1 MONGOLIA, JAPAN TO EXPAND COOPERATION IN TECHNOLOGY, AI, GREEN DEVELOPMENT WWW.MONTSAME.MN PUBLISHED:2026/05/01      2 CUSTOMS INSPECTOR ARRESTED DUE TO BRIBERY WWW.UBPOST.MN PUBLISHED:2026/05/01      3 TRUMP SONS INVESTED IN US GROUP DEVELOPING $1.1B TUNGSTEN PROJECT IN KAZAKHSTAN: FT WWW.MINING.COM PUBLISHED:2026/05/01      4 GOVERNMENT TO FUND THERMAL POWER PLANT REPAIRS FROM RESERVE FUND WWW.MONTSAME.MN PUBLISHED:2026/05/01      5 MONGOLIA RISES 17 PLACES IN PRESS FREEDOM INDEX WWW.MONTSAME.MN PUBLISHED:2026/05/01      6 MONGOLIA-CUBA PARLIAMENTARY GROUP CHAIR MEETS AMBASSADOR WWW.MONTSAME.MN PUBLISHED:2026/05/01      7 CHINA ADVANCES INNER MONGOLIA AS A KEY HUB FOR NORTHERN OPENING UP WWW.ALWIHDAINFO.COM PUBLISHED:2026/05/01      8 ‘CITIZENS BEAR CONSEQUENCES WHEN COURTS FALL UNDER POLITICAL INFLUENCE’ WWW.UBPOST.MN PUBLISHED:2026/04/30      9 CABINET APPROVES DRAFT TAX LAW AMENDMENTS OFFERING MNT 2.2 TRILLION IN RELIEF WWW.MONTSAME.MN PUBLISHED:2026/04/30      10 MEAT PRICE CRISIS DRIVES INFLATION SPIKE ACROSS MONGOLIA WWW,GOGO.MN PUBLISHED:2026/04/30      ИПОТЕКИЙН ГАЦАА БОЛ САНХҮҮЖИЛТИЙН БИШ ТОГТОЛЦООНЫ АСУУДАЛ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/05/01     ТАТВАРЫН ДАРАМТАНД СӨХӨРСӨН ААН-ҮҮД ХААЛГАА БАРЬЖ БАЙНА WWW.NEWS.MN НИЙТЭЛСЭН:2026/05/01     МОНГОЛБАНК: ИНФЛЯЦ 9.9 ХУВЬД ХҮРЧ БОЛЗОШГҮЙ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/05/01     МОНГОЛ УЛСЫН НЭГДСЭН ТӨСВИЙН 2027 ОНЫ ТӨСВИЙН ХҮРЭЭНИЙ МЭДЭГДЭЛ, 2028-2029 ОНЫ ТӨСВИЙН ТӨСӨӨЛЛИЙН ТУХАЙ ХУУЛИЙН ТӨСӨЛ ӨРГӨН МЭДҮҮЛЛЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/05/01     “БАДРАХ ЭНЕРЖИ”, “МОННИС ИНЖЕНЕРИНГ” ХХК-ИУД ЗӨӨВЧ-ОВОО ТӨСЛИЙН ХҮРЭЭНД ХАМТРАН АЖИЛЛАХААР БОЛЛОО WWW.GOGO.MN НИЙТЭЛСЭН:2026/05/01     Б.ДАВААДАЛАЙ: "ЭРДЭНЭС МОНГОЛ" ХХК-ИЙН ОРОН ТООГ ДАХИАД Ч ЦӨӨЛНӨ. ҮР АШИГГҮЙ КОМПАНИУДЫГ ТАТАН БУУЛГАНА WWW.EGUUR.MN НИЙТЭЛСЭН:2026/05/01     АРЦАТЫН АВТО ЗАМ ХҮРТЭЛ 350 МЕТР АВТО ЗАМ БАРИНА WWW.NEWS.MN НИЙТЭЛСЭН:2026/05/01     “ОЮУ ТОЛГОЙ” КОМПАНИЙН 2026 ОНЫ НЭГДҮГЭЭР УЛИРЛЫН ТАЙЛАНГААС ОНЦЛОХ НЬ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/04/30     УИХ: ХУДАЛДАА АЖ ҮЙЛДВЭРИЙН ТАНХИМЫН ТУХАЙ ХУУЛИЙН ТӨСЛИЙГ УНАГАВ WWW.NEWS.MN НИЙТЭЛСЭН:2026/04/30     С.НАРАНЦОГТ: ГАДНЫН БАНК ОРЖ ИРЛЭЭ ГЭЭД МОНГОЛ СҮЙРЧИХГҮЙ, БИД ТУСГААР ТОГТНОЛОО АЛДАХГҮЙ WWW.GOGO.MN НИЙТЭЛСЭН:2026/04/29    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Reuters learns when Russia will complete gas pipeline to China www.newsukraine.rbc.ua

Russia will need at least five years to build a gas pipeline to China. An equal amount of time will be required to increase the volume of gas supplies, Reuters reports.
Alexei Miller, CEO of Gazprom, stated that during Russian President Vladimir Putin’s visit to China last month, a "legally binding memorandum" was signed on the construction of the Power of Siberia-2 gas pipeline.
The agency notes that this indicates Moscow’s efforts to redirect its gas reserves to Asia. This comes after the collapse of energy trade with Europe, previously Russia’s largest market, due to Western sanctions.
The construction schedule for the pipeline had not been previously reported. Reuters emphasized that the key terms of the pipeline construction agreement have not yet been finalized.
It is expected to run through Mongolia and deliver up to 50 billion cubic meters of gas annually from the Yamal Arctic region.
Two industry sources reported that, if an agreement is reached next year, about five years will be needed to build the pipeline and begin deliveries. An additional five years will be required to increase supply volumes.
An informed source noted that Gazprom does not expect the pipeline to reach half of its capacity by 2034–2035 if deliveries start after 2031.
Analysts at the Oxford Institute for Energy Studies believe that with a 2026 agreement, initial deliveries could take place by the end of 2030 or 2031, with significant volume increases achieved by January 1, 2035.
Earlier, in early September, Russian Gazprom announced the signing of an agreement to build the Power of Siberia-2 gas pipeline to China via Mongolia.
For context, deliveries of Russian gas to China via the Power of Siberia pipeline began in 2019.
Currently, Western and Eastern Siberia are not connected by a unified network, and Russia hopes to build Power of Siberia-2 to redirect gas from Western Siberian fields.