1 N.UCHRAL: FINISH THE NAADAM FESTIVAL, PREPARE FOR WINTER WWW.GOGO.MN PUBLISHED:2026/07/27      2 OVER 2,800 DELEGATES EXPECTED FOR COP17 IN MONGOLIA WWW.GOGO.MN PUBLISHED:2026/07/27      3 VICTORIA DELMON ANNOUNCED AS WORLD BANK GROUP NEW COUNTRY MANAGER FOR MONGOLIA WWW.MONTSAME.MN PUBLISHED:2026/07/27      4 AI IN GOVERNMENT WWW.GOGO.MN PUBLISHED:2026/07/27      5 SA GAS COMPANY SIGNS BILLION-DOLLAR AGREEMENT WWW.INDAILYSA.COM.AU/ PUBLISHED:2026/07/27      6 MONGOLIA’S HUNNU NOBILITY CEMETERY COMPLEXES ADDED TO UNESCO WORLD HERITAGE LIST WWW.QAZINFORM.COM PUBLISHED:2026/07/27      7 MOM'S TOUCH OPENS 20TH STORE IN MONGOLIA, BECOMES NO. 2 QSR BRAND WWW.EN.SEDAILY.COM PUBLISHED:2026/07/27      8 GOVERNMENT DOMESTIC SECURITIES WORTH MNT 10 BILLION TRADED WWW.MONTSAME.MN PUBLISHED:2026/07/24      9 TMK ENERGY APPOINTS U.S. PRIVATE EQUITY VETERAN STEVE SKINNER AS COO TO DRIVE MONGOLIAN GAS PROJECT WWW.TIPRANKS.COM PUBLISHED:2026/07/24      10 ERDENE STOCK TRACKS LATEST RESOURCE UPDATE AS MONGOLIA GOLD PROJECT ADVANCES WWW.AD-HOC-NEWS.DE PUBLISHED:2026/07/24      Б.МӨНХТАМИР: COP17 ХУРАЛД УЛСЫН ТӨСВӨӨС 267 ТЭРБУМ ТӨГРӨГ ЗАРЦУУЛНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/07/27     МОНГОЛБАНК: ИНФЛЯЦ 2027 ОНООС ЗОРИЛТОТ ТҮВШИНД ТОГТВОРЖИХ ТӨЛӨВТЭЙ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/07/27     ДЭЛХИЙН БАНК ГРУППИЙН МОНГОЛ ДАХЬ СУУРИН ТӨЛӨӨЛӨГЧӨӨР ВИКТОРИА ДЕЛМОН ТОМИЛОГДЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/07/27     ЕРӨНХИЙ САЙД Н.УЧРАЛ: НАЙР НААДМАА ДУУСГА. ӨВӨЛДӨӨ БЭЛД WWW.GOGO.MN НИЙТЭЛСЭН:2026/07/27     ЗЭСИЙН ЭКСПОРТ НҮҮРСИЙГ ДАВЖ, ЭДИЙН ЗАСГИЙН ШИНЭ ТУЛГУУР БОЛЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/07/27     ДАМБАДАРЖАА ДУЛААНЫ СТАНЦЫГ ЭНЭ ОНД АШИГЛАЛТАД ОРУУЛНА WWW.NEWS.MN НИЙТЭЛСЭН:2026/07/27     ЖУУЛЧДЫН ТОО ӨМНӨХ ОНЫ МӨН ҮЕЭС 13.7 ХУВИАР НЭМЭГДЖЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/07/27     МОНГОЛ УЛСААС НҮБ-ЫН АНДЭЗНК-ЫН ДЭРГЭД СУУХ БАЙНГЫН ТӨЛӨӨЛӨГЧ В.ОЮУ ИТГЭМЖЛЭХ ЗАХИДЛАА ГАРДУУЛАВ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/07/24     “GLOBAL SILHOUETTE” ОЛОН УЛСЫН ҮЗЭСГЭЛЭН ХААН ГАЛЕРЕЙД НЭЭЛТЭЭ ХИЙЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/07/24     РИО ТИНТО-ТОЙ ХИЙХ ХЭЛЭЛЦЭЭРИЙН НОГДОЛ АШИГ АВАХ АЖЛЫН ХЭСГИЙГ САНГИЙН САЙД АХАЛНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/07/24    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Second-Stage Tender for Ulaanbaatar Metro Project to Be Announced in August www.montsame.mn

Budget officials and the consortium of the Ulaanbaatar Metro Project, led by the consultancy company “Dohwa Engineering,” conducted a site visit to the 28th khoroo of Bayanzurkh District.
The eastern depot of the Ulaanbaatar Metro project is planned for construction on a 26.6-hectare site within the 28th khoroo of Bayanzurkh district, centralizing operations such as technical servicing, diagnostics, repairs, and parking of the rolling stock. The second stage of the contractor selection process will be announced, followed by contract signing in October 2025 and the commencement of construction work in 2026. Within the framework of the project, a general environmental status assessment has been conducted, and the land certificate for the depot construction site has been issued.
Railway Engineer of the Ulaanbaatar Metro Project B. Amgalanbayar explained, “The Ulaanbaatar Metro will have a daily capacity of 17,200 persons and a total of 15 stations. As for the structure and design, it will span 14 underground stations, with the terminal station located above ground, adjacent to the maintenance depot. The metro is scheduled to run at intervals of 4.5 minutes.”
Mechanical Design Engineer at the consulting company “Dohwa Engineering” Kim Jin Nam elaborated, "The plan includes a total of 19 fully automated, driverless metro trainsets. The maintenance depot will comprise distinct sections for automated servicing, washing, control and monitoring, and rolling stock parking. The parking facilities will be built fully enclosed, specifically designed to withstand Mongolia’s harsh climate conditions. The metros will be centrally managed from the control center."
Routine maintenance is scheduled every two to five years, for which a centralized maintenance facility will be established. According to the operational plan, metro trainsets will travel along the designated route, execute a turnaround at the western terminal station in Tolgoit, proceed and arrive at the eastern depot for washing and maintenance, and enter the parking zone.
Based on current estimates, a total of thirteen 30-meter-long Tunnel Boring Machines (TBMs) will be used for the project to be commissioned by 2030. The TBM will operate at a depth of 25 meters underground, enabling tunnel excavation and installation of tunnel lining segments. Specialists highlighted that since tunnelling will be conducted in densely populated areas of the city, vibrations will be negligible at the surface level.

 



Published Date:2025-08-01