanshireet soum of Dornogobi aimag. The project is financed by a USD 1.2 billion soft loan from the Government of India.
On September 29, 2023, Dr. D. Altantsetseg, Executive Director of the state-owned company “Mongol Refinery” LLC, and P. Rajesh Reddy, President of the Hydrocarbons Division of Megha Engineering & Infrastructure Limited (MEIL), signed the Contract for the EPC-04 package, which is the last of the four EPC packages for the Oil Refinery Plant. The Oil Refinery Plant will have seven deep processing and conversion technology facilities, each requiring specific licenses from the patent owners called licensors. The EPC-04 package consists of the construction of the licensed technology facilities.
MEIL Managing Director PV Krishna Reddy, officials, dignitaries, and representatives from the two countries were present at the Contract Signing Ceremony.
Executive Director D. Altantsetseg emphasized, " The winners of the tenders will be responsible for the general plan, blueprint, procurement, and the construction. In addition to simple and vacuum distillation facilities, deep processing technology means dealing with how to break down the heavy residue of during the distillation and what technology to use to affect the atomic and molecular level in order to increase the yield of well refined oil. To put it another way, it is vital to maximize the production of gasoline, diesel, and jet fuel, which are the main products of the plant."
“Mongol Refinery” LLC conducted competitive bidding process among various multinational oil and gas companies to obtain the licenses for the technological units. After two years of intensive negotiation, they reached agreement and signed Contracts with companies such as Honeywell UoP, Axens, Shell, and Kinetics Technology in 2022. Since signing of the Contracts, companies completed the Basic Design and Engineering Packages for their licensed units and will also provide its proprietary equipment and other supplies as well as training and mandatory services.
"Megha Engineering and Infrastructures Limited" was also selected as the main Contractor for EPC 02 and 03 packages and the site works are ongoing.
MEIL Managing Director Krishna Reddy said, "MEIL's new venture marks its third foray into the region. It involves the construction of the country's first greenfield Mongol Oil Refinery project, a significant undertaking. Within this refinery, MEIL is overseeing the construction of EPC-2, which encompasses open art units, utilities, offsites, and plant buildings valued at USD 598.90 million. Additionally, MEIL is constructing captive power plants for the EPC-3 phase, valued at USD 189.72 million, and USD 648 million for the new EPC-4 project. The company is using cutting-edge technology in the construction of all the projects."
 
 
 


Published Date:2023-10-04