The feasibility study and an expert review for the Sludge Processing Plant project have been completed, with the next stages of the project under preparation.
As part of the 24 megaprojects aimed at developing Ulaanbaatar city, the sludge incineration and energy generation project is planned to be implemented in the Khoroo No. 20 of Songinokhairkhan district.
The facility will have the capacity to process an average of 250 cubic meters of sludge per day and incinerate up to 238 tons of sludge. It is expected to recycle approximately 843,200 cubic meters of sludge annually, with emissions generated during the incineration process, such as smoke and gas, planned to be filtered through a high-tech air purification system. In addition to sludge processing and disposal, the project is significant in its contributions to reducing soil and water pollution, eliminating unpleasant odor sources, energy generation, and waste recycling.
The total area of the project site is approximately 40,000 square meters. The sludge incineration plant is planned to be constructed in front of the Ulaanbaatar Central Wastewater Treatment Facility.
Published Date:2025-08-08