1 MONGOLIA'S INTERNATIONAL BOND MARKET: A STRONG 2026, BUT THE NEXT TEST LIES AHEAD WWW.CAPITALMARKETS.MN PUBLISHED:2026/09/22      2 STATE ENTERPRISE LISTINGS PITCHED TO 150 INVESTORS IN LONDON WWW.UBPOST.MN PUBLISHED:2026/09/22      3 MONGOLIAN STOCK MARKET MAIN INDICES SHOW POSITIVE MOVEMENT WWW.MONTSAME.MN PUBLISHED:2026/09/22      4 ARVAIKHEER THERMAL POWER PLANT FUNDING TO BE INCLUDED IN 2027 BUDGET WWW.GOGO.MN PUBLISHED:2026/09/22      5 PRESIDENT U.KHURELSUKH TO MEET WITH MONGOLIANS IN CHICAGO WWW.GOGO.MN PUBLISHED:2026/09/22      6 50 AVIATION PROFESSIONALS TO RECEIVE TRAINING IN CHINA WWW.MONTSAME.MN PUBLISHED:2026/09/21      7 CONTRACT FOR POWER PLANT EXPANSION TO BE CONCLUDED SOON WWW.MONTSAME.MN PUBLISHED:2026/09/21      8 MONGOLIAN FUEL IMPORTER SHUNKHAI OPENS 100 BILLION TUGRIK BOND SALE WWW.STREAMLINEFEED.CO.KE PUBLISHED:2026/09/21      9 PRESIDENT KHURELSUKH UKHNAA DEPARTS TO ATTEND UN GENERAL ASSEMBLY SESSION WWW.MONTSAME.MN PUBLISHED:2026/09/21      10 ADB ALLOCATES $30 MILLION FOR THE DEVELOPMENT OF MONGOLIA'S CASHMERE SECTOR WWW.OPEN.KG PUBLISHED:2026/09/21      АВСТРАЛИЙН ПАРЛАМЕНТЫН ТӨЛӨӨЛӨГЧДИЙН ТАНХИМЫН ДАРГА МОНГОЛД АЛБАН ЁСНЫ АЙЛЧЛАЛ ХИЙХЭЭР ХҮРЭЛЦЭН ИРЛЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/22     НҮҮРС ТЭЭВРИЙН ХАМТЫН АЖИЛЛАГААГ ЭРЧИМЖҮҮЛНЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/22     ХАСБАНК ЕСБХБ-ТАЙ ЗЭЭЛИЙН ЭРСДЭЛ ХУВААЛЦАХ ГЭРЭЭНД ГАРЫН ҮСЭГ ЗУРЛАА WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/22     ЭМЭЭЛТ ЭКО АЖ ҮЙЛДВЭРИЙН ПАРКИЙН ДЦС-ЫН БҮТЭЭН БАЙГУУЛАЛТЫН АЖИЛ ЭХЭЛЛЭЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/21     ЭРЧИМ ХҮЧНИЙ САЙД Б.НАЙДАЛАА: ЭНЭ ӨВӨЛ ДУЛААНЫ ЭРЧИМ ХҮЧ ДУТАГДАНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/21     БОТАНИКИЙН ЦЭЦЭРЛЭГТ ХҮРЭЭЛЭНГИЙН ОРЧИМД БААВГАЙ ОРЖ ИРСЭН МЭДЭЭЛЭЛ БҮРТГЭГДЖЭЭ WWW.EGUUR.MN НИЙТЭЛСЭН:2026/09/21     ИРГЭНИЙ НИСЭХИЙН ДАРГААР Г.БАТБАЯРЫГ ТОМИЛЖЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/21     ЕРӨНХИЙЛӨГЧ У.ХҮРЭЛСҮХ НҮБ-ЫН ЕРӨНХИЙ АССАМБЛЕЙН ЧУУЛГАНД ОРОЛЦОХООР ЭХ ОРНООСОО МОРДЛОО WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/21     МОНГОЛЫН ИРГЭНИЙ НИСЭХИЙН 50 МЭРГЭЖИЛТНИЙГ БНХАУ-Д СУРГАХААР БОЛЖЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/21     АРВАЙХЭЭРИЙН ДУЛААНЫ СТАНЦЫН БҮТЭЭН БАЙГУУЛАЛТЫГ ЭРЧИМЖҮҮЛНЭ WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/21    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Arvaikheer Thermal Power Plant funding to be included in 2027 budget www.gogo.mn

On September 10, Prime Minister N.Uchral visited Uvurkhangai province, where the Government has decided to secure funding for the Arvaikheer Thermal Power Plant through the 2027 state budget and accelerate its completion under a public-private partnership.

The project is currently 45% complete, although construction had come to a complete standstill over the past year.

The Government plans to use dividends received from the Oyu Tolgoi project to fully complete thermal power plants in nine provinces.

Regarding the financing of Thermal Power Plant No. 6 in Ulaanbaatar, 30% of the project cost will be covered by the state budget, including Oyu Tolgoi dividend revenues, while the remaining 70% will be financed by the private sector.

Prime Minister N.Uchral said that energy-sector challenges would be addressed comprehensively once the 2027 state budget is approved. He also noted that construction of the Arkhangai Thermal Power Plant has not yet begun and therefore the project will be implemented through a public-private partnership.

For the first time, the Government has announced an open auction for renewable energy projects in five provinces. Private-sector companies are working to commission battery energy storage systems and solar power plants in December, ahead of the upcoming winter peak demand period.

Local authorities reported that a 50 MW solar power plant in Kharkhorin, Uvurkhangai province, is currently 45% complete.

The Prime Minister emphasized that the 2026 state budget amendment and the 2027 budget framework submitted by the Government to Parliament are intended to advance major development projects, deliver tangible results, and address the country’s energy-sector challenges.



Published Date:2026-09-22