1 CENTRAL BANK INTRODUCES NEW RESERVE RULE FOR FOREIGN BORROWING WWW.MONTSAME.MN PUBLISHED:2026/05/27      2 CONSUMER LOAN DEFAULTS STABILIZE IN RECENT MONTHS WWW.MONTSAME.MN PUBLISHED:2026/05/27      3 GOVERNMENT APPROVES MAJOR RESTRUCTURING OF ERDENES MONGOL WWW.MONTSAME.MN PUBLISHED:2026/05/27      4 CAPITAL MARKETS MONGOLIA SUCCESSFULLY HOSTS INAUGURAL MONGOLIA INVESTMENT FORUM IN SHANGHAI WWW.CAPITALMARKETS.MN PUBLISHED:2026/05/27      5 NATIONAL GREEN LAB SHORTLISTS TOP PROJECTS FOR COP17 WWW.MONTSAME.MN PUBLISHED:2026/05/27      6 MONGOLIA INTRODUCES IDENTIFICATION SIGNS FOR PREGNANT WOMEN WWW.XINHUANET.COM PUBLISHED:2026/05/27      7 ROAD CONSTRUCTION FOR COP-17 TO BE COMPLETED BY JULY 1 WWW.GOGO.MN PUBLISHED:2026/05/27      8 B.PUREVDAGVA APPOINTED GOVERNOR OF THE CAPITAL CITY AND MAYOR OF ULAANBAATAR WWW.GOGO.MN PUBLISHED:2026/05/27      9 INTERIM TRADE AGREEMENT TO DIVERSIFY EXPORT STRUCTURE, MARKETS WWW.MONTSAME.MN PUBLISHED:2026/05/27      10 TOWARD A US-MONGOLIA CRITICAL MINERALS PARTNERSHIP WWW.NATIONALINTEREST.ORG PUBLISHED:2026/05/26      "РИО ТИНТО"-ТОЙ ХЭЛЭЛЦЭЭ ХИЙХТЭЙ ЗЭРЭГЦЭН Г.ДАМДИННЯМ ЗЭСИЙН АМНАТ-ИЙГ БУУРУУЛАХ ХУУЛЬ ЗҮТГҮҮЛЛЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/05/27     “ЭРДЭНЭТ ҮЙЛДВЭР” ТӨҮГ-Т АЖИЛЛАЖ БАЙХДАА ИХ ХЭМЖЭЭНИЙ ХАХУУЛЬ АВСАН ХЭРГИЙГ ШҮҮХЭЭР ШИЙДВЭРЛЭЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/05/27     "ЭРДЭНЭС ОЮУ ТОЛГОЙ" КОМПАНИЙГ Б.ТЭЛМҮҮН УДИРДАНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/05/27     Б.ДАВААДАЛАЙ: "ЭРДЭНЭС МОНГОЛ НЭГДЭЛ" НЭРЭЭ ӨӨРЧИЛЖ, ХӨРӨНГӨ УДИРДАХ ЧИГЛЭЛД ТӨВЛӨРНӨ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/05/27     УС, ДУЛААНЫ ТӨЛБӨРӨӨ ТӨЛДӨГГҮЙ ӨРХИЙН МЭДЭЭЛЛИЙГ ЗЭЭЛИЙН МЭДЭЭЛЛИЙН САНД БҮРТГЭНЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/05/27     ЗҮТГҮҮРИЙН ЦАХИЛГААН ХӨДӨЛГҮҮРИЙГ МОНГОЛДОО ЗАСДАГ БОЛЛОО WWW.GOGO.MN НИЙТЭЛСЭН:2026/05/27     БАНКНЫ САЛБАР ГАДААД ЗАХ ЗЭЭЛЭЭС УРТ ХУГАЦААТ ЭХ ҮҮСВЭР ТАТАХЫГ ДЭМЖИХ ШИЙДВЭР ГАРГАВ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/05/27     МАНАЙ УЛС АМИА ХОРЛОЛТЫН ТООГООР ДЭЛХИЙД ХОЁРТ ЭРЭМБЭЛЭГДЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/05/27     ЗӨВЛӨМЖ: НАС БАРСАН ИРГЭНИЙ 1072 ХУВЬЦААГ ӨВЛҮҮЛЖ, НОГДОЛ АШИГ АВАХ 5 АЛХАМ, БУСАД ЗААВАРЧИЛГАА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/05/27     БАНКНЫ САЛБАР 2.5 ИХ НАЯД ТӨГРӨГИЙН НОГООН ЗЭЭЛ ОЛГООД БАЙНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/05/27    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Construction of Oil Refinery at 50 Percent Complete www.montsame.mn

Mongolia is building its first major oil refinery in Altan Shiree soum of Dornogobi aimag with a soft loan worth about USD 1.7 billion from the Export-Import Bank of the Republic of India.
The construction work is being carried out in four phases, and as of today, the project is 50 percent complete. In addition, the crude oil pipeline project is 90 percent complete, reported Executive Director of Mongol Refinery LLC Altantsetseg Dashdavaa. In accordance with the intergovernmental agreement between the two countries, the plant is scheduled to become operational in 2028.  However, due to the government and the Ministry of Industry and Mineral Resources’ efforts to accelerate the construction, it is planned to be commissioned a year ahead of schedule.  
Minister of Industry and Mineral Resources Damdinnyam Gongor said, “During the fuel and oil products crisis, Mongolia relies 95 percent on Russia and 5 percent on China — in other words, we were fully dependent on foreign suppliers. The way out of this dependence is to build a domestic oil refinery. Once the plant becomes operational, Mongolia will be able to meet about 50 percent of its domestic demand for oil products. The main challenge now is securing raw materials. Our ministry is focusing on this issue, and we plan to hold talks with PetroChina to find a solution.”
As of today, construction of the pipeline racks for the primary processing facilities and the foundation concrete work for the furnaces of the atmospheric and vacuum distillation units have been completed. Meanwhile, installation works are continuing on the pipeline racks, substations, and buildings intended for control and server operations within the auxiliary and support facilities.
In addition, officials reported that construction of the storage tank park, pipeline racks, substations, and the foundations for the plant’s power plant control system and substation buildings is underway, with the main structural works nearing completion. The majority of the plant’s technological equipment is being manufactured by nearly 20 companies in India.



Published Date:2025-12-26