1 TRUMP’S SON WITH KAZAKH TUNGSTEN TIES LOST IN MONGOLIAN MOUNTAINS WWW.KZ.KURSIV.MEDIA PUBLISHED:2026/09/10      2 MONGOLIA TO HOLD PARLIAMENTARY HEARING ON EPSTEIN FILES IN OCTOBER WWW.AZERNEWS.AZ PUBLISHED:2026/09/10      3 MONGOLIA'S FOREIGN TRADE TURNOVER SURGES NEARLY 37 PCT IN FIRST 8 MONTHS WWW.XINHUANET.COM PUBLISHED:2026/09/10      4 MONGOLIA SIGNS MOU WITH BLACKROCK FMA WWW.MONTSAME.MN PUBLISHED:2026/09/10      5 MONGOLIA, UAE SIGN ENERGY COOPERATION MOU WWW.MONTSAME.MN PUBLISHED:2026/09/10      6 SPEAKERS OF MONGOLIA, VIETNAM HOLD OFFICIAL TALKS WWW.MONTSAME.MN PUBLISHED:2026/09/10      7 MONGOLIA AGREES TO PURCHASE 10,000 TONS OF GASOLINE AND 4,000 TONS OF JET FUEL FROM CHINA IN SEPTEMBER WWW.GOGO.MN PUBLISHED:2026/09/10      8 ADB SUPPORTS MONGOLIA'S FIRST GREEN-CERTIFIED RESIDENTIAL COMPLEX BUILT BY THE PRIVATE SECTOR WWW.ADB.ORG PUBLISHED:2026/09/09      9 MONGOLIA FINISHES FOURTH WITH 26 MEDALS AT WORLD NOMAD GAMES WWW.ASIANEWS.NETWORK PUBLISHED:2026/09/09      10 NEW FLIGHT ROUTES EXPLORED WITH HOKKAIDO AIRPORTS WWW.UBPOST.MN PUBLISHED:2026/09/09      ШАТАХУУНЫ НИЙЛҮҮЛЭЛТЭЭ УРТ ХУГАЦААНД ТОГТВОРЖУУЛЖ, ГАЗРЫН ТОС, НҮҮРС-ХИМИЙН ХАМТЫН АЖИЛЛАГААГ ӨРГӨЖҮҮЛНЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/10     ГОЛОМТ БАНК ХАРИЛЦАГЧДЫНХАА ХУДАЛДАА, ТӨЛБӨР ТООЦООГ ДЭМЖИХЭЭР BANK OF CHINA-ТАЙ СТРАТЕГИЙН ХАМТЫН АЖИЛЛАГААГ ЭХЛҮҮЛЛЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/10     АНЭУ-ТАЙ ЭРЧИМ ХҮЧНИЙ САЛБАРТ ХАМТРАН АЖИЛЛАНА WWW.MONTSAME.MN НИЙТЭЛСЭН:2026/09/10     МАХ, БЕНЗИНИЙ ҮНИЙН НӨЛӨӨГӨӨР ИНФЛЯЦ 12.5 ХУВЬД ХҮРЛЭЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/10     МОНГОЛД ИРЖ БУЙ РИО ТИНТО ГРУППИЙН CEO САЙМОН ТРОТТ ГЭЖ ХЭН БЭ WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/10     Ц.БАТБААТАР: ХАТУУ ЗОХИЦУУЛАЛТТАЙ 38 УЛСААС ОРЖ ИРЖ БАЙГАА ЭМҮҮДИЙГ ХӨНГӨЛӨЛТТЭЙ ЭМИЙН ЖАГСААЛТАД ХАМРУУЛНА WWW.ITOIM.MN НИЙТЭЛСЭН:2026/09/10     Н.УЧРАЛ: МИНИЙ ГЭР БҮЛ, АЖИЛ МЭРГЭЖЛИЙН НЭР ХҮНДЭД ХАЛДЛАА WWW.NEWS.MN НИЙТЭЛСЭН:2026/09/10     СЭЛБЭ УХААЛАГ ХОТОД УНДНЫ УСНЫ ЗЭС ХООЛОЙ ШУГАМ УГСАРЧ БАЙНА WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/09     НАЙМДУГААР САРД ХҮНСНИЙ БҮЛГИЙН БҮТЭЭГДЭХҮҮНИЙ ҮНЭ 21.5 ХУВЬ НЭМЭГДЖЭЭ WWW.EAGLE.MN НИЙТЭЛСЭН:2026/09/09     ЭРЧИМ ХҮЧНИЙ ҮНЭ НЭМЭХГҮЙН ТУЛД ТӨСӨВТ 200 ТЭРБУМ ТӨГРӨГИЙН ТАТААС ТУСГАЖЭЭ WWW.GOGO.MN НИЙТЭЛСЭН:2026/09/09    
Англи амин дэм Монгол улсад албан ёсоор бүртгэгдлээ.

