1 PARLIAMENT VOTES TO REMOVE SPEAKER UCHRAL, CLEARING PATH TO PRIME MINISTERSHIP WWW.MONTSAME.MN PUBLISHED:2026/03/30      2 MONGOLIA RECEIVES UP TO $1 BILLION IN BIDS FOR BORTEEG COAL DEPOSIT WWW.MONTSAME.MN PUBLISHED:2026/03/30      3 ANNUAL POLITICAL DIALOGUE BETWEEN THE UK AND MONGOLIA: JOINT PRESS STATEMENT WWW.GOV.UK PUBLISHED:2026/03/30      4 COP17 ROADS, SITE, PARKING WORKS REACH 65 PERCENT COMPLETION WWW.MONTSAME.MN PUBLISHED:2026/03/30      5 CITY LAUNCHES BOND TRADING FOR THERMAL POWER PLANT PROJECT WWW.MONTSAME.MN PUBLISHED:2026/03/30      6 PRODUCTION BRANCH OF CHINA'S LARGEST TRUCK MANUFACTURER TO OPEN IN MONGOLIA WWW.AKIPRESS.COM PUBLISHED:2026/03/30      7 INTERNAL PARTY SPLITS FORCE MONGOLIA’S PM TO STEP DOWN WWW.INTELLINEWS.COM PUBLISHED:2026/03/30      8 MONGOLIA PLANS TO PROVIDE FULL MOBILE COVERAGE ACROSS ITS VAST TERRITORY BY 2028 WWW.OPEN.KG PUBLISHED:2026/03/30      9 MPP BACKS UCHRAL FOR PRIME MINISTER WITH 99.7 PERCENT VOTE WWW.MONTSAME.MN PUBLISHED:2026/03/30      10 PRIME MINISTER ZANDANSHATAR GOMBOJAV RESIGNS WWW.MONTSAME.MN PUBLISHED:2026/03/29      Н.НАНДИНХҮСЭЛ WNCAA DIVISION I-Д ТОГЛОХ АНХНЫ МОНГОЛ ТАМИРЧИН БОЛЛОО WWW.ITOIM.MN НИЙТЭЛСЭН:2026/03/30     ДЦС-5 ТӨСЛИЙГ САНХҮҮЖҮҮЛЭХ ₮200 ТЭРБУМЫН БОНДЫГ АРИЛЖААЛАВ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/03/30     “УБТЗ” ХНН: ДӨРӨВДҮГЭЭР САРД КОКСЖСОН ХӨХ НҮҮРСИЙГ ТЭЭВЭРЛЭЖ ДУУСГАНА WWW.EGUUR.MN НИЙТЭЛСЭН:2026/03/30     СЭЛБЭ ГОЛЫН ГАДНА ТОХИЖИЛТЫН АЖЛЫГ ЗУРГАДУГААР САРД ДУУСГАНА ГЭВ WWW.NEWS.MN НИЙТЭЛСЭН:2026/03/30     ОЙРХ ДОРНОДЫН ДАЙН: ДЭЛХИЙД НҮҮРСНИЙ ҮНЭ ӨСӨЖ БАЙХАД МОНГОЛ УЛСЫН АЛДАЖ БУЙ БОЛОМЖ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/03/30     МАН-ЫН ДАРГА Н.УЧРАЛЫГ 99.7 ХУВИЙН САНАЛААР ЕРӨНХИЙ САЙДАД НЭР ДЭВШҮҮЛЭХИЙГ ДЭМЖЛЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/03/29     Г.ЗАНДАНШАТАР: ТӨР ЗОГСОХГҮЙ, БОДЛОГО ТАСАЛДАХГҮЙ, МОНГОЛ УЛС УРАГШИЛСААР БАЙХ ЁСТОЙ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/03/29     Э.ӨГӨӨМӨР: ҮНДСЭН ШУГАМУУДАА ГАЗАР ДООРХ ТУННЕЛИЙН СИСТЕМД ОРУУЛЧИХВАЛ УС ТАСАЛЖ, ГАЗАР УХАХ ШААРДЛАГАГҮЙ БОЛНО WWW.ITOIM.MN НИЙТЭЛСЭН:2026/03/29     БОРТЭЭГИЙН ОРДОД ХӨРӨНГӨ ОРУУЛЖ, ХАМТРАН АЖИЛЛАХААР 1 ТЭРБУМ АМ.ДОЛЛАРЫН САНХҮҮЖИЛТИЙН САНАЛ ИРЛЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/03/29     АҮЭБЯ: ОХУ-ЫН АВТОБЕНЗИНИЙ ЭКСПОРТЫН ХОРИГТ МАНАЙХ ХАМААРАХГҮЙ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/03/29    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

COP17 Roads, Site, Parking Works Reach 65 Percent Completion www.montsame.mn

Representatives of the 17th Conference of the Parties (COP17) to the United Nations Convention to Combat Desertification (UNCCD) are visiting Mongolia for the third time.
 
During the visit, a delegation led by Director of the UNCCD Liaison Office in New York Rajeb Boulharouf reviewed progress at the project site as part of preparations for the COP17 conference. The delegates examined the technical solutions of the conference facilities, room layouts, and planning process, and provided recommendations to ensure compliance with international standards and requirements.

 While working at the project site, Deputy Minister of Environment and Climate Change Munkhtamir Batbayar and Head of the State Protocol Department Odmunkh Enkhbold provided proposals and relevant directives to the National Committee’s Working Office regarding the access areas for high-level delegates and the “Green Zone,” overall organization, and matters to be incorporated into the work plan.

 As of today, connections to the site’s infrastructure have been completed, while road, site, and parking works, which began on March 15, are 65 percent complete. Installation of the main structures is scheduled to be finished by June.

 At the same time, the project contractor emphasized the need to urgently select contractors for landscaping, assembly of conference halls, and equipment installation, and to commence these works simultaneously, urging attention to this matter.