1 CLEAN-UP, INFRASTRUCTURE PREPARATIONS FOR COP17 UNDERWAY AT NATIONAL GARDEN PARK WWW.MONTSAME.MN PUBLISHED:2025/11/07      2 BANK OF MONGOLIA PURCHASES 2,829 KG OF PRECIOUS METALS IN OCTOBER WWW.MONTSAME.MN PUBLISHED:2025/11/07      3 SINGAPORE NOW HAS NON-STOP FLIGHTS TO MONGOLIA WWW.MAINLYMILES.COM PUBLISHED:2025/11/07      4 PETRO MATAD ANNOUNCES UPDATES ON GAZELLE AND HERON WELLS IN MONGOLIA WWW.OFFSHORE-TECHNOLOGY.COM PUBLISHED:2025/11/07      5 MONGOLIA SHINES AT WTM 2025 IN LONDON, UNVEILING ITS RICH CULTURE AND SUSTAINABLE TRAVEL TO A GLOBAL AUDIENCE WWW.TRAVELANDTOURWORLD.COM PUBLISHED:2025/11/07      6 MONGOLIAN DOCTORS AND HEALTH STAFF ANNOUNCE STRIKE FROM NOVEMBER 13 WWW.THESTAR.COM.MY PUBLISHED:2025/11/07      7 ADB TO SUPPORT MONGOLIA’S DISASTER PREPAREDNESS THROUGH INNOVATION AND TECHNOLOGY WWW.ADB.ORG PUBLISHED:2025/11/07      8 MINISTER G.DAMDINNYAM: “WE HAVE FIRMLY DEMANDED THAT RIO TINTO END THE MANAGEMENT CONTRACT BASED ON THE “EXPIRED” DUBAI AGREEMENT” WWW.ARCTUSANALYTICS.COM PUBLISHED:2025/11/05      9 MONGOLIA’S DEFECTOR DILEMMA: NAVIGATING THE KOREA DIVIDE WWW.THEDIPLOMAT.COM PUBLISHED:2025/11/05      10 AIR INDIA TO FLY RELIEF AIRCRAFT TO MONGOLIA TO BRING BACK 228 STRANDED PASSENGERS WWW.INDIATODAY.COM PUBLISHED:2025/11/05      МОНГОЛООР ДАМЖИХ УМАРД СОЛОНГОСЫН ДҮРВЭГЧДИЙН ХЯМРАЛ: СОЛОНГОСЫН ХУВААГДАЛ ДУНДАХ ИДЕАЛИЗМ БА ПРАГМАТИЗМ WWW.ITOIM.MN НИЙТЭЛСЭН:2025/11/07     "УХАА ХУДАГ"-ИЙН АСУУДЛААР ХЯНАН ШАЛГАХ ТҮР ХОРОО БАЙГУУЛАХ САНАЛ ХУРААЛТАД МАРГААН ГАРЧ, ХОЙШЛУУЛАВ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/11/07     АКУА ГАРДЕН: ӨЧИГДӨР ТОВЛОГДСОН ШҮҮХ ХУРАЛ ДАХИН ХОЙШИЛЖ, ЗАХИАЛСАН 640 АЙЛ БАЙРАА ЗАРЖ ЭХЭЛЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/11/07     ДУУЛИАНТ ХЭЛЦЭЛ: "РИО ТИНТО" ТӨМРИЙН ХҮДРИЙН УУРХАЙГАА ЧАЙНАЛКОД ӨГСНӨӨР АВСТРАЛИЙН ТӨСӨВТ 10 ТЭРБУМ АМ.ДОЛЛАРЫН АЛДАГДАЛ ҮҮСНЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2025/11/07     МАХ, МАХАН БҮТЭЭГДЭХҮҮНИЙГ 211.2 САЯ ДОЛЛАРААР ЭКСПОРТОЛЖЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2025/11/07     ЦАГ АГААРЫН УЛМААС НИСЛЭГИЙН ЗАРИМ ХУВААРИЙГ ӨӨРЧЛӨВ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/11/07     “ХҮНСНИЙ ХУВЬСГАЛ”-ЫН ҮР ДҮНД 53 ҮЙЛДВЭР АШИГЛАЛТАД ОРЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2025/11/07     ГАДААД ВАЛЮТЫН НӨӨЦ 5.9 ТЭРБУМ АМ.ДОЛЛАРТ ХҮРЛЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2025/11/05     ОЮУ ТОЛГОЙГООС ЭРДЭНЭС ОЮУ ТОЛГОЙ РУУ ШИЛЖҮҮЛСЭН 18.3 САЯ ДОЛЛАРЫН ЗАРЦУУЛАЛТЫГ НУУЦААС ГАРГАНА WWW.ITOIM.MN НИЙТЭЛСЭН:2025/11/05     БАГШ НАР НАМЖСАН Ч ЭРҮҮЛ МЭНДИЙН САЛБАРЫНХАН 5 ХОНОГИЙН ДАРАА АЖИЛ ХАЯНА WWW.EGUUR.MN НИЙТЭЛСЭН:2025/11/05    

Turnaround Track Installed as Construction Progresses on Ulaanbaatar’s First Urban Cable Car System www.montsame.mn

Ulaanbaatar is making visible progress on its first urban cable car system, a landmark infrastructure project designed to ease traffic, cut air pollution, and improve public transport connectivity. The Cable Car Transport Project – Line I, a 4.2 km route connecting the Yarmag area (Artsat Yarmag Station) to Unur khoroolol (Kharkhorin Station) via a crossing over the Tuul River, is currently under active construction.
A turnaround track, a key structural component enabling the movement of cables and cabins, has been installed at the Yarmag Station. Out of the planned 19 pylons (support towers), six have already been erected at the Yarmag and Kharkhorin sites.
Nearby, construction is ongoing on a garage facility that will house cable car cabins, with concrete foundation and structural works currently underway.
The project is being led by engineers from France's POMA Group, with Monnis Engineering serving as the local subcontractor.
According to the current timeline, concrete works will be completed by October 30, and all 19 support towers are scheduled for installation by November 2025. Interior work for technical systems, including plumbing, heating, ventilation, communication, and control systems, will begin in January 2026.
Notably, the cabins will feature heating systems for winter comfort, ventilation for summer operation, dual power supplies for reliability, and safety equipment to ensure secure and efficient service year-round.
The project is being managed by the Unified Project Management Authority, a state-owned enterprise acting as the client representative. The authority is working closely with contractors to ensure timely and efficient implementation.
Cable Car Transport Project – Line I:
Line Length: 4.2 km
Stations: 2 (6.45–42 meters in elevation)
Support Towers / Pylons: 19
Peak Capacity: 2,320 passengers per hour