Ivanhoe Electric’s assessment for Santa Cruz project details new source of ‘green’ copper in US www.mining.com

Ivanhoe Electric (TSX: IE) has released the results of an initial assessment (IA) analyzing the potential for an underground copper mine at its Santa Cruz project located west of Casa Grande, Arizona, powered predominantly by renewable energy.
The IA, which is preliminary in nature, envisions a 5.9-million-tonne-per-year copper mining operation with an estimated 20-year life. Life of mine (LOM) copper production is calculated at 1.6 million tonnes with average grade of 1.58% total copper (1 million tonnes will be in the form of 99% pure copper cathode, the rest being copper contained in a 48% copper concentrate).
The study focuses exclusively on the high-grade exotic, oxide and enriched domains of the Santa Cruz and East Ridge deposits, with combined resources of 2.7 million tonnes indicated grading 1.42% total copper and 27.3 million tonnes inferred grading 1.39% total copper.
However, there is potential for resource upgrades from the oxide domains of the Texaco deposit (900,000 tonnes indicated grading 1.05% total copper and 35 million tonnes inferred grading 1.06% total copper), and from the large primary sulfide domains at Santa Cruz (76.2 million tonnes indicated grading 0.88% total copper and 8 million tonnes inferred grading 0.92% total copper).
Copper recoveries of 95.4% are expected to be achieved through a combination of solvent extraction and electrowinning (SX/EW) and conventional froth flotation, as outlined by the IA.
On the project economics side, the IA projects Santa Cruz to have an after-tax net present value of $1.3 billion with an after-tax internal rate of return of 23%, using an 8% discount rate and an LOM copper price of $3.80/lb.
The study also estimates initial project capital expenditures of $1.15 billion and LOM sustaining capital expenditures of $980 million. A three-year construction period is contemplated to develop the underground workings and build the surface processing facilities.
Ivanhoe noted that the IA is designed to minimize environmental impact and minimize surface land disruption. As a result of the small surface footprint required for mining activities, the area expected to be required for the project would cover approximately one-third of the total land package, it says.
As a primarily “green” copper mine operation, the IA base case assumes 70% of the total electric power requirements for the project will be generated by onsite renewable infrastructure, enabling copper production with low carbon dioxide equivalent (CO2e) emissions (0.49 tonnes per tonne of copper produced for Scope 1 and 2 emissions). In comparison, the global mining industry average is approximately 3.9 tonnes of CO2e, Ivanhoe said.
Robert Friedland, executive chairman of Ivanhoe, says completion of the IA for the Santa Cruz copper project is an “important achievement” for the company as it works to advance a new source of responsibly produced ‘green’ copper in the United States.
“Our goal is to develop a modern copper mine that produces copper with among the lowest levels of carbon dioxide output in the industry; a product we think has the potential to attract a premium price in the future,” Friedland said in Wednesday’s news release.
“We believe the Santa Cruz copper project will become an industry-leading example of responsibly produced copper in the United States, and a source of high-quality jobs in Arizona during development and throughout its anticipated long mine life,” CEO Taylor Melvin added.
Shares of Ivanhoe Electric gained 1.1% by 12:50 p.m. EDT, giving the company a market capitalization of C$2.2 billion ($1.6 billion).


Published Date:2023-09-07