1 FOREIGN TRADE TURNOVER REACHES USD 2.6 BILLION WWW.MONTSAME.MN PUBLISHED:2026/02/25      2 MONGOLIA REVOKES PERMITS OF SIX FOREIGN NGOS WWW.MONTSAME.MN PUBLISHED:2026/02/25      3 MINING DRIVES MONGOLIA’S ECONOMY AS REFORM MOMENTUM BUILDS WWW.EASTASIAFORUM.ORG PUBLISHED:2026/02/25      4 P.NARANBAYAR ANNOUNCES PLAN TO DRAFT LAW TO RESTRICT CHILDREN’S USE OF SOCIAL NETWORKS WWW.GOGO.MN PUBLISHED:2026/02/25      5 “EAGLE FESTIVAL-2026” TO BE HELD ON MARCH 7-8 WWW.GOGO.MN PUBLISHED:2026/02/24      6 BEATE DASTEL: UNICEF WILL CONTINUE THE IMPLEMENTATION OF SUCCESSFUL PROJECTS AND PROGRAMS IN MONGOLIA WWW.OPEN.KG PUBLISHED:2026/02/24      7 SAXAUL TREE CULTIVATED IN WINTER GREENHOUSE FOR FIRST TIME IN MONGOLIA WWW.MONTSAME.MN PUBLISHED:2026/02/24      8 MONGOLIA'S PROPOSED SENIOR UNSECURED NOTES ASSIGNED 'BB-' LONG-TERM FOREIGN CURRENCY RATING WWW.SPGLOBAL.COM PUBLISHED:2026/02/24      9 MOODY’S ASSIGNS B1 RATING TO MONGOLIA BONDS ON REFINANCING PLAN WWW.IN.INVESTING.COM PUBLISHED:2026/02/24      10 THE 2250-KM, MORE DIVERSE ALTERNATIVE TO THE TRANS-SIBERIAN RAILWAY WWW.BRISBANETIMES.COM.AU PUBLISHED:2026/02/24      НИЙСЛЭЛ ЗАРДЛАА ТЭЛЖ, ТРАМВАЙН ТӨСӨЛД 350 ТЭРБУМЫГ ЗАРЦУУЛНА WWW.NEWS.MN НИЙТЭЛСЭН:2026/02/25     САНГИЙТ КАУР ДЕО: МАЛАЙЗЫН ТӨР БУРУУТАЙ ГЭДГИЙГ ШИЙДҮҮЛЭХ ЭЦСИЙН БОЛОМЖ УЧРААС МОНГОЛЫН ТӨР ХАМТРАН АЖИЛЛАХЫГ ХҮСЭЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/02/25     НИЙСЛЭЛИЙН ТӨСӨВ: COP17 ХУРАЛД 70 ТЭРБУМ ЗАРЦУУЛЖ, 200 ТЭРБУМЫН БОНД БОСГОЖ V ЦАХИЛГААН СТАНЦ БАРИНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/02/25     ХӨРСНИЙ УС, ҮЕРИЙН ХАМГААЛАЛТЫН ТӨСЛИЙН ТЭЗҮ-ИЙГ БОЛОВСРУУЛАХ АЖИЛ 90 ХУВЬТАЙ ХЭРЭГЖИЖ БАЙНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/02/24     COP17 БАГА ХУРЛЫН БЭЛТГЭЛ ХАНГАХ ХҮРЭЭНД ТЕНДЕРГҮЙ, ШУУД ХУДАЛДАН АВАЛТ ХИЙХ ЭРХИЙГ ӨГЧЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/02/24     "ЭРДЭНЭБҮРЭНГИЙН УСАН ЦАХИЛГААН СТАНЦЫН АЖЛЫН ЯВЦ 20 ХУВЬТАЙ БАЙНА" WWW.EGUUR.MN НИЙТЭЛСЭН:2026/02/24     ТӨМӨР ЗАМЫН ТЕРМИНАЛЫН ДЭД БҮТЦИЙГ САНХҮҮЖҮҮЛЭХ САНАЛ ТАВЬЖЭЭ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/02/24     НИЙСЛЭЛД ЖИЛДЭЭ 44.420 ТОНН ХУВАНЦАРЫГ ДАХИН БОЛОВСРУУЛНА WWW.EGUUR.MN НИЙТЭЛСЭН:2026/02/24     МОНГОЛ УЛС, БНСУ-ЫН ГХЯ ХООРОНДЫН СТРАТЕГИЙН УУЛЗАЛТ БОЛОВ WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/02/24     ДҮҮЖИН ЗАМЫН ТЭЭВЭР ТӨСЛИЙН ЯВЦ 60.5 ХУВЬТАЙ БАЙНА WWW.NEWS.MN НИЙТЭЛСЭН:2026/02/24    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Turquoise Hill announces second quarter 2018 production and completion of Shaft 5 www.gogo.mn

Turquoise Hill Resources today announced second quarter 2018 production for Oyu Tolgoi as well as the completion of Shaft 5.

Luke Colton, interim Chief Executive Officer of Turquoise Hill, said, “During the second quarter, Oyu Tolgoi continued processing Phase 4A ore resulting in improved gold grades, production and recovery.

This trend is expected for the remainder of the year. Mill throughput during the quarter benefited from high intensity blasting, which was introduced in 2017.

Oyu Tolgoi continues to make good underground development progress, as evidenced by the completion of Shaft 5.” Mill throughput increased 6.3% over Q1’18 due to higher utilization rates and the positive impact of high intensity blasting.

Copper production in Q2’18 increased 1.5% over Q1’18 as a result of higher mill utilization rates offset by slightly lower grades from the depletion of Phase 6 ore. Gold production increased 19.0% over Q1’18 due to stronger mill utilization rates, higher grades from Phase 4A and increased recovery. Sales in Q2’18 benefited from improved logistics as inventory accumulated during the Q1’18 force majeure worked its way through the system.

Oyu Tolgoi is expected to produce 125,000 to 155,000 tonnes of copper and 240,000 to 280,000 ounces of gold in concentrates for 2018. Due to the positive impact of high intensity blasting, mill throughput for 2018 is expected to be approximately 40 million tonnes.



Published Date:2018-07-18