Ulaanbaatar to Install 11.7 km of Storm Drains at 19 Sites www.montsame.mn
This year, the Geodesy, Water, and Construction Facilities Authority Municipality-Owned Enterprise will install 11.7 kilometers of road stormwater drainage networks at 19 locations in the capital city, funded by the Ulaanbaatar city budget.
According to the Governor’s Office of the Capital City of Ulaanbaatar, as part of works at the Selbe and Sharkhad sub-centers, 7.2 kilometers of groundwater drainage networks will be installed at two locations. The following works are also planned:
· In the territory of Khoroos 13 and 14 of Sukhbaatar district, construction will begin on a five-tier water reservoir system with a capacity of 1.3 million cubic meters, covering a 21.7-hectare floodplain area, to store floodwaters of the Selbe river.
· At 28 locations, 48,000 cubic meters of silt and sediment will be removed from flood protection facilities to ensure normal operation of flood channels.
· Cleaning works will be carried out on 4,034 catch basins and 4,171 inspection manholes along 217 kilometers of road, stormwater, and groundwater drainage networks across six districts of the capital.
Published Date:2026-01-09