1 TRUMP’S SON WITH KAZAKH TUNGSTEN TIES LOST IN MONGOLIAN MOUNTAINS WWW.KZ.KURSIV.MEDIA PUBLISHED:2026/09/10      2 MONGOLIA TO HOLD PARLIAMENTARY HEARING ON EPSTEIN FILES IN OCTOBER WWW.AZERNEWS.AZ PUBLISHED:2026/09/10      3 MONGOLIA'S FOREIGN TRADE TURNOVER SURGES NEARLY 37 PCT IN FIRST 8 MONTHS WWW.XINHUANET.COM PUBLISHED:2026/09/10      4 MONGOLIA SIGNS MOU WITH BLACKROCK FMA WWW.MONTSAME.MN PUBLISHED:2026/09/10      5 MONGOLIA, UAE SIGN ENERGY COOPERATION MOU WWW.MONTSAME.MN PUBLISHED:2026/09/10      6 SPEAKERS OF MONGOLIA, VIETNAM HOLD OFFICIAL TALKS WWW.MONTSAME.MN PUBLISHED:2026/09/10      7 MONGOLIA AGREES TO PURCHASE 10,000 TONS OF GASOLINE AND 4,000 TONS OF JET FUEL FROM CHINA IN SEPTEMBER WWW.GOGO.MN PUBLISHED:2026/09/10      8 ADB SUPPORTS MONGOLIA'S FIRST GREEN-CERTIFIED RESIDENTIAL COMPLEX BUILT BY THE PRIVATE SECTOR WWW.ADB.ORG PUBLISHED:2026/09/09      9 MONGOLIA FINISHES FOURTH WITH 26 MEDALS AT WORLD NOMAD GAMES WWW.ASIANEWS.NETWORK PUBLISHED:2026/09/09      10 NEW FLIGHT ROUTES EXPLORED WITH HOKKAIDO AIRPORTS WWW.UBPOST.MN PUBLISHED:2026/09/09      ШАТАХУУНЫ НИЙЛҮҮЛЭЛТЭЭ УРТ ХУГАЦААНД ТОГТВОРЖУУЛЖ, ГАЗРЫН ТОС, НҮҮРС-ХИМИЙН ХАМТЫН АЖИЛЛАГААГ ӨРГӨЖҮҮЛНЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/10     ГОЛОМТ БАНК ХАРИЛЦАГЧДЫНХАА ХУДАЛДАА, ТӨЛБӨР ТООЦООГ ДЭМЖИХЭЭР BANK OF CHINA-ТАЙ СТРАТЕГИЙН ХАМТЫН АЖИЛЛАГААГ ЭХЛҮҮЛЛЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/10     АНЭУ-ТАЙ ЭРЧИМ ХҮЧНИЙ САЛБАРТ ХАМТРАН АЖИЛЛАНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/10     МАХ, БЕНЗИНИЙ ҮНИЙН НӨЛӨӨГӨӨР ИНФЛЯЦ 12.5 ХУВЬД ХҮРЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/10     МОНГОЛД ИРЖ БУЙ РИО ТИНТО ГРУППИЙН CEO САЙМОН ТРОТТ ГЭЖ ХЭН БЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/10     Ц.БАТБААТАР: ХАТУУ ЗОХИЦУУЛАЛТТАЙ 38 УЛСААС ОРЖ ИРЖ БАЙГАА ЭМҮҮДИЙГ ХӨНГӨЛӨЛТТЭЙ ЭМИЙН ЖАГСААЛТАД ХАМРУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/10     Н.УЧРАЛ: МИНИЙ ГЭР БҮЛ, АЖИЛ МЭРГЭЖЛИЙН НЭР ХҮНДЭД ХАЛДЛАА WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/10     СЭЛБЭ УХААЛАГ ХОТОД УНДНЫ УСНЫ ЗЭС ХООЛОЙ ШУГАМ УГСАРЧ БАЙНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/09     НАЙМДУГААР САРД ХҮНСНИЙ БҮЛГИЙН БҮТЭЭГДЭХҮҮНИЙ ҮНЭ 21.5 ХУВЬ НЭМЭГДЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/09     ЭРЧИМ ХҮЧНИЙ ҮНЭ НЭМЭХГҮЙН ТУЛД ТӨСӨВТ 200 ТЭРБУМ ТӨГРӨГИЙН ТАТААС ТУСГАЖЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/09    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Second-Stage Tender for Ulaanbaatar Metro Project to Be Announced in August www.montsame.mn

Budget officials and the consortium of the Ulaanbaatar Metro Project, led by the consultancy company “Dohwa Engineering,” conducted a site visit to the 28th khoroo of Bayanzurkh District.
The eastern depot of the Ulaanbaatar Metro project is planned for construction on a 26.6-hectare site within the 28th khoroo of Bayanzurkh district, centralizing operations such as technical servicing, diagnostics, repairs, and parking of the rolling stock. The second stage of the contractor selection process will be announced, followed by contract signing in October 2025 and the commencement of construction work in 2026. Within the framework of the project, a general environmental status assessment has been conducted, and the land certificate for the depot construction site has been issued.
Railway Engineer of the Ulaanbaatar Metro Project B. Amgalanbayar explained, “The Ulaanbaatar Metro will have a daily capacity of 17,200 persons and a total of 15 stations. As for the structure and design, it will span 14 underground stations, with the terminal station located above ground, adjacent to the maintenance depot. The metro is scheduled to run at intervals of 4.5 minutes.”
Mechanical Design Engineer at the consulting company “Dohwa Engineering” Kim Jin Nam elaborated, "The plan includes a total of 19 fully automated, driverless metro trainsets. The maintenance depot will comprise distinct sections for automated servicing, washing, control and monitoring, and rolling stock parking. The parking facilities will be built fully enclosed, specifically designed to withstand Mongolia’s harsh climate conditions. The metros will be centrally managed from the control center."
Routine maintenance is scheduled every two to five years, for which a centralized maintenance facility will be established. According to the operational plan, metro trainsets will travel along the designated route, execute a turnaround at the western terminal station in Tolgoit, proceed and arrive at the eastern depot for washing and maintenance, and enter the parking zone.
Based on current estimates, a total of thirteen 30-meter-long Tunnel Boring Machines (TBMs) will be used for the project to be commissioned by 2030. The TBM will operate at a depth of 25 meters underground, enabling tunnel excavation and installation of tunnel lining segments. Specialists highlighted that since tunnelling will be conducted in densely populated areas of the city, vibrations will be negligible at the surface level.

 



Published Date:2025-08-01