1 N.UCHRAL: FINISH THE NAADAM FESTIVAL, PREPARE FOR WINTER WWW.GOGO.MN PUBLISHED:2026/07/27      2 OVER 2,800 DELEGATES EXPECTED FOR COP17 IN MONGOLIA WWW.GOGO.MN PUBLISHED:2026/07/27      3 VICTORIA DELMON ANNOUNCED AS WORLD BANK GROUP NEW COUNTRY MANAGER FOR MONGOLIA WWW.MONTSAME.MN PUBLISHED:2026/07/27      4 AI IN GOVERNMENT WWW.GOGO.MN PUBLISHED:2026/07/27      5 SA GAS COMPANY SIGNS BILLION-DOLLAR AGREEMENT WWW.INDAILYSA.COM.AU/ PUBLISHED:2026/07/27      6 MONGOLIA’S HUNNU NOBILITY CEMETERY COMPLEXES ADDED TO UNESCO WORLD HERITAGE LIST WWW.QAZINFORM.COM PUBLISHED:2026/07/27      7 MOM'S TOUCH OPENS 20TH STORE IN MONGOLIA, BECOMES NO. 2 QSR BRAND WWW.EN.SEDAILY.COM PUBLISHED:2026/07/27      8 GOVERNMENT DOMESTIC SECURITIES WORTH MNT 10 BILLION TRADED WWW.MONTSAME.MN PUBLISHED:2026/07/24      9 TMK ENERGY APPOINTS U.S. PRIVATE EQUITY VETERAN STEVE SKINNER AS COO TO DRIVE MONGOLIAN GAS PROJECT WWW.TIPRANKS.COM PUBLISHED:2026/07/24      10 ERDENE STOCK TRACKS LATEST RESOURCE UPDATE AS MONGOLIA GOLD PROJECT ADVANCES WWW.AD-HOC-NEWS.DE PUBLISHED:2026/07/24      Б.МӨНХТАМИР: COP17 ХУРАЛД УЛСЫН ТӨСВӨӨС 267 ТЭРБУМ ТӨГРӨГ ЗАРЦУУЛНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/07/27     МОНГОЛБАНК: ИНФЛЯЦ 2027 ОНООС ЗОРИЛТОТ ТҮВШИНД ТОГТВОРЖИХ ТӨЛӨВТЭЙ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/07/27     ДЭЛХИЙН БАНК ГРУППИЙН МОНГОЛ ДАХЬ СУУРИН ТӨЛӨӨЛӨГЧӨӨР ВИКТОРИА ДЕЛМОН ТОМИЛОГДЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/07/27     ЕРӨНХИЙ САЙД Н.УЧРАЛ: НАЙР НААДМАА ДУУСГА. ӨВӨЛДӨӨ БЭЛД WWW.GOGO.MN НИЙТЭЛСЭН:2026/07/27     ЗЭСИЙН ЭКСПОРТ НҮҮРСИЙГ ДАВЖ, ЭДИЙН ЗАСГИЙН ШИНЭ ТУЛГУУР БОЛЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/07/27     ДАМБАДАРЖАА ДУЛААНЫ СТАНЦЫГ ЭНЭ ОНД АШИГЛАЛТАД ОРУУЛНА WWW.NEWS.MN НИЙТЭЛСЭН:2026/07/27     ЖУУЛЧДЫН ТОО ӨМНӨХ ОНЫ МӨН ҮЕЭС 13.7 ХУВИАР НЭМЭГДЖЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/07/27     МОНГОЛ УЛСААС НҮБ-ЫН АНДЭЗНК-ЫН ДЭРГЭД СУУХ БАЙНГЫН ТӨЛӨӨЛӨГЧ В.ОЮУ ИТГЭМЖЛЭХ ЗАХИДЛАА ГАРДУУЛАВ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/07/24     “GLOBAL SILHOUETTE” ОЛОН УЛСЫН ҮЗЭСГЭЛЭН ХААН ГАЛЕРЕЙД НЭЭЛТЭЭ ХИЙЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/07/24     РИО ТИНТО-ТОЙ ХИЙХ ХЭЛЭЛЦЭЭРИЙН НОГДОЛ АШИГ АВАХ АЖЛЫН ХЭСГИЙГ САНГИЙН САЙД АХАЛНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/07/24    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Prime Minister Orders to Accelerate Thermal Power Plant Repairs and Renovation www.montsame.mn

Prime Minister of Mongolia Zandanshatar Gombojav reviewed the implementation of his previously issued directives at the state-owned company “Thermal Power Plant No. 3."
Minister of Energy of Mongolia Choijilsuren Battogtokh and Plenipotentiary Representative of the Government Tavinbekh Nansal reported about an accident that occurred on June 2, 2025, at the 50-megawatt high-pressure station, causing a fire in the production building and shutting down the ninth turbogenerator. The officials then presented three courses of action underway to eliminate the ramifications and restore normal operations.
The demolition and reconstruction of the damaged building are planned between July 25 and November 1, 2025. Additionally, the heat production system mode will be adjusted to prevent disruption of heat generation by October 2025. The basic groundwork has been completed, and negotiations are underway for the selection of the contractor.
Furthermore, the seventh and ninth turbogenerators will be fully replaced and commissioned for operation during the 2025–2026 winter. The ninth turbogenerator is the high-voltage power transmission unit located at the site of the accident, while the seventh 25 MW turbogenerator will compensate for the 50 MW lost caused by the accident. The initial funding for the renovation has been included in the state budget amendment, and the remaining funds will be reflected in next year’s budget. Plenipotentiary Representative of the Government Tavinbekh Nansal noted that the ninth turbogenerator is planned to be ordered for manufacture in the People’s Republic of China.
Moreover, a Joint Project with the Russian Federation has been launched to increase the capacity of the 48 MW medium-voltage station by 250 MW, with completion expected in 2028.
Prime Minister Zandanshatar Gombojav reminded the energy sector to work in unity and accelerate reparation and renovation works to prevent heating outages in the winter. The Prime Minister's further directives are as follows: to reduce the oversized structure and unnecessary positions in the sector; cut inefficient expenses; submit proposals by the end of the month; eradicate widely discussed issues such as bid-rigging, supplier pressure, and corruption in procurement processes; apply similar structural and expense-cutting measures to coal mines; prepare proposals for dissolving, merging, or privatizing non-essential units and present them to the Government by August 15, 2025. The Government will conduct a comprehensive inspection of the organization, operations, and finances to resolve the issues.
The 150 MW second block of the Buuruljuut Power Plant is scheduled to be commissioned in December 2025. Additionally, construction of a power plant in Selenge aimag has begun. The Prime Minister assured the country will successfully overcome the upcoming winter with the addition of the Toson Thermal Power Plant in Zavkhan, battery storage systems, and solar power plants.

 



Published Date:2025-07-18