1 CHINA’S MONGOLIAN COAL IMPORTS UP 20% IN OCT, RUSSIAN IMPORTS SLIP 18% WWW.BRECORDER.COM  PUBLISHED:2025/11/21      2 S.KOREA-MONGOLIA JOINT COMMITTEE MEETING REAFFIRMS MINERAL COOPERATION WWW.KOREAPOST.COM PUBLISHED:2025/11/21      3 TEAM MONGOLIA FROM PHYSICAL ASIA: WHERE ARE THEY NOW? WWW.MOVIEDELIC.COM PUBLISHED:2025/11/21      4 N.UCHRAL: I’LL BE LENIENT WITH THE RIGHT, STRICT WITH THE WRONG WWW.GOGO.MN PUBLISHED:2025/11/20      5 MONGOLIAN BANKING SECTOR'S NET FOREIGN ASSETS DECLINE 16.1 PCT IN OCTOBER WWW.XINHUANET.COM PUBLISHED:2025/11/20      6 ON THE TALKS OF SECRETARY-GENERAL WITH THE MINISTER OF FOREIGN AFFAIRS OF MONGOLIA WWW.ENG.SECTSCO.ORG PUBLISHED:2025/11/20      7 MONGOLIA UNIFIES TO COMBAT NEW THREATS TO SNOW LEOPARDS WWW.SNOWLEOPARD.ORG PUBLISHED:2025/11/20      8 AMERICAN-CANADIAN BILLIONAIRE OPENS $2-BILLION PLATINUM MINE IN SOUTH AFRICA WWW.AFRICA.BUSINESSINSIDER.COM PUBLISHED:2025/11/20      9 EDUCATION INFRASTRUCTURE: 12 SCHOOLS, 24 KINDERGARTENS SET FOR 2025 LAUNCH WWW.MONTSAME.MN PUBLISHED:2025/11/20      10 MONGOLIA JAPAN HOSPITAL INTRODUCES SELECTIVE LASER TRABECULOPLASTY SYSTEM WWW.AKIPRESS.COM PUBLISHED:2025/11/20      Н.УЧРАЛ: ХУУЛЬ ТОТООХ ДЭЭД БАЙГУУЛЛАГААС ХУЛГАЙН СЭЖИГТНҮҮД БИШ ХУУЛЬ ТӨРЖ БАЙХ ЁСТОЙ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/11/21     ТЭРБУМ МОД САНГИЙН ТӨСЛИЙН СОНГОН ШАЛГАРУУЛАЛТ ЗАРЛАГДЛАА WWW.BILLIONTREE.MN НИЙТЭЛСЭН:2025/11/20     ОЙЖУУЛАЛТАД ХАМГИЙН ИХ ХӨРӨНГӨ ОРУУЛАЛТ ХИЙЖ БАЙГАА ХУВИЙН ХЭВШЛИЙН САНГААР ТЭРБУМ МОД САНГ НЭРЛЭЛЭЭ WWW.BILLIONTREE.MN НИЙТЭЛСЭН:2025/11/20     МОНГОЛД ГАДНЫ БАНК НЭЭХ НЬ ХЭРЭГЛЭГЧДЭД ӨГӨӨЖТЭЙ Ч ДОТООДЫН БАНК САНХҮҮГИЙН САЛБАРТ ЭРСДЭЛТЭЙ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/11/20     ӨНГӨРСӨН САРД 11 УЛСЫН 240 ИРГЭНИЙГ АЛБАДАН ГАРГАЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/11/20     Х.НЯМБААТАР: ГАНДАН ОРЧМЫГ НОГООН БАЙГУУЛАМЖ БҮХИЙ ЖИШИГ ГУДАМЖ БОЛГОН ТОХИЖУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/11/20     ОЮУ ТОЛГОЙ ТӨСЛИЙН ХУВЬ НИЙЛҮҮЛЭГЧДИЙН ЗЭЭЛИЙН ХҮҮГ БУУРУУЛАХ ХЭЛЭЛЦЭЭ ҮРГЭЛЖИЛЖ БАЙНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/11/20     УИХ-ЫН ДАРГААР Н.УЧРАЛ СОНГОГДЛОО WWW.ITOIM.MN НИЙТЭЛСЭН:2025/11/20     "ЧИНГИС ХААН" ОДОН ХҮРТЭЖ БУЙ С.НАРАНГЭРЭЛ ГЭЖ ХЭН БЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/11/20     ОХУ-ЫН БАНК САЛБАРАА МОНГОЛД НЭЭХ ҮҮ? WWW.NEWS.MN НИЙТЭЛСЭН:2025/11/20    

Baganuur 50 MW Battery Storage Power Station Supplies Energy to Central System www.montsame.mn

Baganuur 50 MW Battery Storage Power Station has been completed and commissioned in Baganuur District, Ulaanbaatar city, supplying energy to the Central System.
This will allow the provision of electricity to approximately 25,000 households. The construction contract for the Plant was signed in September 2024, and on-site work began on September 15, 2024.
N. Batsaikhan, Deputy Director of "Monhorus International" LLC and Project Director of the Baganuur Battery Storage Power Station, said, "From the first of this month, we conducted testing and adjustments of the battery. On December 6, 2024, we began supplying energy to the central system for the first time. Initially, Blocks 1 and 2 supplied 25-30 MW of power, and then Blocks 3 and 4 were commissioned, bringing the total output to 40-50 MW supplied to the central system. To date, the Plant has delivered energy to the central system at full capacity twice, and over 12 days, it has supplied 1,800 MWh of electricity. When the Station operates at full capacity, it can provide electricity to around 25,000 households.”
J. Chen, an authorized representative of "Envision Energy" LLC, remarked, "Our company supplied 27 battery packages for the Baganuur Battery Storage Power Station. Each package consists of two parts. The Plant has the unique capability to charge during low-consumption nighttime hours and supply electricity during high-demand evening hours. This makes the Plant a clean green technology that does not emit carbon dioxide, serving as a renewable energy source. We aim at supplying higher-capacity battery storage plants and wind power plants in the future."
S. Khurelsukh, Executive Director of "Ulaanbaatar Energy" LLC, noted, "The testing and adjustments of the Plant have been completed, and the Plant is now operating at full capacity. During this period, no faults or interruptions have occurred in the equipment. Mongolian engineers actively participated in the Project and are now fully prepared to manage the Plant independently." as reported by the Public Relations and Communication Department of the Governor's Office of the Capital City.


Published Date:2024-12-19