1 D. DALAIJARGAL: URANIUM MINING PROJECT ADVANCES FAST WITH FRENCH FUNDING WWW.MONGOLIANMININGJOURNAL.COM  PUBLISHED:2025/12/05      2 MONGOLIA, INDIA TO ADVANCE STRATEGIC PARTNERSHIP IN DIGITAL DEVELOPMENT AND INNOVATION WWW.MONTSAME.MN PUBLISHED:2025/12/05      3 POPE LEO MEETS WITH THE PRESIDENT OF MONGOLIA WWW.VATICANNEWS.VA PUBLISHED:2025/12/05      4 NATIONAL PROTECTED AREA CONSULTATION TARGETS STRONGER RANGER SYSTEM WWW.MONTSAME.MN PUBLISHED:2025/12/05      5 RIO TINTO REVISES UP 2025 COPPER PRODUCTION FORECAST AS MONGOLIAN PROJECT ACCELERATES OPERATIONS WWW.NEWS.METAL.COM  PUBLISHED:2025/12/05      6 MONGOLIA CALLS PUBLIC HEARINGS AHEAD OF LIKELY PUSH TO RENEGOTIATE RIO TINTO TERMS ON GIANT COPPER MINE WWW.INTELLINEWS.COM PUBLISHED:2025/12/05      7 MONGOLIA RECEIVES HIGHEST NUMBER OF FOREIGN TOURISTS SINCE THE BEGINNING OF 2025 WWW.XINHUANET.COM PUBLISHED:2025/12/05      8 MONGOLIA SIGNALS READINESS TO CONTRIBUTE TO GLOBAL FIGHT AGAINST DESERTIFICATION WWW.QAZINFORM.COM PUBLISHED:2025/12/04      9 MONGOLIA’S FOREIGN EXCHANGE RESERVES REACH USD 6 BILLION WWW.MONTSAME.MN PUBLISHED:2025/12/04      10 FUEL SUPPLY STRENGTHENED AS DECEMBER PURCHASE ORDERS CONFIRMED WWW.MONTSAME.MN PUBLISHED:2025/12/04      МАЛ, ТЭЖЭЭВЭР АМЬТНЫ ТООЛЛОГО НЯМ ГАРАГТ ЭХЭЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/12/05     Ш.РАДНААСЭД ЕРӨНХИЙ САЙДЫН АХЛАХ ЗӨВЛӨХ БОЛОВ WWW.NEWS.MN НИЙТЭЛСЭН:2025/12/05     АШИГТ МАЛТМАЛЫН 8 ЗӨВШӨӨРЛИЙН ХАРИУД ₮2.7 ТЭРБУМЫГ АВСАН Ш.ГАНХУЯГ, ӨГСӨН ЭДВАРД СҮРЭН НАРЫГ 1 САР ХОРИВ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/05     ЕРӨНХИЙЛӨГЧ У.ХҮРЭЛСҮХ ГЭГЭЭН ШИРЭЭТ УЛСЫН ТӨРИЙН ТЭРГҮҮНТЭЙ УУЛЗЛАА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/12/05     ТАВАНТОЛГОЙ-ГАШУУНСУХАЙТ ЧИГЛЭЛИЙН ТӨМӨР ЗАМААР ТАВАН САРД 3 САЯ ТОНН НҮҮРС ТЭЭВЭРЛЭВ WWW.EGUUR.MN  НИЙТЭЛСЭН:2025/12/05     MONGOLIA FOCUS: МОНГОЛД ӨӨРИЙГӨӨ ЦЕНЗУРДЭХ ҮЗЭГДЭЛ НЭМЭГДСЭН НЬ АРДЧИЛЛЫН ЧАНАР ДОРОЙТОЖ БУЙН ИЛРЭЛ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/12/05     11575 АЙЛЫН ОРОН СУУЦ БАРИХ БОЛОМЖ БҮРДЭВ WWW.NEWS.MN  НИЙТЭЛСЭН:2025/12/05     Н.ЦЭРЭНСАМБУУ: ГАДААДЫН ХӨРӨНГӨ ОРУУЛАЛТААР БОР ТЭЭГИЙН ОРДЫГ ЭДИЙН ЗАСГИЙН ЭРГЭЛТЭД ОРУУЛНА WWW.EAGLE.MN НИЙТЭЛСЭН:2025/12/04     С.БЯМБАЦОГТ: ЗЭС ХАЙЛУУЛАХ ҮЙЛДВЭРИЙГ БАРИХ ХӨРӨНГӨ ОРУУЛАГЧИЙГ НЭЭЛТТЭЙ СОНГОН ШАЛГАРУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/04     NETFLIX-ИЙН МОНГОЛД ХИЙХ ШИНЭ НЭВТРҮҮЛГИЙН НӨЛӨӨ БА АЛГАН ДЭЭР ТАВЬСАН БОЛОМЖОО АШИГЛАХУЙ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/12/04    

Turnaround Track Installed as Construction Progresses on Ulaanbaatar’s First Urban Cable Car System www.montsame.mn

Ulaanbaatar is making visible progress on its first urban cable car system, a landmark infrastructure project designed to ease traffic, cut air pollution, and improve public transport connectivity. The Cable Car Transport Project – Line I, a 4.2 km route connecting the Yarmag area (Artsat Yarmag Station) to Unur khoroolol (Kharkhorin Station) via a crossing over the Tuul River, is currently under active construction.
A turnaround track, a key structural component enabling the movement of cables and cabins, has been installed at the Yarmag Station. Out of the planned 19 pylons (support towers), six have already been erected at the Yarmag and Kharkhorin sites.
Nearby, construction is ongoing on a garage facility that will house cable car cabins, with concrete foundation and structural works currently underway.
The project is being led by engineers from France's POMA Group, with Monnis Engineering serving as the local subcontractor.
According to the current timeline, concrete works will be completed by October 30, and all 19 support towers are scheduled for installation by November 2025. Interior work for technical systems, including plumbing, heating, ventilation, communication, and control systems, will begin in January 2026.
Notably, the cabins will feature heating systems for winter comfort, ventilation for summer operation, dual power supplies for reliability, and safety equipment to ensure secure and efficient service year-round.
The project is being managed by the Unified Project Management Authority, a state-owned enterprise acting as the client representative. The authority is working closely with contractors to ensure timely and efficient implementation.
Cable Car Transport Project – Line I:
Line Length: 4.2 km
Stations: 2 (6.45–42 meters in elevation)
Support Towers / Pylons: 19
Peak Capacity: 2,320 passengers per hour