1 MONGOLIA MOVES TO NEXT STAGE OF COPPER SMELTER SELECTION PROCESS WWW.MONTSAME.MN PUBLISHED:2026/02/26      2 INVESTMENT OPPORTUNITY IN MONGOLIAN MINING INTRODUCED IN LONDON WWW.MONTSAME.MN PUBLISHED:2026/02/26      3 MONGOLIA SEEKS LONDON STOCK EXCHANGE LISTINGS FOR MINING COMPANIES WWW.MONTSAME.MN PUBLISHED:2026/02/26      4 TMK ENERGY SETS NEW GAS OUTPUT RECORD AT MONGOLIAN CSG PILOT WWW.TIPRANKS.COM PUBLISHED:2026/02/26      5 WILL MONGOLIA BAN SOCIAL NETWORKS FOR CHILDREN, AS AUSTRALIA AND FRANCE HAVE DONE? WWW.OPEN.KG PUBLISHED:2026/02/26      6 FOREIGN TRADE TURNOVER REACHES USD 2.6 BILLION WWW.MONTSAME.MN PUBLISHED:2026/02/25      7 MONGOLIA REVOKES PERMITS OF SIX FOREIGN NGOS WWW.MONTSAME.MN PUBLISHED:2026/02/25      8 MINING DRIVES MONGOLIA’S ECONOMY AS REFORM MOMENTUM BUILDS WWW.EASTASIAFORUM.ORG PUBLISHED:2026/02/25      9 P.NARANBAYAR ANNOUNCES PLAN TO DRAFT LAW TO RESTRICT CHILDREN’S USE OF SOCIAL NETWORKS WWW.GOGO.MN PUBLISHED:2026/02/25      10 “EAGLE FESTIVAL-2026” TO BE HELD ON MARCH 7-8 WWW.GOGO.MN PUBLISHED:2026/02/24      ГАДААДЫН 95 ИРГЭНИЙГ УЛСЫН ХИЛЭЭР ОРУУЛАЛГҮЙ БУЦААЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/02/26     ЗЭСИЙН БАЯЖМАЛ ХАЙЛУУЛАХ, БОЛОВСРУУЛАХ ҮЙЛДВЭРИЙН ХӨРӨНГӨ ОРУУЛАГЧИЙГ ИРЭХ ТАВДУГААР САРД ТОДРУУЛНА WWW.EAGLE.MN НИЙТЭЛСЭН:2026/02/26     УЛААНБААТАР-ЛҮНГИЙН ЗАМЫГ ЗУРГААН ЭГНЭЭ БОЛГОНО WWW.EAGLE.MN НИЙТЭЛСЭН:2026/02/26     ЖАЙКА БОЛОН МТҮП МЭДЭЭЛЭЛ ТЕХНОЛОГИЙН САЛБАРЫГ ХӨГЖҮҮЛЭХ ТӨСЛИЙГ ХЭРЭГЖҮҮЛЖ ЭХЭЛЛЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/02/26     ЕРӨНХИЙ САЙДЫН АХЛАХ ЗӨВЛӨХ БӨГӨӨД АЖЛЫН АЛБАНЫ ДАРГААР Ж.САНДАГСҮРЭНГ ТОМИЛЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/02/26     БАРАА БҮТЭЭГДЭХҮҮНИЙ ҮНЭ САРЫН ХУГАЦААНД 2.7 ХУВИАР ӨСЧЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/02/26     НИЙСЛЭЛ ЗАРДЛАА ТЭЛЖ, ТРАМВАЙН ТӨСӨЛД 350 ТЭРБУМЫГ ЗАРЦУУЛНА WWW.NEWS.MN НИЙТЭЛСЭН:2026/02/25     САНГИЙТ КАУР ДЕО: МАЛАЙЗЫН ТӨР БУРУУТАЙ ГЭДГИЙГ ШИЙДҮҮЛЭХ ЭЦСИЙН БОЛОМЖ УЧРААС МОНГОЛЫН ТӨР ХАМТРАН АЖИЛЛАХЫГ ХҮСЭЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/02/25     НИЙСЛЭЛИЙН ТӨСӨВ: COP17 ХУРАЛД 70 ТЭРБУМ ЗАРЦУУЛЖ, 200 ТЭРБУМЫН БОНД БОСГОЖ V ЦАХИЛГААН СТАНЦ БАРИНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/02/25     ХӨРСНИЙ УС, ҮЕРИЙН ХАМГААЛАЛТЫН ТӨСЛИЙН ТЭЗҮ-ИЙГ БОЛОВСРУУЛАХ АЖИЛ 90 ХУВЬТАЙ ХЭРЭГЖИЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/02/24    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Second-Stage Tender for Ulaanbaatar Metro Project to Be Announced in August www.montsame.mn

Budget officials and the consortium of the Ulaanbaatar Metro Project, led by the consultancy company “Dohwa Engineering,” conducted a site visit to the 28th khoroo of Bayanzurkh District.
The eastern depot of the Ulaanbaatar Metro project is planned for construction on a 26.6-hectare site within the 28th khoroo of Bayanzurkh district, centralizing operations such as technical servicing, diagnostics, repairs, and parking of the rolling stock. The second stage of the contractor selection process will be announced, followed by contract signing in October 2025 and the commencement of construction work in 2026. Within the framework of the project, a general environmental status assessment has been conducted, and the land certificate for the depot construction site has been issued.
Railway Engineer of the Ulaanbaatar Metro Project B. Amgalanbayar explained, “The Ulaanbaatar Metro will have a daily capacity of 17,200 persons and a total of 15 stations. As for the structure and design, it will span 14 underground stations, with the terminal station located above ground, adjacent to the maintenance depot. The metro is scheduled to run at intervals of 4.5 minutes.”
Mechanical Design Engineer at the consulting company “Dohwa Engineering” Kim Jin Nam elaborated, "The plan includes a total of 19 fully automated, driverless metro trainsets. The maintenance depot will comprise distinct sections for automated servicing, washing, control and monitoring, and rolling stock parking. The parking facilities will be built fully enclosed, specifically designed to withstand Mongolia’s harsh climate conditions. The metros will be centrally managed from the control center."
Routine maintenance is scheduled every two to five years, for which a centralized maintenance facility will be established. According to the operational plan, metro trainsets will travel along the designated route, execute a turnaround at the western terminal station in Tolgoit, proceed and arrive at the eastern depot for washing and maintenance, and enter the parking zone.
Based on current estimates, a total of thirteen 30-meter-long Tunnel Boring Machines (TBMs) will be used for the project to be commissioned by 2030. The TBM will operate at a depth of 25 meters underground, enabling tunnel excavation and installation of tunnel lining segments. Specialists highlighted that since tunnelling will be conducted in densely populated areas of the city, vibrations will be negligible at the surface level.

 