1 TRUMP’S SON WITH KAZAKH TUNGSTEN TIES LOST IN MONGOLIAN MOUNTAINS WWW.KZ.KURSIV.MEDIA PUBLISHED:2026/09/10      2 MONGOLIA TO HOLD PARLIAMENTARY HEARING ON EPSTEIN FILES IN OCTOBER WWW.AZERNEWS.AZ PUBLISHED:2026/09/10      3 MONGOLIA'S FOREIGN TRADE TURNOVER SURGES NEARLY 37 PCT IN FIRST 8 MONTHS WWW.XINHUANET.COM PUBLISHED:2026/09/10      4 MONGOLIA SIGNS MOU WITH BLACKROCK FMA WWW.MONTSAME.MN PUBLISHED:2026/09/10      5 MONGOLIA, UAE SIGN ENERGY COOPERATION MOU WWW.MONTSAME.MN PUBLISHED:2026/09/10      6 SPEAKERS OF MONGOLIA, VIETNAM HOLD OFFICIAL TALKS WWW.MONTSAME.MN PUBLISHED:2026/09/10      7 MONGOLIA AGREES TO PURCHASE 10,000 TONS OF GASOLINE AND 4,000 TONS OF JET FUEL FROM CHINA IN SEPTEMBER WWW.GOGO.MN PUBLISHED:2026/09/10      8 ADB SUPPORTS MONGOLIA'S FIRST GREEN-CERTIFIED RESIDENTIAL COMPLEX BUILT BY THE PRIVATE SECTOR WWW.ADB.ORG PUBLISHED:2026/09/09      9 MONGOLIA FINISHES FOURTH WITH 26 MEDALS AT WORLD NOMAD GAMES WWW.ASIANEWS.NETWORK PUBLISHED:2026/09/09      10 NEW FLIGHT ROUTES EXPLORED WITH HOKKAIDO AIRPORTS WWW.UBPOST.MN PUBLISHED:2026/09/09      ШАТАХУУНЫ НИЙЛҮҮЛЭЛТЭЭ УРТ ХУГАЦААНД ТОГТВОРЖУУЛЖ, ГАЗРЫН ТОС, НҮҮРС-ХИМИЙН ХАМТЫН АЖИЛЛАГААГ ӨРГӨЖҮҮЛНЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/10     ГОЛОМТ БАНК ХАРИЛЦАГЧДЫНХАА ХУДАЛДАА, ТӨЛБӨР ТООЦООГ ДЭМЖИХЭЭР BANK OF CHINA-ТАЙ СТРАТЕГИЙН ХАМТЫН АЖИЛЛАГААГ ЭХЛҮҮЛЛЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/10     АНЭУ-ТАЙ ЭРЧИМ ХҮЧНИЙ САЛБАРТ ХАМТРАН АЖИЛЛАНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/10     МАХ, БЕНЗИНИЙ ҮНИЙН НӨЛӨӨГӨӨР ИНФЛЯЦ 12.5 ХУВЬД ХҮРЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/10     МОНГОЛД ИРЖ БУЙ РИО ТИНТО ГРУППИЙН CEO САЙМОН ТРОТТ ГЭЖ ХЭН БЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/10     Ц.БАТБААТАР: ХАТУУ ЗОХИЦУУЛАЛТТАЙ 38 УЛСААС ОРЖ ИРЖ БАЙГАА ЭМҮҮДИЙГ ХӨНГӨЛӨЛТТЭЙ ЭМИЙН ЖАГСААЛТАД ХАМРУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/10     Н.УЧРАЛ: МИНИЙ ГЭР БҮЛ, АЖИЛ МЭРГЭЖЛИЙН НЭР ХҮНДЭД ХАЛДЛАА WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/10     СЭЛБЭ УХААЛАГ ХОТОД УНДНЫ УСНЫ ЗЭС ХООЛОЙ ШУГАМ УГСАРЧ БАЙНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/09     НАЙМДУГААР САРД ХҮНСНИЙ БҮЛГИЙН БҮТЭЭГДЭХҮҮНИЙ ҮНЭ 21.5 ХУВЬ НЭМЭГДЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/09     ЭРЧИМ ХҮЧНИЙ ҮНЭ НЭМЭХГҮЙН ТУЛД ТӨСӨВТ 200 ТЭРБУМ ТӨГРӨГИЙН ТАТААС ТУСГАЖЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/09    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Ulaanbaatar Cable Car Construction Reaches 85 Percent Completion www.montsame.mn

Construction on the Ulaanbaatar Cable Car transport project, which will connect the capital city's Kharkhorin market area with Yarmag, commenced on March 10, 2025. As of today, the overall project execution stands at 85 percent, according to the Governor's Office of the Capital City.

Under the project being implemented along the Artsat-Unur Khoroolol route, 19 support pillars have been installed, and the construction of two stations is currently underway.

The project is being jointly implemented by specialists from France’s POMA Group, alongside teams from "Monnis Engineering" LLC and "Tsagaan Uran Khiits" LLC. The client's supervision is being carried out by the "Integrated Project Management Department," a local government-owned enterprise, and "Maximal" LLC.

Governor of the Capital City and Mayor of Ulaanbaatar Purevdagva Byaruuzana, accompanied by relevant officials, inspected the G1 cable car station. "The testing of the cable car system will begin on September 19, 2026. Following this, the State Commission will evaluate the project from October 20 to November 20, 2026. The overall project completion is at 85 percent, while the construction of the G1 and G2 stations is about 80 percent complete, proceeding according to schedule," stated Mayor Purevdagva. "A successful single-cabin test was conducted during the National Naadam festival. Each cabin can accommodate 10 passengers and has a carrying capacity of 800 kg. Passengers will be able to travel the 4.2 km route between Yarmag and Kharkhorin in just 11 minutes. A total of 98 such cabins will serve the public. With the commissioning of the cable car system, citizens will experience the most modern culture of public transportation."

The cable car system is equipped with a backup generator that activates automatically in the event of a power outage. Furthermore, it features an emergency mode designed to bring all cabins safely to the stations and evacuate passengers in high-risk situations.

Juan Munier, Site Manager of the Cable Car Transport Project, noted: "Throughout the project's implementation, all stakeholders, the Integrated Project Management Department, 'Monnis Engineering', 'Maximal', and POMA's engineering and technical staff have shared a unified vision. We are working together highly effectively, and it is a great pleasure to collaborate with Mongolian engineers. As stipulated in the contract, we will provide training and maintenance services for three years after the project is commissioned. Starting this week, French experts are conducting rescue operation training for professional organizations."

Chief of Staff of the Rescue Unit of the Ulaanbaatar City Emergency Management Department Tsogtbayar M. added, "As the cable car is a completely new mode of transportation being introduced in our country for the first time, we are organizing high-altitude training exercises to build the capacity of our rescue personnel. Although the risk of an accident on the cable car is low, we are ensuring full readiness and training our rescue teams to access the system and operate safely."


By Enkh-Od.G



Published Date:2026-07-23